P15PS01390
x x
4 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
GOGA 14995207/23/2015000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/12/2015
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Golden Gate National Recreation Area, Alcatraz Island (Building 68) - GOGA 149952
Project Title: Stabilize and Repair the Exterior Walls of the Cellhouse for
Visitor/Resource Protection
The purpose of this Amendment Number 0001 is to revise/clarify when the Government may exercise the Optional Bid Items, update the Davis Bacon Wage Rate, add Specification
Sections for 2A and 2B, provide pre-bid meeting documents, and provide questions and answers received as of July 23, 2014.
See the following Page(s)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
David E. Thomas
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Number: P15PS01390 Amend #0001 GOGA 149952, Stabilize and Repair the Exterior Walls Page 2 of 2
a. Request for Proposal (RFP), Section B and Proposal Submission Package, Volume II: Replace the Contract Price Schedules. This change adds the following sentence:
If 2A Options, 1 through 4, are not exercised at time of initial award, they or any 2B Options will only be exercised if the 2B Base is exercised and the contract completion date is extended 365 calendar days.
b. RFP, Section J, Replace page with the attached Amendment 0001, Section J. This changes Item
3. Davis Bacon Wage Rate, as follows:
FROM:
3. Davis Bacon Wage Rate, General Decision Number: CA150029 06/19/2015 CA29
TO:
3. Davis Bacon Wage Rate, General Decision Number: CA150029 07/172015 CA29
The updated Davis Bacon Wage Rate is attached.
c. Specifications Phase 2A insert the attached Specifications Section, Definitions of Bid Items
d. Specifications Phase 2B insert the attached Specifications Section, Definitions of Bid Items
e. See attached Presentation Slides for the pre-bid meeting which was held on July 15, 2015.
f. See attached Attendance Record for the pre-bid meeting held on July 15, 2015.
g. See Attached Spreadsheet for Questions and Answers as of July 23, 2015.
h. All other terms and conditions remain unchanged.