The file's text, extracted by GovTribe without its formatting.
Line Item
| Description |
| Quantity |
| Unit |
| Unit Price |
| Sub-Total |
| Total Price |
| 001 |
| BASE PRICE: Total Price for the entire work for Aircraft Engine Repair Facility P683 in accordance with the drawings and specifications complete but excluding work provided in another Priced Line Item. Source funding is a MILCON. |
| 1 |
| EA |
| 001A |
| Subtotal of Base Price for the entire work for the Aircraft Engine Repair Facility primary facility (CC21125) complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 001B |
| Subtotal of Base Price for the entire work for Parking Structure (CC85310) complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item |
| 1 |
| EA |
| 001C |
| Subtotal of Base Price for the entire project sitework, outside the facilities 5-foot line, for including a 1.34-acre temporary gravel parking |
lot , 3.24-acre asphalt paved parking lot , utilities, storm drainage, walks, signalization, etc., complete in accordance with the [drawings and specifications, but excluding work described in another line item.
| 001D |
| Subtotal of Base Price for the Electrical Distribution Line, complete in accordance with the drawings and specifications but excluding work described in another line Item. |
| 1 |
| EA |
| 001E |
| Unit Price for providing Foundation Piling for the Parking Garage facility complete in accordance with the drawings and specifications but excluding work provided in another line item. |
| 23,595 |
| VLF |
| $______ |
| $_______ |
| 001F |
| Unit Price for providing Pile Load Test for the Parking Garage facility, complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 23,595 |
| VLF |
| $______ |
| $_______ |
| 001G |
| Unit Price for removal and disposal of asbestos containing pipe insulation (by pipe diameter ranges complete in accordance with the drawings and specifications but excluding work provided in another line item. |
| 100 |
| LF |
| $______ |
| $_______ |
| 001H |
| Unit Price for removal and disposal of asbestos containing floor tile complete in accordance with the drawings and specifications but excluding work provided in another line item. |
| 5,000 |
| CY |
| $______ |
| $_______ |
| 001I |
| Unit Price for removal and disposal of contaminated stockpiled soils complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 10,000 |
| CY |
| $______ |
| $_______ |
| 001J |
| Unit Price for provision and compaction of fill in place of removed contaminated soil, complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 5,000 |
| CY |
| $______ |
| $_______ |
| 001K |
| Unit Price for Demolition of Buildings 6F and 6G and covered walkway, complete in accordance with the drawings and specifications, but excluding work provided in another line item. |
| 1 |
| EA |
| 001L |
| Subtotal of Base Price for providing Swing Space and all utilities (including end of project disassembly and restoration of the site) complete in accordance with the drawings and the specifications but excluding work provided in another Priced line item |
| 1 |
| EA |
| 002 |
| Base Bid: Price for providing all work in connection with Vertical Build Platforms (CFCI) excluding utilities (cost for the structure and lifting elevators only), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item. Source of funding is NON-MILCON |
| 1 |
| EA |
| 003 |
| Base Bid: Price for providing Main Facility cranes, excluding structure, complete in accordance with the drawings and specifications but excluding work provided in another Priced line item. |
| 1 |
| EA |
| 004 |
| Option Item No. 1: Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications but excluding work provided in another Priced line item. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, and communication cabling connecting these devices together. |
Include the price for supporting permanent infrastructure under the Base Price. Interior supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections. The source of funding is NON-MILCON. Option to be executed withing 365 days of contract Notice to Proceed in accordance with FAR 52.217-7 Government Estimated Price:
$955,979 HAR Percent (NTE 5%)
HAR Subtotal Total AV System Estimated Price
| 005 |
| Option Item No. 2: Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item. The source of funding is NON-MILCON. Option to be executed withing 365 days of contract Notice to Proceed in accordance with FAR 52.217-7 |
| Government Estimated Price: |
$6,543,186 HAR Percent (NTE 5%)
HAR Subtotal Total FF&E Estimated Price