P09 Corrected OR_ARCH_A-003 - PHASING AND INFECTION CONTROL PLAN - 1 Page.pdf

PDF 179 KB Posted

Attached to
Z2DA--Construct Surgical Suite Addition P/N: 657-501 Federal contract opportunity
Solicitation number
36C25520R0040-0001
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15

About this file

This document contains a phasing and infection control plan for a surgical suite addition project at the Marion VA Medical Center in Marion, Illinois. The plan outlines construction barriers, traffic control measures, cleaning requirements, and other infection control protocols to be followed during the project. Negative air machines with HEPA filtration will be used to exhaust air from construction areas out perimeter windows. At entrances to construction zones, contractors shall provide an ante room with solid wall, door, and door closer, as well as graduated air pressure monitor, tacky mats, HEPA vac, and waste bin. Phasing shall include containment barriers, temporary partitions, and negative air ventilation as indicated. The contractor will be responsible for coordinating related infection control and risk assessment documentation with the VA Contracting Officer's Representative.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Construct Surgical Suite Addition P/N: 657-501, newest first.
File Type Posted
P09 Corrected OR_ARCH_A-501 - PARTITION TYPE DETAILS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-601 - DOOR SCHEDULE DOOR ELEVATIONS AND DETAILS - 1 page.pdf PDF
P09 Corrected OR_ARCH_A-101 - SECOND FLOOR OVERALL RENOVATION PLAN - 1 page.pdf PDF
P09 Corrected OR_ARCH_A-001 - ARCHITECTURAL NOTES ABBREVIATIONS AND SYMBOLS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-301 - BUILDING SECTIONS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_AC103 - Bldg 2 2nd FLOOR AREA B REFLECTED CEILING PLAN - 1 page.pdf PDF
P09 Corrected OR_ARCH_A-502 - GENERAL DETAILS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-202 - EXTERIOR BUILDING ELEVATIONS - 1 Page.pdf PDF
S06 36C25520R0040 0001.docx DOCX document
P09 Corrected OR_ARCH_A-104 - BLDG 38 SECOND FLOOR RENOVATION PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_LS101 - LIFE SAFETY FLOOR PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_AC102 - BLDG 2 2nd FLOOR AREA A REFLECTED CEILING PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_AC101 - SECOND FLOOR REFLECTED CEILING PLAN - 1 page.pdf PDF
P09 Corrected OR_ARCH_A-105 - ROOF PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_LS112 - LIFE SAFETY - ACCESSIBILITY GUIDELINES - 1 Page.pdf PDF
P09 Corrected OR_ARCH_G-001 - COVER - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-102 - BLDG 02 2ND FLOOR AREA A RENOVATION PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-103 - BLDG 02 2ND FLOOR AREA B RENOVATION PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_LS111 - LIFE SAFETY - ACCESSIBILITY GUIDELINES - 1 page.pdf PDF
P09 Corrected OR_ARCH_A-201 - EXTERIOR BUILDING ELEVATIONS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_AD101 - SECOND FLOOR DEMOLITION PLAN - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-002 - SECOND FLOOR EXISTING PLAN - 1 page.pdf PDF
P09 Corrected OR_ARCH_G-002 - DRAWING INDEX AND PROJECT INFORMATION - 1 Page.pdf PDF
P09 Corrected OR_ARCH_A-401 - ENLARGED PLANS - 1 Page.pdf PDF
P09 Corrected OR_ARCH_AC104 - BLDG 38 2ND FLOOR REFLECTED CEILING PLAN - 1 Page.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

A-301

A-301

STAIR

S2-02

CARE STATION

CORRIDOR

C206-02

PACU

CLEAN SUPPLY

PRE/POST

PRE/POST

CORRIDOR

C204-02

CORRIDOR

C207-02

SOILED HOLDING

MEDS

HAC

STERILE CORE

OR

ALCOVE

C207-02A

CORRIDOR

C204-2

CORRIDOR

205-02

OR

CORRIDOR

C201-02

EQUIPMENT

CORRIDOR

C202-02

CORRIDOR

C203-02

STORAGE

259 STAIR

S1-02

WAITING

ELECTRICAL

CHASE

CORRIDOR

C201-38

STAFF LOUNGE

SOILED

ELECTRICAL

HAC

CORRIDOR

C203-38

STAFF TOILET

STAFF TOILET

WOMEN'S

LOCKER

MEN'S LOCKER

CHASE

ELEVATOR

SHAFT

ELEVATOR 2

C207-02B

ELEVATOR 1

C207-02C

PAMN

C207-02FFIBER OPTIC

LOGISTICS

PAGING

EQUIPMENT

C207-02G

WHEELCHAIR

ALCOVE

C3

SOILED UTILITY

ELEC.

CORRIDOR

C2 ELEVATOR

LOBBY

C1

STRESS LAB

B U

IL

D

IN

G

B U

IL

D

IN

G

B U

IL

D

IN

G

B U

IL

D

IN

G

B U

IL

D

IN

G

B

U

IL

D

IN

G

B U

IL

D

IN

G

B

U

IL

D

IN

G

A-102

A-103

A-104

CONSTRUCTION FOOTPRINT. PROVIDE

CONTAINMENT BARRIERS AND ILSM MEASURES

ANTE ROOM WITH SOLID WALL, DOOR, AND DOOR

CLOSER. OUTSIDE: PROVIDE GRADUATED AIR

PRESSURE MONITOR. INSIDE: PROVIDE TACKY

MATS, HEPA VAC, AND WASTE BIN. MINIMUM SIZE

OF ANTE ROOM SHALL BE 5'-0" x 7'-0"

NEGATIVE AIR VENTILATION MACHINES WITH HEPA

FILTRATION EXHAUSTING OUT PERIMETER

WINDOWS TO EXTERIOR. TYPICAL. CONFIRM

REQUIRED NUMBER WITH VA COR.

SCRUB STATION

247A

ALCOVE

249A

SCRUB STATION

249B

SCRUB STATION

250A

CHASE

C202-57

PRE/POST

PACU

PACU

ALCOVE

C206-02A

ISOLATION

ANTE

DICTATION

TOILET

TOILET

STAFF TOILET

ANESTHESIA

IMMED. STER.

BIO-MED

TOILET

TOILET

N. MANAGER

OFFICE

CONSULTATION

RECEPTION

PSA OFFICE

CHASE

PRE/POST

PRE/POST

PRE/POST

PRE/POST

OR

CORRIDOR

C208-02

A-502

OFFICE

ELEVATOR

LOBBY

C202-38

D N

CONTRACTOR TO DESIGNATE

(1) WINDOW FOR TRASH

CHUTE. SEE PHASING

GENERAL NOTE 7.

LEGEND

CONST. FOOTPRINT WITH CONTAINMENT

BARRIERS AND ILSM MEASURES

TEMPORARY CONST. PARTITION. RE:

PARTITION TYPES

NEGATIVE AIR MACHINE EXHAUSTING TO THE

OUTSIDE.

LIFE SAFETY LEGEND:

NEW 2-HR FIRE BARRIER

EXISTING 2-HR FIRE/SMOKE BARRIER

NEW SMOKE PARTITION

EXIT SIGN

TRAVEL DISTANCE

FIRE EXTINGUISHER CABINET

E

F.E.C.

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg. of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

THE ROOM NUMBERING SEQUENCE IS FOR

CONSTRUCTION IDENTIFICATION ONLY. FINAL ROOM

NUMBERING SHALL BE CORRELATED WITH CURRENT

BAS IDENTIFICATION POINTS THAT ARE NOT BEING USED

DUE TO DEMOLITION. FINAL ROOM NUMBERING AND

SIGNAGE SHALL EB APPROVED BY VA STAFF ON

SITE

N

T

C E

I L

TA

S SHEILA

001-016606

CD A R

S E

LYNN

T C

H I

T E

ILOF I L

E NO

I S

EXPIRES 11-30-20

HENSLEY

BAYSINGER

/1

/2

:0

:4

P

M

A-003

PHASING AND INFECTION CONTROL

PLAN

3 28ZC

RELOCATE AND UPGRADE

OPERATING SUITES -

MARION, IL

MARION VAMC

MARION, IL 62959

11/13/2019

BID DOCUMENTS

657-501

2, 38

MM

1/8" = 1'-0"

SECOND FLOOR OVERALL PHASING AND INFECTION CONTROL PLAN

N

AREA OF WORK

SCOPE OUTLINE

KEY PLAN

SCALE: NO SCALE

2A 2B N

CONSTRUCTION BARRIERS: CONSTRUCTION AREA

TO BE SEPARATED FROM OTHER AREAS BY FIRE

RESISTIVE BARRIERS THAT KEEP THE DIRT AND

DUST INSIDE THE WORKSITE AND PROVIDE A

COMPLETE SEAL OF THE CONSTRUCTION AREA

FROM ADJACENT AREAS. THE BARRIER IS TO BE

CONSTRUCTED OF RIGID CONSTRUCTION. WALLS

MUST BE DUSTPROOF WITH AIRTIGHT SEALS

MAINTAINED AT THE FULL PERIMETER OF THE WALLS

AS WELL AS ALL PENETRATIONS. ALL AIR VENTS

MUST BE SEALED OFF NEAR THE CONSTRUCTION

AREA AS REQUIRED AFTER COORDINATION WITH

COR TO ENSURE NON-INTERFERENCE WITH HVAC

AND NEGATIVE PRESSURE SYSTEMS. DUST TO BE

CONTROLLED WITHIN THE WORK SITE FROM FLOOR

TO DECK.

TRAFFIC CONTROL: DESIGNATED ENTRY AND EXIT

PROCEDURES WILL BE DEFINED AND CLEARLY

ARTICULATED WITH CONSTRUCTION SIGNAGE TO BE

PROVIDED BY THE CONTRACTOR. ALL EGRESS WAYS

MUST BE MAINTAINED FREE OF DEBRIS AT ALL

TIMES. THEY MUST BE UTILIZED AT SCHEDULED

TIMES ONLY AS COORDINATED WITH COR. DUST

MATS MUST BE PLACED AT ENTRANCES/EXITS OF

WORK AREA AND REPLACED DAILY OR MORE

FREQUENTLY IF NECESSARY. DEBRIS WHEN

TRANSPORTED THROUGH HOSPITAL AREAS MUST BE

COMPLETELY COVERD TO CONTAIN DUST DURING

TRANSPORT. DEBRIS SHALL BE REMOVED IN

EVENINGS OR NON-DUTY TIMES IF POSSIBLE. ALL

CART WHEELS MUST BE CLEANED BEFORE LEAVING

THE CONSTRUCTION AREA.

CLEANING: THE CONSTRUCTION ZONE AND

ADJACENT ENTRY AREA SHALL BE MAINTAINED IN A

CLEAN AND SANITARY MANNER BY THE

CONTRACTOR AND WILL BE HIGH EFFICIENCY

PARTICULATE AIR (HEPA) VACUUMED AND WET

MOPPED DAILY OR MORE FREQUENTLY AS NEEDED

TO MINIMIZE DUST GENERATION. CLOTHING SHALL

BE FREE OF LOOSE SOIL AND DEBRIS UPON EXITING

THE CONSTRUCTION ZONE. PROVIDE PERSONAL

PROTECTIVE EQUIPMENT, INCLUDING FACE SHIELDS,

GLOVES, AND N95 RESPIRATORS REQUIRED BY THE

SAFETY SPECIFICATION.

INFECTION CONTROL CONSTRUCTION PERMIT:

CONTRACTOR SHALL APPLY FOR AND ASSIST VA

COR THROUGH THE REQUIRED INFECTION CONTROL

CONSTRUCTION PERMIT.

STAGING AREAS WILL BE DESIGNATED BY THE COR.

CONTRACTOR TO COORDINATE WITH THE COR

PRIOR TO CONSTRUCTON.

CONTAINMENT BARRIERS, ILSM, AND ICRA

ENCLOSURES HAVE BEEN SHOWN FOR REFERENCE

ONLY. THE CONTRACTOR SHALL COORDINATE WITH

RISK ASSESSMENT DOCUMENTATION AND THE COR

PRIOR TO IMPLEMENTATION.

AT THE ENTRANCE TO EACH CONSTRUCTION AREA,

WHETHER INDICATED OR NOT, CONTRACTOR SHALL

PROVIDE AN ANTE ROOM WITH A SOLID WALL, DOOR,

AND DOOR CLOSER. OUTSIDE SHALL INCLUDE A

GRADUATED AIR PRESSURE MONITOR. INSIDE SHALL

INCLUDE TACKY MATS, HEPA VAC, AND WASTE BIN.

MINIMUM SIZE OF ANTE ROOM SHALL BE 5'-0" x 7'-0".

THE GENERAL CONTRACTOR IS RESPONSIBLE FOR

ENSURING THAT ALL SUBCONTRACTORS ARE

FAMILIAR WITH THESE NOTES AND THE

REQUIREMENTS IDENTIFED IN THE DIVISION 1

SPECIFICATION “GENERAL CONDITIONS.”

WHEN WORKING IN OCCUPIED AREAS OF THE

MEDICAL CENTER, THE CONTRACTOR CANNOT

LEAVE TOOLS, EQUIPMENT, LADDERS, ETC.,

UNATTENDED AT ANY TIME. THE CONTRACTOR

CANNOT LEAVE CEILING AREA, INCLUDING CEILING

TILES AND CEILING ACCESS PANELS, UNATTENDED

AT ANY TIME.

UTILITY WORK THAT WILL REQUIRE A SHUTDOWN

OF EXISTING SERVICE SHALL BE DONE AT TIMES

OTHER THAN NORMAL WORKING HOURS AT NO

ADDITIONAL COST TO THE GOVERNMENT. WORK

MUST BE SCHEDULED WITH THE COR.

HEAVY NOISE AND VIBRATION PRODUCING WORK IS

TO BE COMPLETED OUTSIDE NORMAL WORKING

HOURS, UNLES NOTED OTHERWISE. WORK MUST BE

SCHEDULED WITH THE VA COR.

COORDINATE ALL WORK WITH OTHER TRADES AND

EXISTING CONDITIONS TO ELIMINATE CONFLICTS

AND/OR INTERFERENCES.

REFER TO EXISTING CONDITIONS DRAWINGS FOR

WORK IN AREAS OUTSIDE THE CONTSTRUCTION

FOOTPRINT(S). THE MAJORITY OF THESE AREAS

WILL BE OCCUPIED AND WILL REQUIRE WORK TO BE

COMPLETED AT TIMES OTHER THAN NORMAL

WORKING HOURS, UNLESS NOTED OTHERWISE.

CONTRACTOR WILL BE RESPONSIBLE FOR

PROVIDING CONTAINMENT BARRIERS, ILSM

MEASURES AND TEMPORARY CONSTRUCTION

PARTITIONS AS REQUIRED.

CONTRACTOR SHALL REMOVE AND REINSTALL OR

REPLACE WINDOW AT KITCHEN AREA USED FOR

TRASH CHUTE.

COORDINATE FINAL PHASING SEQUENCE WITH THE

VA COR PRIOR TO START OF CONSTRUCTION.

IN AREAS WHERE CONSTRUCTION ACTIVITIES

EXPOSE THE BUILDING INTERIOR TO THE EXTERIOR

ENVIRONMENT, CONTRACTOR SHALL CONSTRUCT

TEMPORARY BARRIERS AND WEATHERPROOF

ENCLOSRUES AS REQUIRED TO MEET INFECTION

CONTROL REQUIREMENTS AND PROTECT THE

BUILIDNG INTERIOR (FINISHES, BUILDING SYSTEMS,

ETC.) FROM DAMAGE.

THE VA RESERVES THE RIGHT TO START AND STOP

WORK BETWEEN PHASES AS REQUIRED TO

RELOCATE STAFF AND PATIENTS AND OBTAIN

NECESSARY CLEARANCES. THE CONTRACTOR

SHALL ALLOW TEN (10) DAYS BETWEEN EACH

PHASE FOR THESE ACTIVITIES. CONTRACTOR SHALL

NOT RECEIVE ADDITIONAL COMPENSATION FOR

THESE PERIODS.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

PHASING

GENERAL NOTES

1.

2.

3.

4.

5.

6.

7.

INFECTION CONTROL

GENERAL NOTES

File details come from the government source that posted it. Updated .