This Request for Information (RFI) is issued by the U.S. Department of Labor (DOL) to conduct market research for a comprehensive renovation of the Frances Perkins Building located at 200 Constitution Avenue, NW in Washington, DC. The project scope includes a complete design and build of the building's Auditorium, Great Hall, and Mezzanine, along with mechanical, electrical, and plumbing upgrades, building systems modernization, and sustainability enhancements. The renovation will be performed in phases while the building remains partially occupied, with the NAICS code 236220 for commercial and institutional building construction.
The RFI requests detailed information from potential vendors, including company background, relevant experience with federal facility renovations, technical capabilities, contracting considerations, and rough order of magnitude (ROM) cost estimates. An Industry Day is scheduled for January 13, 2026, with limited attendance (two representatives per company) via prior registration. Responses to the RFI are due by February 2, 2026, at 4:00 PM ET, should be limited to 15 pages in PDF format, and submitted via email to specified DOL contacts. The government emphasizes that this RFI is for market research purposes only and does not constitute a solicitation or commitment to procure services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Questions - Communication and IT.pdf | ||
| BOC Public Meeting Space Industry Final.pptx | PPTX presentation | |
| RFI Questions - Procurement .pdf | ||
| RFI Questions - Mechanical.pdf | ||
| Reference Drawings.zip | ZIP file | |
| RFI Questions - Architectural and interior.pdf | ||
| RFI Questions - Electrical.pdf | ||
| RFI Questions - General.pdf | ||
| RFI Questions - Plumbing.pdf | ||
| RFI Questions - Audio Visual.pdf | ||
| FPB Renovation RFI 1.22.26 updated.pdf | ||
| DOL_FPB_AV_Upgrade_Draft PWS.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought: Renovation of the Main Public Spaces in the Frances Perkins Building
1. Purpose
The U.S. Department of Labor (DOL) is issuing this Request for Information (RFI) in accordance with Federal Acquisition Regulation (FAR) Part 10, Market Research, to obtain input from industry regarding a potential renovation project at the Francis Perkins Building (FPB) located at 200 Constitution Avenue, NW Washington, DC 20210. The information received will assist the Government in understanding industry capabilities, refining requirements, assessing risks, and developing an appropriate acquisition strategy consistent with applicable procurement laws and regulations.
This RFI is for planning and market research purposes only and does not constitute a solicitation, request for proposal, request for quote, or an obligation on the part of the Government to acquire any supplies or services.
2. Project Overview
The Francis Perkins Building is a federally owned, occupied office facility requiring renovation to modernize infrastructure, improve functionality, enhance safety and accessibility, and support current and future mission needs. The anticipated scope may include, but is not limited to:
A complete design and build of the FPB Auditorium, Great Hall, and Mezzanine, including the architectural, interior, structure, audio/visual, furniture, fixtures, and other corresponding infrastructure.
Mechanical, electrical, and plumbing upgrades
Building systems modernization (e.g., HVAC, electrical distribution, fire protection)
Sustainability and energy-efficiency enhancements
Phased construction while the building remains partially occupied
The Government anticipates that the project may be executed in phases to minimize operational disruption.
The North American Industry Classification System (NAICS) code for this requirement is 236220 - commercial and institutional building construction.
3. Industry Day
DOL intends to host a non-mandatory Industry Day to provide additional project information and allow for dialogue with interested vendors.
Tentative Date: January 13, 2026
Location: Francis Perkins Building located at 200 Constitution Avenue, NW Washington, DC 20210.
Format: Presentation The Industry Day will consist of an in-person building tour of the applicable spaces slated for renovation.
Attendance at Industry Day is highly recommended but is not required to submit an RFI response.
Registration Information:
Attendance is by prior registration only. Given space constraints, attendance will be limited to two (2) representatives per company. Interested parties can register by emailing with the subject line: RSVP Site Visit – Francis Perkins Building Renovation – (XYZ company’s name), Helen A. Williams (Williams.Helen.A@dol.gov) and Broderick Morris (Morris.Broderick@dol.gov) no later than January 5, 2026. Confirmation of registration will be sent out by January 8, 2026.
Attendees should provide the following information with their email to Helen A. Williams and Broderick Morris:
Company Name and Business Size (Include applicable socio-economic status) Name of Attendee(s) Attendee(s) Contact Information (Email and Phone Number) Company Website
Updated Technical Capability Statement
4. Requested Information After Industry Day
Respondents are requested to provide concise, relevant information addressing the areas below:
A. Company Information Company name, address, and point of contact Business size and socioeconomic status (e.g., small business, 8(a), HUBZone, SDVOSB, WOSB)
Relevant NAICS codes
B. Relevant Experience
Description of experience performing renovation or modernization projects of similar size, complexity, and occupancy conditions
Experience with occupied federal facilities Examples of projects completed within the last 5–7 years
C. Technical Capabilities and Anticipated Approach
Capabilities related to phased construction and continuity of operations mailto:Williams.Helen.A@dol.gov mailto:Morris.Broderick@dol.gov
Recommended clear and actionable design upgrades Offer insights for audio visual equipment upgrades and follow-up services Experience with modernizing mechanical, electrical, and plumbing upgrades and building systems integration Approaches to minimizing disruptions for DOL employees Safety and quality control practices
D. Contracting and Acquisition Considerations
Recommended contract types (e.g., Firm fixed price, Indefinite delivery indefinite quantity, etc.)
Considerations for phasing, scheduling, and risk mitigation Lessons learned from similar federal renovation projects
E. Schedule and Cost Considerations
General feedback on schedule drivers and constraints Cost considerations or escalation risks Market conditions that may impact performance Identification of long-lead materials or systems that could affect schedule Recommendations for sequencing or phasing to reduce overall duration
F. Rough Order of Magnitude (ROM) and Schedule Input
A high-level, not-to-exceed ROM cost range for the overall project based on the draft scope described above (clearly state assumptions)
Identification of major cost drivers A conceptual project schedule showing major phases and estimated durations
(e.g., design, mobilization, phased construction, closeout) Assumptions regarding working hours, access constraints, and building occupancy Risks that could significantly impact cost or schedule and recommended mitigation strategies
G. Industry Day Feedback Topics or questions you recommend the Government address after Industry Day Information that would be helpful to industry prior to a future solicitation
Please provide any general comments, thoughts, and feedback your firm would like to share regarding this RFI.
5. Response Instructions due by February 2, 2026-4:00 PM (ET)
Responses should be limited to no more than 15 pages, excluding cover page.
Submit responses in PDF format.
Email responses to Helen A. Williams at Williams.Helen.A@dol.gov and Broderick Morris at Morris.Broderick@dol.gov with the subject line: RFI – Francis Perkins Building Renovation
– (XYZ company’s name).
All proprietary information should be clearly marked.
6. Government Disclaimer
This RFI is issued solely for informational and planning purposes in accordance with FAR Part 10 and does not obligate the Government to issue a solicitation, award a contract, or otherwise commit funds. The Government will not reimburse respondents for any costs associated with responding to this RFI, participating in Industry Day, or providing follow-up information.
Information submitted may be used to develop or refine acquisition strategies, requirements, and procurement documentation.
Evaluation Disclaimer – ROM Costs and Schedules:
Any ROM cost ranges, conceptual schedules, phasing concepts, sequencing approaches, or other planning-level information submitted in response to this RFI are non-binding, budgetary in nature, and provided for market research purposes only. Such information will not be used to rank, score, evaluate, or otherwise compare respondents.
The Government recognizes that ROMs and schedules are based on preliminary assumptions and limited information and are subject to material change as requirements are further defined.
Submission or non-submission of ROM cost or schedule information will not result in a competitive advantage or disadvantage in any future acquisition.
The Government will not rely on ROM pricing or schedule data as the sole basis for establishing an Independent Government Cost Estimate (IGCE) or project baseline without additional analysis, validation, and refinement.
No Commitment to Scope or Phasing:
Any references within this RFI to anticipated scope elements, construction phasing, sequencing, occupancy assumptions, or execution approaches are preliminary and subject to change. The Government makes no commitment to the scope, phasing plan, schedule, or project structure described herein. Final requirements, scope definition, phasing strategy, and acquisition approach will be determined at the Government’s discretion and may differ materially from the concepts described in this RFI.
7. Questions
Questions regarding this RFI will not be answered during the walk-through. Questions must be submitted in writing using the following disciplines:
• Architectural/ Interior
• Mechanical
• Electrical
• Plumbing
• Audio-Visual
• Communication/ Information Technology
All RFI questions shall be submitted to Helen A. Williams (Williams.Helen.A@dol.gov) and Broderick Morris (Morris.Broderick@dol.gov) no later than January 14, 2026. Questions over the telephone will NOT be addressed.
File details come from the government source that posted it. Updated .