IMPROVED NAVY LIGHTERAGE SYSTEM (INLS)
CONTRACT NO.
CDRL DATA ITEM NO:
| Test Title: | Ships Service Diesel Generator Operational |
| Test (Warping Tug/Power Module) | |
| Test No: |
Revision:
Hull:
TEST PROCEDURE PREPARATION/APPROVAL
PREPARED BY:
K. Fischer
DATE:
JULY 2015
APPROVED BY:
DATE:
TEST PROCEDURE CONDUCTED
| CONTRACTOR: |
| DATE: |
| GOV. WITNESS: |
| DATE: |
| TEST TITLE: | TEST NO: | HULL NO: |
| Beach Module Bow Ramp Operational Test | 169-00001 | BM X |
REVISION RECORD
| REV |
| AFFECTED |
PAGES
| DESCRIPTION |
| APPROVED |
Original Issue
TEST OBJECTIVE:
The objective of this test is to demonstrate the no load, incremental and full load operation of the ships service diesel generators and to demonstrate that the manual features will control the generator within specific limits.
EQUIPMENT INVOLVED:
1. Starboard Ship Service Diesel Generator
2. Port Ship Service Diesel Generator
REFERENCES:
1. IEEE – 45, section 34.2.1, Ship Test, New Installations, Circuits
2. NAVFAC # 1600428 Electrical One Line Diagram
SAFETY PRECAUTIONS:
1. Test personnel shall strictly adhere to all shipyard safety precautions including, but not limited to all caution and warning notes contained in this test procedure and applicable documents.
2. All unauthorized personnel shall be kept clear of test areas for duration of test. Persons in adjacent areas shall be notified of testing being done.
3. Ensure all power sources are de-energized during insulation resistance tests.
4. A 500 Volt Megger shall be used only on the Generator Stator Circuit. A 50 Volt Megger shall be used on all other circuits, rotor, exciter field for a minimum of 60 seconds.
5. Observe Wattmeter and Ammeter during voltage adjustment demonstration to prevent overloading generator.
6. In the event of unusual noise or vibration, shut down the Generator.
PREREQUISITES:
1. Generator and Switchboard System Cable Test
2. Generator and Switchboard System Input Output Test
ADDITIONAL INSTRUCTIONS:
1. The test conductor will list on comment sheet, Section “H”, any discrepancies requiring corrective action, any unusual response observed while performing test or any significant events and observations occurring during performance of the test. If hazardous conditions exist, test is to be stopped until conditions are corrected.
2. Verify calibration of installed instruments and equipment to be used during test is complete.
3. All breakers on switchboard shall be secured during test. Vessel lighting electrical loads should be fed from a shore power supplied source the duration of the test.
4. Controls and indicators not specifically mentioned in this procedure shall be observed for proper operation.
5. Read the entire test procedure prior to initiating the tests described herein.
TEST EQUIPMENT REQUIRED TO ACCOMPLISH THIS TEST PROCEDURE:
| QTY | DESCRIPTION | DESIGN TEST READING (DTS) | ||||
| (1) | Load Bank, 250 kW, 450 Volt, Resistive Load Bank | |||||
| 3 Phase, 60 Hz, | ||||||
| (1) | Megger | 500 VDC, Conforming to type GC or | ||||
| GM of MIL-0-16485 (or equal) SCAT | ||||||
| 4452. | ||||||
| (1) | Megger | 50 VDC, Weston, Model 799 Scat 4448 | ||||
| (1) | Contact Thermometers or Digital | 0-100 Deg C or 32-212 Deg F | ||||
| Thermometers | Omega Model 871 or equal |
(1) Stop Watch
(4) Slack Tube Manometer Inches of Water
PERSONNEL REQUIRED TO ACCOMPLISH THIS TEST PROCEDURE:
1. Two Qualified Electricians, One Qualified Machinery Installer
GOVERNMENT SUPPORT PERSONNEL:
1. Subject Matter Expert (SME): One SME, ISEA/SSA/PE or equivalent to witness and sign off on testing as Government Representative.
2. Ship’s Force personnel to stand by as safety watch, as necessary.
3. Ship’s Force engineer to align machinery as required.
4. Ship’s Force ET to support electrical checks and system alignment.
5. Contractor will require 4 hours of ISEA or SSA support. This support must be scheduled with the ISEA or SSA at least two weeks in advanced.
EQUIPMENT CONFIGURATION:
1. Ship Service Generators shall have all fluids checked and filled to their service levels.
2. Ensure starting batteries have been charged.
3. Align fuel oil system for normal operation.
4. Connect the variable resistive load bank to the bus work of the generator under test at the switchboard.
5. Align all auxiliary equipment to support the SSDG under full load conditions.
6. Attach a manometer to each SSDG exhaust and combustion air test port
TEST INSTRUCTIONS:
STEP 1: Ensure safety instructions paragraph are followed.
STEP 2: Measure the insulation resistance (cold) of the generator. Correct the insulation resistance readings to 25 degrees centigrade using the Nomograph on page 12. RECORD ON DATA SHEET
NO LOAD TEST
STEP 3: Bring engine up to speed with Generator Circuit Breaker open. Test is conducted at No Load as output power will be cut off. Check operation of over speed trips, manual trips, and all safety control and warning systems to ensure proper operation
STEP 4: Turn Auto/Manual switch to Manual. Line voltage should measure 460 VAC. Adjust manual Rheostat as necessary to obtain 460 VAC indication on AC Voltmeter. RECORD ON DATA SHEET
STEP 5: Adjust Automatic Voltage to minimum and maximum voltage. The Rheostat should be capable of adjusting the Generator Voltage between 432 and 510 Volts. RECORD ON DATA SHEET
STEP 6: Demonstrate operation of the speed control device in Manual Mode to control speed of the unit. Record the minimum and maximum values and the time to go from minimum to maximum on the Data Sheet. RECORD ON DATA SHEET
FULL LOAD TEST
STEP 7: Operate the Generator at full rated load for 30 minutes to bring it up to or near its operating temperature. During this period the general operation of the generator shall be monitored and any necessary adjustments shall be made.
STEP 8: Demonstrate that the generator Voltage can be adjusted over the minimum acceptable range of 436.5 to 481.5 volts under full load. RECORD ON DATA SHEET
STEP 9: After reaching operating temperature, the load shall be removed from the generator. At No Load and with Generator excitation under the control of the Voltage Regulator, set the generator to 100% of rated speed (1800 RPM). Note: Do not readjust speed during test.
| STEP 10: Apply load steps in 20% increments from no load to 100% load using ships load and the resistive load bank. (In order to achieve the 20 and 40 percent load’s, minimal ships loads should be running and the Engine Room Supply Fan should be run at half speed. Above the 40 percent load step, additional ship loads can be applied along with the resistive load bank and the Engine Room Supply Fan shall run at full speed). Maintain voltage at rated output voltage for each load step for 15 minutes and record dates on the data sheets. |
| Observed Load (kW) |
| % Load |
| Engine Speed (RPM) |
| Time (min.) |
| 15 |
| 20 |
| 1800 |
| 15 |
| 30 |
| 40 |
| 1800 |
| 15 |
| 45 |
| 60 |
| 1800 |
| 15 |
| 60 |
| 80 |
| 1800 |
| 15 |
| 75 |
| 100 |
| 1800 |
| 15 |
| 82 |
| 110 |
| 1800 |
| 20 min / 2 hrs |
110% LOAD TEST
STEP 11: Operate the unit at 110% rated load for 2 hours (minimum) to approximately 3 hours, until temperatures stabilize within 1 degree centigrade for 3 consecutive data points. Record Generator and Diesel Engine Data at 20 minute intervals as listed on the data sheets. RECORD ON DATA SHEET
SHUTDOWN
STEP 12: Secure the Diesel Generator and take hot insulation resistance readings. Correct the insulation resistance readings to 25 degrees centigrade using the Nomograph on page 11. RECORD ON DATA SHEET
STEP 13: Return all equipment to pretest conditions.
STEP 14: Perform a visual inspection of the generator set for oil for fuel leaks, loose connections and fittings.
COLD INSULATION RESISTANCE SSDG
STEP 2 MINIMUM EXPECTED RESULTS ACTUAL RESULTS
| EQUIPMENT |
| NOT CLEANED |
| CLEANED IN PLACE |
| RECOND |
| NEW |
| SSDG #1 |
| SSDG #2 |
| STATOR |
| 0.2 MEGOHMS |
| 1.0 MEGOHMS |
| 2.0 MEGOHMS |
| 10.0 MEGOHMS |
| EXCITER FIELD |
| 0.5 MEGOHMS |
| 1.25 MEGOHMS |
| 2.5 MEGOHMS |
| 5.0 MEGOHMS |
| ___________________________ | _________________________________ | __________________________ | |
| TEST CONDUCTOR | GOVERNMENT WITNESS | DATE |
NO LOAD DATA SHEET
| STEP |
| FUNCTION |
| EXPECTED RESULTS |
| ACTUAL RESULTS |
| SSDG #1 |
| SSDG #2 |
| 4 |
| Line Voltage |
| SAT |
| 5 |
| Manual Voltage Control |
| SAT |
| Maximum Voltage in Manual |
| 481.5V |
| Minimum Voltage in Manual |
| 436.5V |
| 6 |
| Speed Change Control Range |
| 57 – 63 Hz |
| Time from Min to Max – Speed Control |
| 1 Min. Nominal |
| ___________________________ | _________________________________ | __________________________ | |
| TEST CONDUCTOR | GOVERNMENT WITNESS | DATE |
TEST TITLE: TEST NO: REV
Ships Service Diesel Generator Operational Test WT/PM
STEP 10 FULL LOAD DATA SHEET
| SSDG#1 |
| SSDG#2 |
Start Time
Date
| Data Sheet |
| 20% LOAD |
40% LOAD
60% LOAD
80% LOAD
100% LOAD
| Parameter |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
Power (ekW)
Power Factor
Engine RPM
Frequency (Hz)
Voltage Phase A
Voltage Phase B
Voltage Phase C
Current Phase A
Current Phase B
Current Phase C
L.O. Pressure
Engine F.W. Temp Coolant/Out
Manifold Exhaust Temp
Exh Press (60” H2O max)
Air Intake Temp
Comb Air Press (32” H2O max)
| ___________________________ | _________________________________ | __________________________ | |
| TEST CONDUCTOR | GOVERNMENT WITNESS | DATE |
STEP 11 110% LOAD DATA SHEET
| SSDG#1 |
| SSDG#2 |
Start Time
Date
| Data Sheet |
| 20 Minutes |
40 Minutes
60 Minutes
80 Minutes
100 Minutes
120 Minutes
| Parameter |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
| SSDG#1 |
| SSDG#2 |
Power (ekW)
Power Factor
Engine RPM
Frequency (Hz)
Voltage Phase A
Voltage Phase B
Voltage Phase C
Current Phase A
Current Phase B
Current Phase C
L.O. Pressure
Eng F.W. Temp Coolant/Out
Manifold Exhaust Temp
Exh Press (60” H2O max)
Air Intake Temp
Comb Air Press (32” H2O max)
| ___________________________ | _________________________________ | __________________________ | |
| TEST CONDUCTOR | GOVERNMENT WITNESS | DATE |
| STEP 12 | HOT INSULATION RESISTANCE SSDG |
| USE NOMOGRAPH |
| MINIMUM EXPECTED RESULTS |
| ACTUAL RESULTS |
EQUIPMENT
NOT CLEANED
CLEANED IN PLACE
RECOND
NEW
| SSDG#1 |
| SSDG#2 |
STATOR
0.2 MEGOHMS
1.0 MEGOHMS
2.0 MEGOHMS
10.0 MEGOHMS
EXCITER FIELD
0.5 MEGOHMS
1.25 MEGOHMS
2.5 MEGOHMS
5.0 MEGOHMS
| ___________________________ | _________________________________ | __________________________ | |
| TEST CONDUCTOR | GOVERNMENT WITNESS | DATE |
NOMOGRAPH FOR TEMPERATURE CORRECTION OF INSULATION RESISTANCE
TEST EQUIPMENT
| NAME |
| MODEL |
NUMBER
SERIAL
NUMBER
CALIBRATION
DUE DATE
REMARKS/WITNESS
| CONTRACTOR: |
| DATE: |
| GOVERNMENT REP: |
| DATE: |
| NUMBER |
| COMMENTS |
| CONTRACTOR: |
| DATE: |
| GOVERNMENT REP: |
| DATE: |
| NUMBER |
| OPEN ITEMS AND CORRECTIONS |
| CONTRACTOR: |
| DATE: |
| GOVERNMENT REP: |
| DATE: |
| NUMBER |
| TEST RESULTS SUMMARY |
This test was conducted in accordance with this test procedure; no adjustments were made to equipment under test except as required by the test procedure, and the results of the test are as stated in this report.
| CONTRACTOR: |