Attachment J.2(L)(4) - Cost Summary Template (Amended)

View the file

Other files for this federal contract opportunity

Other files attached to Construction, Maintenance, Environmental & Testing Services (COMETS), newest first.
File Type Posted
COMETS_Source_Selection_Statement.pdf PDF
COMETS_RFP-_Q&As_(2).docx DOCX document
COMETS_RFP-_Q&As.docx DOCX document
Attachment_J1(A)(1)_-_GLPR_8553_1D.pdf PDF
Attachment_J1(D)(4)_-_GRC_Accounting_Calendar_Template.xlsx XLSX spreadsheet
Attachment_J2(I)_-_Site_Assessment_for_Building_Demolition_Sample_Task.docx DOCX document
Attachment_J1(A)(2)_-_GLWI-FE-8550.pdf PDF
SF-33_for_COMETS_RFP.pdf PDF
Attachment_J2(L)(2)_-_Cognizant_Audit_Office_Template.xlsx XLSX spreadsheet
Attachment_J2(J)_-_NASA_GRC-150_Environmental_Checklist.pdf PDF
Attachment_J2(K)_-_Drawing_(for_Sample_Task).pdf PDF
Attachment_J2(L)(3)_-_Price_Summary_Template.xlsx XLSX spreadsheet
Attachment_J2(L)(4)_-_Cost_Summary_Template.xlsx XLSX spreadsheet
Attachment_J1(A)_-_Statement_of_Work.docx DOCX document
Attachment_J2(N)_-_Past_Performance_Questionnaire_(PPQ).docx DOCX document
NNC17ZFD015R-_COMETS_RFP_Cover_Letter_(signed).pdf PDF
Attachment_J2(L)(1)_-_Business_Systems_Reviews_and_Status_Information_Template.xlsx XLSX spreadsheet
Attachment_J1(D)(3)_-_GRC_533_Template.xlsx XLSX spreadsheet
Attachment_J1(E)_-_Quality_Assurance_and_Surveillance_Plan_(QASP).docx DOCX document
Attachment_J1(C)_-_Wage_Determination_2015-4727.pdf PDF
Attachment_J1(D)(2)_-_GRC_533_Baseline_Template.xlsx XLSX spreadsheet
Attachment_J1(D)(1)_-_GRC_533_Supplemental_Cost_Report_Template.xlsx XLSX spreadsheet
Attachment_J2(M)_-_Client_Authorization_Letter_(CAL).docx DOCX document
NNC17ZFD015R_-_RFP_for_COMETS.docx DOCX document
Attachment_J1(B)_-_Government_Furnished_Property.xlsx XLSX spreadsheet
COMETS_Industry_Day_Attendees_(5-22-2017).xlsx XLSX spreadsheet
Industry_Day_Presentation_for_COMETS_(5-22-2017).pptx PPTX presentation
COMETS_Industry_Day_Registration_Form.docx DOCX document
NNC17ZFD015R-_COMETS_Industry_Day_Event_Information.docx DOCX document
Attachment_J2(M)_-_Client_Authorization_Letter_(CAL).docx DOCX document
Attachment_J1(D)(2)_-_GRC_533_Baseline_Template.xlsx XLSX spreadsheet
Attachment_J1(E)_-_Quality_Assurance_and_Surveillance_Plan_(QASP).docx DOCX document
Attachment_J2(I)_-_Site_Assessment_for_Building_Demolition_Sample_Task.docx DOCX document
NNC17ZFD015R_-_Draft_RFP_Cover_Letter.pdf PDF
Attachment_J2(L)(1)_-_Business_Systems_Reviews_and_Status_Information_Template.xlsx XLSX spreadsheet
Attachment_J2(N)_-_Past_Performance_Questionnaire_(PPQ).docx DOCX document
Attachment_J1(B)_-_Government_Furnished_Property.xlsx XLSX spreadsheet
Attachment_J1(D)(4)_-_GRC_Accounting_Calendar_Template.xlsx XLSX spreadsheet
Attachment_J2(J)_-_NASA_GRC-150_Environmental_Checklist.pdf PDF
Attachment_J1(C)_-_Wage_Determination_2015-4727.pdf PDF
Attachment_J2(L)(2)_-_Cognizant_Audit_Office_Template.xlsx XLSX spreadsheet
Attachment_J1(D)(5)_-_GRC_Contractor_Headcount_Report_Template.xlsx XLSX spreadsheet
Attachment_J1(A)(1)_-_GLPR_8553_1D.pdf PDF
Attachment_J1(A)(2)_-_GLWI-FE-8550.pdf PDF
Attachment_J2(L)(4)_-_Cost_Summary_Template.xlsx XLSX spreadsheet
NNC17ZFD015R_-_DRAFT_RFP_for_COMETS.docx DOCX document
Attachment_J1(D)(1)_-_GRC_533_Supplemental_Cost_Report_Template.xlsx XLSX spreadsheet
Attachment_J1(A)_-_Statement_of_Work.docx DOCX document
Attachment_J1(D)(3)_-_GRC_533_Template.xlsx XLSX spreadsheet
Attachment_J2(L)(3)_-_Price_Summary_Template.xlsx XLSX spreadsheet
Show all 50

Construction, Maintenance, Environmental & Testing Services (COMETS) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Total Tasks + IDIQ

TOTAL OF TASKS & PHASE-IN + GOVERNMENT ESTIMATED IDIQ EFFORT

TOTAL OF TASKS & PHASE-IN

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Phase-In Firm Fixed Price$ -
CLIN 1- Project Management Office
CLIN 2- Construction Management$ 11,240$ 22,480$ 22,480$ 22,480$ 22,480$ 11,240$ 11,240$ 123,640
CLIN 3- Construction Management IDIQ$ 500,000$ 1,000,000$ 1,000,000$ 1,000,000$ 1,000,000$ 500,000$ 500,000$ 5,500,000
CLIN 4- Environmental Management$ 75,220$ 150,435$ 150,435$ 150,435$ 150,435$ 75,220$ 75,220$ 827,400
CLIN 5- Environmental Management IDIQ$ 1,750,000$ 3,500,000$ 3,500,000$ 3,500,000$ 3,500,000$ 1,750,000$ 1,750,000$ 19,250,000
Total of Tasks & Phase-In$ 2,336,460$ 4,672,915$ 4,672,915$ 4,672,915$ 4,672,915$ 2,336,460$ 2,336,460$ 25,701,040
IDIQ FIXED FEE RATES PROPOSED
BASE PERIODOPTION PERIODS
Year 1Year 2Year 3Year 4Year 5Year 6Year 7

1a Total CLIN Costs

Total CLINS 1-4
Total Cost Template

COST PLUS FIXED FEE

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Direct Labor
Hours0000000- 0
Overtime Hours0000000- 0
Total Hours- 0- 0- 0- 0- 0- 0- 0- 0

Direct Labor Cost from Labor Template $ - $ - $ - $ - $ - $ - $ - $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
2. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Total Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Other Direct Costs (ODCs)
1. (ODC Description)$ 86,460$ 172,915$ 172,915$ 172,915$ 172,915$ 86,460$ 86,460$ 951,040
2. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
3. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
Total Other Direct Costs$ 86,460$ 172,915$ 172,915$ 172,915$ 172,915$ 86,460$ 86,460$ 951,040
Subcontractor Costs
1. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
2. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
3. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
Total Subcontract Cost$ -$ -$ -$ -$ -$ -$ -$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -$ -$ -$ -$ -$ -$ -
M&H Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
M&H Cost$ -$ -$ -$ -$ -$ -$ -$ -
G&A Cost
1. (Description of G&A Base)$ -$ -$ -$ -$ -$ -$ -
G&A Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
G&A Cost$ -$ -$ -$ -$ -$ -$ -$ -

Subtotal $ 86,460 $ 172,915 $ 172,915 $ 172,915 $ 172,915 $ 86,460 $ 86,460 $ 951,040

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -$ -$ -$ -$ -$ -$ -
FCCOM Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
FCCOM Cost$ -$ -$ -$ -$ -$ -$ -$ -
Fixed Fee
1. (Description of Fee Base)$ -$ -$ -$ -$ -$ -$ -
Fixed Fee Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Fixed Fee Amount$ -$ -$ -$ -$ -$ -$ -$ -

Total Estimated Cost Plus Fixed Fee $ 86,460 $ 172,915 $ 172,915 $ 172,915 $ 172,915 $ 86,460 $ 86,460 $ 951,040

2 CLIN 1 Costs

CLIN ONE: PROJECT MANAGEMENT OFFICE
Total Cost Template

COST PLUS FIXED FEE

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Direct Labor
Hours- 0
Overtime Hours- 0
Total Hours- 0- 0- 0- 0- 0- 0- 0- 0

Direct Labor Cost from Labor Template $ - $ - $ - $ - $ - $ - $ - $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
2. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Total Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Other Direct Costs (ODCs)
1. Travel/Materials/Supplies/Misc. ODCs$ -$ -
2. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
3. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
Total Other Direct Costs$ -$ -$ -$ -$ -$ -$ -$ -
Subcontractor Costs
1. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
2. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
3. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
Total Subcontract Cost$ -$ -$ -$ -$ -$ -$ -$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -$ -$ -$ -$ -$ -$ -
M&H Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
M&H Cost$ -$ -$ -$ -$ -$ -$ -$ -
G&A Cost
1. (Description of G&A Base)$ -$ -$ -$ -$ -$ -$ -
G&A Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
G&A Cost$ -$ -$ -$ -$ -$ -$ -$ -

Subtotal $ - $ - $ - $ - $ - $ - $ - $ -

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -$ -$ -$ -$ -$ -$ -
FCCOM Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
FCCOM Cost$ -$ -$ -$ -$ -$ -$ -$ -
Fixed Fee
1. (Description of Fee Base)$ -$ -$ -$ -$ -$ -$ -
Fixed Fee Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Fixed Fee Amount$ -$ -$ -$ -$ -$ -$ -$ -

Total Estimated Cost Plus Fixed Fee $ - $ - $ - $ - $ - $ - $ - $ -

3 CLIN 1 Labor

CLIN ONE: PROJECT MANAGEMENT OFFICE
Labor Template
CONTRACT YEAR: ONE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 1- Project Management Office0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: TWO
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 1- Project Management Office0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: THREE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 1- Project Management Office0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FOUR
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FIVE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SIX
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SEVEN
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$1.00$0.00
0.000.00$2.00$0.00
0.000.00$3.00$0.00
0.000.00$4.00$0.00
0.000.00$5.00$0.00
0.000.00$6.00$0.00
0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00

2 CLIN 2 Costs

CLIN TWO: CONSTRUCTION MANAGEMENT
Total Cost Template

COST PLUS FIXED FEE

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Direct Labor
Hours- 0
Overtime Hours- 0
Total Hours- 0- 0- 0- 0- 0- 0- 0- 0

Direct Labor Cost from Labor Template $ - $ - $ - $ - $ - $ - $ - $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
2. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Total Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Other Direct Costs (ODCs)
1. Travel/Materials/Supplies/Misc. ODCs$ 11,240$ 22,480$ 22,480$ 22,480$ 22,480$ 11,240$ 11,240$ 123,640
2. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
3. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
Total Other Direct Costs$ 11,240$ 22,480$ 22,480$ 22,480$ 22,480$ 11,240$ 11,240$ 123,640
Subcontractor Costs
1. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
2. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
3. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
Total Subcontract Cost$ -$ -$ -$ -$ -$ -$ -$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -$ -$ -$ -$ -$ -$ -
M&H Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
M&H Cost$ -$ -$ -$ -$ -$ -$ -$ -
G&A Cost
1. (Description of G&A Base)$ -$ -$ -$ -$ -$ -$ -
G&A Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
G&A Cost$ -$ -$ -$ -$ -$ -$ -$ -

Subtotal $ 11,240 $ 22,480 $ 22,480 $ 22,480 $ 22,480 $ 11,240 $ 11,240 $ 123,640

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -$ -$ -$ -$ -$ -$ -
FCCOM Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
FCCOM Cost$ -$ -$ -$ -$ -$ -$ -$ -
Fixed Fee
1. (Description of Fee Base)$ -$ -$ -$ -$ -$ -$ -
Fixed Fee Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Fixed Fee Amount$ -$ -$ -$ -$ -$ -$ -$ -

Total Estimated Cost Plus Fixed Fee $ 11,240 $ 22,480 $ 22,480 $ 22,480 $ 22,480 $ 11,240 $ 11,240 $ 123,640

3 CLIN 2 Labor

CLIN TWO: CONSTRUCTION MANAGEMENT
Labor Template
CONTRACT YEAR: ONE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: TWO
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: THREE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FOUR
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FIVE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SIX
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SEVEN
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$1.00$0.00
Construction Manager0.000.00$2.00$0.00
Construction Quality Inspector0.000.00$3.00$0.00
Surveying Technician0.000.00$4.00$0.00
GMS Administrator0.000.00$5.00$0.00
Building Manager0.000.00$6.00$0.00
Maintenance Management0.000.00$7.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00

4 CLIN 4 Costs

CLIN FOUR: ENVIRONMENTAL MANAGEMENT
Total Cost Template

COST PLUS FIXED FEE

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Direct Labor
Hours- 0
Overtime Hours- 0
Total Hours- 0- 0- 0- 0- 0- 0- 0- 0

Direct Labor Cost from Labor Template $ - $ - $ - $ - $ - $ - $ - $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
2. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Total Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Other Direct Costs (ODCs)
1. Waste Fees/Supplies/Repairs/Misc. ODCs$ 75,220$ 150,435$ 150,435$ 150,435$ 150,435$ 75,220$ 75,220$ 827,400
2. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
3. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
Total Other Direct Costs$ 75,220$ 150,435$ 150,435$ 150,435$ 150,435$ 75,220$ 75,220$ 827,400
Subcontractor Costs
1. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
2. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
3. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
Total Subcontract Cost$ -$ -$ -$ -$ -$ -$ -$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -$ -$ -$ -$ -$ -$ -
M&H Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
M&H Cost$ -$ -$ -$ -$ -$ -$ -$ -
G&A Cost
1. (Description of G&A Base)$ -$ -$ -$ -$ -$ -$ -
G&A Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
G&A Cost$ -$ -$ -$ -$ -$ -$ -$ -

Subtotal $ 75,220 $ 150,435 $ 150,435 $ 150,435 $ 150,435 $ 75,220 $ 75,220 $ 827,400

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -$ -$ -$ -$ -$ -$ -
FCCOM Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
FCCOM Cost$ -$ -$ -$ -$ -$ -$ -$ -
Fixed Fee
1. (Description of Fee Base)$ -$ -$ -$ -$ -$ -$ -
Fixed Fee Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Fixed Fee Amount$ -$ -$ -$ -$ -$ -$ -$ -

Total Estimated Cost Plus Fixed Fee $ 75,220 $ 150,435 $ 150,435 $ 150,435 $ 150,435 $ 75,220 $ 75,220 $ 827,400

5 CLIN 4 Labor

CLIN FOUR: ENVIRONMENTAL MANAGEMENT
Labor Template
CONTRACT YEAR: ONE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: TWO
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: THREE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FOUR
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: FIVE
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SIX
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00
CONTRACT YEAR: SEVEN
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$1.00$0.00
Env Technician0.000.00$2.00$0.00
Sr Env Engineer0.000.00$3.00$0.00
Environmental Specialist0.000.00$4.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00

6a Indirect Rate

INDIRECT RATE TEMPLATE
A current DCAA Forward Pricing Rate Agreement may be provided in lieu of completing this template for the resepctive rates.
Duplicate Template for each Indirect Rate proposed
Company Name:_____________________________[ ] Prime[ ] Major Subcontractor
Indirect Rate Name:_____________________________
Application Base:_____________________________
Fiscal Year Begins:_____________________________
Fiscal Year Ends:_____________________________
ContractorContractorContractorContractorContractorContractorContractorContractor
Cost Elements withinFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal Year
Indirect Rate PoolPrior Yr 3Prior Yr 2Prior Yr 1_____________________________________________
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
Total Pool Expenses$ -$ -$ -$ -$ -
Application Base ($)$ -$ -$ -$ -$ -
Contractor FY Rate (%)0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
CONVERSION OF BURDEN RATE TO CONTRACT YEARContractContractContractContractContract
Year 1Year 2Year 3Year 4Year 5
Proposed Contract Year Rate0.00%0.00%0.00%0.00%0.00%

6b Indirect Rate

INDIRECT RATE TEMPLATE
A current DCAA Forward Pricing Rate Agreement may be provided in lieu of completing this template for the resepctive rates.
Duplicate Template for each Indirect Rate proposed
Company Name:_____________________________[ ] Prime[ ] Major Subcontractor
Indirect Rate Name:_____________________________
Application Base:_____________________________
Fiscal Year Begins:_____________________________
Fiscal Year Ends:_____________________________
ContractorContractorContractorContractorContractorContractorContractorContractor
Cost Elements withinFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal Year
Indirect Rate PoolPrior Yr 3Prior Yr 2Prior Yr 1_____________________________________________
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
Total Pool Expenses$ -$ -$ -$ -$ -
Application Base ($)$ -$ -$ -$ -$ -
Contractor FY Rate (%)0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
CONVERSION OF BURDEN RATE TO CONTRACT YEARContractContractContractContractContract
Year 1Year 2Year 3Year 4Year 5
Proposed Contract Year Rate0.00%0.00%0.00%0.00%0.00%

6c Indirect Rate

INDIRECT RATE TEMPLATE
A current DCAA Forward Pricing Rate Agreement may be provided in lieu of completing this template for the resepctive rates.
Duplicate Template for each Indirect Rate proposed
Company Name:_____________________________[ ] Prime[ ] Major Subcontractor
Indirect Rate Name:_____________________________
Application Base:_____________________________
Fiscal Year Begins:_____________________________
Fiscal Year Ends:_____________________________
ContractorContractorContractorContractorContractorContractorContractorContractor
Cost Elements withinFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal YearFiscal Year
Indirect Rate PoolPrior Yr 3Prior Yr 2Prior Yr 1_____________________________________________
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
$ -$ -$ -$ -$ -
Total Pool Expenses$ -$ -$ -$ -$ -
Application Base ($)$ -$ -$ -$ -$ -
Contractor FY Rate (%)0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
CONVERSION OF BURDEN RATE TO CONTRACT YEARContractContractContractContractContract
Year 1Year 2Year 3Year 4Year 5
Proposed Contract Year Rate0.00%0.00%0.00%0.00%0.00%

7 Total Staffing

TOTAL STAFFING TEMPLATE (INCLUDES SUBCONTRACTOR LABOR)

BASE PERIODOPTION PERIODS
Year 1Year 2Year 3Year 4Year 5Year 6Year 7
Offeror or Subcontractor NameLabor Category per DOLWD, CBA, GSA. or Offeror's established positionE=Exempt N=Non Exempt U=UnionWYEsWYEsWYEsWYEsWYEsWYEsWYEs
CLIN 2 TOTAL STAFFING
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
TOTAL:0.000.000.000.000.000.000.00
CLIN 4 TOTAL STAFFING
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
0.000.000.000.000.000.000.00
TOTAL:0.000.000.000.000.000.000.00

TOTAL CONTRACT STAFFING 0.00 0.00 0.00 0.00 0.00 0.00 0.00

8 Sample Task Costs

SAMPLE TASK: Site Assessment for Building Demolition
Total Cost Template

COST PLUS FIXED FEE

Direct Labor
Hours
Overtime Hours
Total Hours- 0

Direct Labor Cost from Labor Template $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -
Overhead Rate0.00%
Overhead Cost$ -
2. (Name & Description of Base)$ -
Overhead Rate0.00%
Overhead Cost$ -
Total Overhead Cost$ -
Subcontractor Costs
1. (Subcontractor Name)$ -
2. (Subcontractor Name)$ -
3. (Subcontractor Name)$ -
Total Subcontract Cost$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -
M&H Rate0.00%
M&H Cost$ -
G&A Cost
1. (Description of G&A Base)$ -
G&A Rate0.00%
G&A Cost$ -

Subtotal $ -

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -
FCCOM Rate0.00%
FCCOM Cost$ -
Fixed Fee
1. (Description of Fee Base)$ -
Fixed Fee Rate0.00%
Fixed Fee Amount$ -

Total Estimated Cost Plus Fixed Fee $ -

9 Sample Task Labor

SAMPLE TASK: Site Assessment for Building Demolition
Labor Template
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsE=Exempt N=Non Exempt U=UnionWYEsProductive Work HoursStandard Labor RateLabor Cost
CLIN 2- Construction Management0.000.00$0.00$0.00
Industrial Hyg I- Sub0.000.00$0.00$0.00
Fire Protection Specialist0.000.00$0.00$0.00
Facility Project Manager0.000.00$0.00$0.00
Construction Manager0.000.00$0.00$0.00
Construction Quality Inspector0.000.00$0.00$0.00
Surveying Technician0.000.00$0.00$0.00
GMS Administrator0.000.00$0.00$0.00
Building Manager0.000.00$0.00$0.00
Maintenance Management0.000.00$0.00$0.00
CLIN 4- Environmental Management0.000.00$0.00$0.00
Waste Management Lead0.000.00$0.00$0.00
Waste Management and Sustainability0.000.00$0.00$0.00
Waste Management Technician0.000.00$0.00$0.00
Env Technician0.000.00$0.00$0.00
Sr Env Engineer0.000.00$0.00$0.00
Environmental Specialist0.000.00$0.00$0.00
0.000.00$0.00$0.00
0.00$0.00

IDIQ Labor Rates

IDIQ LABOR RATES TEMPLATE

BASE PERIODOPTION PERIODS
CY 01CY - 02CY - 03CY - 04CY - 05CY - 06CY - 07CY -09
Fully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/HourFully Burdened Rate/Hour
Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsSTOTSTOTSTOTSTOTSTOTSTOTSTOTSTOT
CLIN 2- Construction Management
Industrial Hyg I- Sub
Fire Protection Specialist
Facility Project Manager
Construction Manager
Construction Quality Inspector
Surveying Technician
GMS Administrator
Building Manager
Maintenance Management
CLIN 4- Environmental Management
Waste Management Lead
Waste Management and Sustainability
Waste Management Technician
Env Technician
Sr Env Engineer
Environmental Specialist

NNC16ZL009R &"Arial,Bold"&12GEARS- Glenn Engineering and Research Support IDIQ Rates

&F &A Source Selection Information See FAR 3.104 &P of &N

IDIQ LABOR RATES DEVELOPMENT

IDIQ LABOR RATES DEVELOPMENT TEMPLATE
Prime:

rlisy: Enter Name of Prime proposing the IDIQ rates

Contract Year:

Lisy, Robert P. (GRC-CH00): There shall be 7 contract years. One schedule for each contract year is rquired.

Prime Burdens on Subktr.
Prime/Sub (Identify)Contractor's Labor
ClassificationGovernment Provided Labor Category
Table L-2 Incumbent Labor DemographicsST DL RateOverheadOther IndirectG&AProfitSubtotal(Specify)(Specify)(Specify)Fully Burdened Rates
RFP EXAMPLE - Remove in submittalCLIN 2- Construction Management
PrimeIndustrial Hyg I- Sub$ 19.50$ 9.36$ 0.58$ 2.35$ 31.79$ 31.79
PrimeFire Protection Specialist$ 19.25$ 9.24$ 0.57$ 2.32$ 31.38$ 31.38
S(ABC Co.)Facility Project Manager$ 19.00$ 10.45$ 0.88$ 30.330.38$ 1.21$ 2.55$ 34.48
S(XYZ Co.)Construction Manager$ 19.25$ 11.17$ 1.22$ 31.630.39$ 1.27$ 2.66$ 35.94
Construction Quality Inspector
Surveying Technician
GMS Administrator
Building Manager
Maintenance Management
CLIN 4- Environmental Management
Waste Management Lead
Waste Management and Sustainability
Waste Management Technician
Env Technician
Sr Env Engineer
Environmental Specialist
(insert labor category)
(insert labor category)
(insert labor category)
(insert labor category)
(insert labor category)
(insert labor category)

NNC16ZL009R &"Arial,Bold"&12GEARS- Glenn Engineering and Research Support IDIQ Rates

&F &A Source Selection Information See FAR 3.104 &P of &N

Total Costs

CLIN TWO: CONSTRUCTION MANAGEMENT
Total Cost Template

COST PLUS FIXED FEE

BASE PERIODOPTION PERIODS
ELEMENTSYear 1Year 2Year 3Year 4Year 5Year 6Year 7TOTAL
Direct Labor
Hours- 0
Overtime Hours- 0
Total Hours- 0- 0- 0- 0- 0- 0- 0- 0

Direct Labor Cost from Labor Template $ - $ - $ - $ - $ - $ - $ - $ -

Overhead (List) Cost
1. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
2. (Name & Description of Base)$ -$ -$ -$ -$ -$ -$ -
Overhead Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Total Overhead Cost$ -$ -$ -$ -$ -$ -$ -$ -
Other Direct Costs (ODCs)
1. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
2. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
3. (ODC Description)$ -$ -$ -$ -$ -$ -$ -$ -
Total Other Direct Costs$ 86,460$ 172,915$ 172,915$ 172,915$ 172,915$ 86,460$ 86,460$ 951,040
Subcontractor Costs
1. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
2. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
3. (Subcontractor Name)$ -$ -$ -$ -$ -$ -$ -$ -
Total Subcontract Cost$ -$ -$ -$ -$ -$ -$ -$ -
Material Handling (Pass through costs)
1. (Description of Material Handling Base)$ -$ -$ -$ -$ -$ -$ -
M&H Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
M&H Cost$ -$ -$ -$ -$ -$ -$ -$ -
G&A Cost
1. (Description of G&A Base)$ -$ -$ -$ -$ -$ -$ -
G&A Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
G&A Cost$ -$ -$ -$ -$ -$ -$ -$ -

Subtotal $ 86,460 $ 172,915 $ 172,915 $ 172,915 $ 172,915 $ 86,460 $ 86,460 $ 951,040

Facilities Capital Cost of Money (FCCOM)
1. (Description of FCCOM Base)$ -$ -$ -$ -$ -$ -$ -
FCCOM Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
FCCOM Cost$ -$ -$ -$ -$ -$ -$ -$ -
Fixed Fee
1. (Description of Fee Base)$ -$ -$ -$ -$ -$ -$ -
Fixed Fee Rate0.00%0.00%0.00%0.00%0.00%0.00%0.00%
Fixed Fee Amount$ -$ -$ -$ -$ -$ -$ -$ -

Total Estimated Cost Plus Fixed Fee $ 86,460 $ 172,915 $ 172,915 $ 172,915 $ 172,915 $ 86,460 $ 86,460 $ 951,040