This is a Questions and Answers (Q&A) document from a Request for Information (RFI) focused on electrical systems.
The document addresses a single question regarding the availability of existing electrical system drawings. In response, the government commits to posting original construction electrical drawings (numbered 9-E-13, 9-E-16, 9-E-19, 9-E-21, and 9-E-64) to SAM.gov prior to February 6th. Additionally, drawing indexes for both Phase I and Phase II original construction will be posted to the same platform by the same deadline. The response indicates that bidders may request additional drawings beyond those initially provided; such requests should reference the drawing indexes, and the government will provide identified drawings upon request. This Q&A does not address specific products or services, pricing, award dates, or other substantive contract terms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Questions - Communication and IT.pdf | ||
| BOC Public Meeting Space Industry Final.pptx | PPTX presentation | |
| RFI Questions - Procurement .pdf | ||
| Reference Drawings.zip | ZIP file | |
| RFI Questions - Architectural and interior.pdf | ||
| RFI Questions - General.pdf | ||
| RFI Questions - Plumbing.pdf | ||
| RFI Questions - Audio Visual.pdf | ||
| RFI Questions - Mechanical.pdf | ||
| FPB Renovation RFI 1.22.26 updated.pdf | ||
| DOL_FPB_AV_Upgrade_Draft PWS.docx | DOCX document | |
| FPB Renovation RFI (12-17-2025).pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions – Electrical
1. Can you provide existing drawings of electrical systems?
Response: Original construction electrical drawings 9-E-13, 9-E-16, 9-E-19, 9-E-21, and 9-E-64 will be posted to SAM.gov as part of the responses prior to February 6th. In addition, drawing indexes for both Phase I and Phase II original construction will be posted to SAM.gov as part of the responses prior to February 6th. If the bidder needs additional drawings, please identify them from the indexes and we will provide.