About this file

Attachment 23 DEIF Crompton Site Visit Power Point

View the file

Other files

File Type Posted
Admendment_0002.pdf PDF
Attachment_17-_Woodword_L-Series_Integrate_Speed_Control.pdf PDF
Attachment_15-_WT CFPM_SWBD_Layout.pdf PDF
Attachment_20-_BM_SWBD_Layout.pdf PDF
Attachment_21-_BM_Field_Termination_Drawings.pdf PDF
Attachment_16-_WT CPFM_Field_Termination_Drawings.pdf PDF
Attachment_7_Rev.__1-_Attachment_7_-_Switchboard_System_Wiring_Diagram.pdf PDF
Attachment_24-_DEIF_Crompton_Site_Visit_Power_Point_Part_2.pdf PDF
Attachment_5_Rev.__1-Attachment_5_-_Crompton_Configuration_Parameter.pdf PDF
Attachment_19-_DEIF_Layout.pdf PDF
Attachment_22-_ASME_Y14.100.pdf PDF
N64498-16-R-5019-0001.pdf PDF
N64498-16-R-5019.pdf PDF
Attachment_10_-Generator_System_Operational_Test_BM.docx DOCX document
Attachment_6_-_Generator_System_Wiring_Diagram.pdf PDF
Attachment_4b_-_Welding_Tasks_Electrical_Isolation_Tech_Refresh.pdf PDF
Attachment_12_-Switchboard_System_Operational_Test_BM.docx DOCX document
Attachment_1_-_Alarm_Set_Points_(2).pdf PDF
Copy_of_Attachment_3_-_DEIF_Configuration_Parameter.xlsx XLSX spreadsheet
Attachment_2_-_Crafts_Network_Diagram_(2).pdf PDF
Attachment_7_-_Switchboard_System_Wiring_Diagram.pdf PDF
Attachment_5_-_Crompton_Configuration_Parameter.pdf PDF
cdrls.pdf PDF
Attachment_8_-_Generator_and_Switchboard_System_Input_Output_Test.docx DOCX document
Attachment_11_-Switchboard_System_Operational_Test_WT_PM.docx DOCX document
Attachment_8_Appendix_-_Generator_and_Switchboard_System_IO_Table.pdf PDF
Attachment_14_-_S9074-AR-GIB-010_278.pdf PDF
Attachment_4a_-_Welding_Tasks_Electrical_Isolation_Non_Tech.pdf PDF
Attachment_13_-_S0400-AD-URM-010_TUM.pdf PDF
N64498-16-R-5019.pdf PDF
Attachment_9_-_Generator_System_Operational_Test_WT_PM.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INLS Generator/Switchboard Control, Monitoring and

Protection System Replacement

N64498-16-R-5019

2 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 2

INLS Project Team

• Contract Specialist: Andrea Merlino

• Contract Specialist: Jane Dematto

• Contracting Officer: John Stefano

• Software Support: Joseph Messenger

• Diesel Engine Support: Alan Tibbetts

• Electrical Support: David Senos

• Control System Support: Ken Fischer

• Control System Support : Ghanshyam Dhamelia

3 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 3

BIC Base Information

• Follow the speed and other signs strictly while driving on base

• Do not park the vehicle on grass surface

• No photos or video allowed anywhere outside except inside the INLS craft

4 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 4

Improved Navy Lighterage System (INLS)

• What is INLS?

- New and improved lighterage system that can be assembled into causeway, docks or ferries

Presenter Presentation Notes Rev 2 submitted to EXWC Nov 14 APL and TM impacts from Rev 2

5 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 5

• Provides the Navy and Marine Corps with a safer, more versatile way to deliver vehicle and critical supplies from ship to shore during war or peacetime operations

INLS Mission

Presenter Presentation Notes This alteration provides failsafe alignment of the battery charging circuit to prevent inverter damage.

SAR package is ready for EXWC review and W7M input as soon as we validate that upgraded breaker will resolve last remaining problem in this circuit.

6 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 6

INLS Overview

• Consists of powered and non-powered floating modules

- Warping Tug (WT) - powered

- Causeway Ferry (CF) – The CF is an assembly of Causeway Ferry Powered Module (CFPM) -powered Beach Module (BM) - powered Intermediate Module (IM) – non-powered

- Combination Module (CM) – non-powered

- Docking Module (DM) – non-powered

- Ramp Module (RM) – non-powered

• There are 22 Warping Tugs, 38 Causeway Ferry Powered Modules and 38 Beach Modules in fleet

Presentation Notes Joe Messenger to speak to this.

7 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 7

Warping Tug (WT)

• Used for assembling non-powered modules, towing, anchoring and salvaging operations

• Contains two generators system and two switchboard system, one for each side

Presenter

Joe Messenger to speak to this.

8 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 8

Causeway Ferry (CF)

• An assembly of the CFPM, BM and IM used to transport cargo from ship to shore

• The CFPM has two generators system and two switchboard system, one for each side

• The BM has one generator system and one switchboard system

The majority of DEIF failures have been due to repetitive high rate input (i.e. pressure switches) and repetitive high rate output (i.e. pulse width modulation governor control signal) failures. In December 2012 at ACB-1 we found a DEIF that had failed for this same reason. The emerging pattern indicates that the I/O internal to the DEIF is not durable enough for our application. ACB-1 has been able to get repairs done and ACB-2 /CAT D&FP are trying to set up the local Cat dealer.

Replacing the DEIF is an extensive engineering and testing effort, requiring OEM support.

To that effect, we hosted a sources sought industry day where several companies with ideas on how to resolve the problem were shown the current Configuration, from this, we received Order of Magnitude estimates on how much this alteration would cost and used it to develop the SSCP.

We have an RFP ready to go and the plan is for us to approve one proposal and have a prototype installed prior to full scale rollout.

9 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 9

Non-powered Module

• Does not have any electrical system

• Used as roll on roll off discharge facility and/or the floating causeway, which supports the discharge ramp from the cargo ship and serves as pier to transfer rolling stock to a barge

Presenter Presentation Notes The majority of DEIF failures have been due to repetitive high rate input (i.e. pressure switches) and repetitive high rate output (i.e. pulse width modulation governor control signal) failures. In December 2012 at ACB-1 we found a DEIF that had failed for this same reason. The emerging pattern indicates that the I/O internal to the DEIF is not durable enough for our application. ACB-1 has been able to get repairs done and ACB-2 /CAT D&FP are trying to set up the local Cat dealer.

Replacing the DEIF is an extensive engineering and testing effort, requiring OEM support.

To that effect, we hosted a sources sought industry day where several companies with ideas on how to resolve the problem were shown the current Configuration, from this, we received Order of Magnitude estimates on how much this alteration would cost and used it to develop the SSCP.

We have an RFP ready to go and the plan is for us to approve one proposal and have a prototype installed prior to full scale rollout.

10 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 10

Generator System

• All INLS Diesel Generators use the Caterpillar C4.4 diesel engine along with a Caterpillar generator rated at 78.6KW

• The device that provides diesel generator control, monitoring and protection is the DEIF Protection and Paralleling Unit (PPU)

– This system is beginning to experience failures due to high repetition input/output signals

11 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 11

DEIF PPU

• There are two DEIF PPUs, one for each generator on Warping Tug and Causeway Ferry Power Module, and one DEIF PPU for Beach Module generator

• They share the same capability

PPU

Main Controller

12 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 12

• In local mode, DEIF allows control and monitoring at local panel

• In remote mode, built in serial Modbus Remote Terminal Unit (RTU) communication allows control and monitoring at Machinery Control System (MCS) station

• Refer to PWS document for control and monitoring requirements

DEIP PPU Local/Remote Mode

Presentation Notes This alteration provides failsafe alignment of the battery charging circuit to prevent inverter damage.

SAR package is ready for EXWC review and W7M input as soon as we validate that upgraded breaker will resolve last remaining problem in this circuit.

13 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 13

DEIF PPU Wiring Diagram

• Integrates with existing C4.4 instruments as shown in schematic below

• Refer to attachment 6 on solicitation package for wiring diagram

14 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 14

INLS Switchboard Control, Monitoring and Protection

• The device that provides switchboard control, monitoring and protection is the Crompton Switchboard Protection Relay

– Obsolete with no fit, form and function replacement

15 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 15

Crompton Switchboard Protection Relay

• There are two cromptons, one for each side on Warping Tug and Causeway Ferry Power Module, and one crompton for Beach Module switchboard

• They share the same capability

16 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 16

• In manual mode, crompton provides control and monitoring at switchboard

• In power management mode, built in serial Modbus Remote Terminal Unit (RTU) communication allows control and monitoring at MCS station

• On both mode, crompton provides protection to switchboard.

• Refer to PWS document for their requirements

Switchboard Manual/Power Management Mode

Presenter Presentation Notes This alteration provides failsafe alignment of the battery charging circuit to prevent inverter damage.

SAR package is ready for EXWC review and W7M input as soon as we validate that upgraded breaker will resolve last remaining problem in this circuit.

17 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 17

Crompton Switchboard Protection Relay Wiring Diagram

• Integrates with existing switchboard instruments as shown in schematic below

• Refer to attachment 7 on solicitation package for wiring diagram

18 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 18

• In auto mode, both systems acts together upon detecting deadbus

– DEIF starts the generator and closes the breaker

– Crompton provides monitoring and protection to switchboard

Switchboard Auto Mode

Presentation Notes This alteration provides failsafe alignment of the battery charging circuit to prevent inverter damage.

SAR package is ready for EXWC review and W7M input as soon as we validate that upgraded breaker will resolve last remaining problem in this circuit.

19 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 19

Purpose of RFP

• To provide a replacement for the current DEIF and Crompton control, monitoring, and protection system

– Refer to Performance Work Statement (PWS) for system requirement

• Looking for modern integrated control, monitoring, synchronization and protection system

• The current system basically interface to the MCS. We are looking for a fit, form and function type solution that will interface to our MCS.

• Ethernet TCP/IP communication is desirable.

20 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 20

RFP Clarification

• N64498-16-R-5019, Section 4.1.1 & 4.2.2 (remote monitoring) will be controlled and monitored at INLS MCS station

– Refer to PWS documents for details

21 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 21

RFP Modification

• N64498-16-R-5019, Section 4.18.3.2 steps h to j is not available as government furnished equipment

– Sync check relay (ANSI 25D)

– Power reverse relay (ANSI 32R)

– Power available relay (ANSI 59) (QTY 2)

– Under voltage relay (ANSI 27)

• The above relays are part of the Crompton and should be included in proposed replacement

22 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 22

RFP Modification

• N64498-16-R-5019, Section 4.1.1.c.i.7 remote indication monitoring is not required at MCS station

– Switchboard mode for generator

• Auto

• Power Management

• Manual

• Off

• This capability already exists so please make sure not to break

it. Refer to solicitation drawings for more details.

23 NAVFAC EXPEDITIONARY PROGRAMS OFFICE 23

Questions

INLS Generator/Switchboard Control, Monitoring and Protection System Replacement��N64498-16-R-5019
INLS Project Team
BIC Base Information
Slide Number 4
INLS Mission
INLS Overview
Warping Tug (WT)
Causeway Ferry (CF)
Non-powered Module
Generator System
DEIF PPU
DEIP PPU Local/Remote Mode
DEIF PPU Wiring Diagram
INLS Switchboard Control, Monitoring and Protection
Crompton Switchboard Protection Relay
Switchboard Manual/Power Management Mode
Crompton Switchboard Protection Relay�Wiring Diagram
Switchboard Auto Mode
Purpose of RFP
RFP Clarification
RFP Modification
RFP Modification
Questions