NNG16572637R
Set 5 Questions and Answers
266. Question: Please clarify following for our approach to FOMSIII.
What is the total estimated approximate IDIQ per year? Is it $7M/year or more? Does
$7m/year represent total for SOW 3 Part 3 -IDIQ Requirement? Please provide Total for
SOW 3 Part 3.
Please refer to question 233.
267. Question: This is direct opposite of section M.6 Cost Evaluation Factor, last paragraph
"The probable cost of the core, the probable cost of the RTO's, the FFP phase - in, and the
Total bid schedule price will be summed to determine the cost for the purpose of selection"
Please clarify, is FFP of the phase in period part of the selection or Not?
As stated in M.6, “The proposed costs of the Core requirements, Representative Task
Orders (RTOs), Bid Schedule Total Prices per year, and the rates proposed in Attachment
B, DIRECT LABOR RATES, INDIRECT RATES AND FEE MATRICES, will be assessed to determine reasonableness and cost realism.” The proposed Phase-in proposal is not being evaluated. It is a data point that is included in the Selection briefing to the