Attachment_12_-Switchboard_System_Operational_Test_BM.docx

DOCX document 43 KB Posted

Attached to
The development of Three (3) generator and switchboard control, monitoring and protection systems, along with the associated integration and installation service support.
Solicitation number
N64498-16-R-5019
Issued by

About this file

Attachment 12- Switchboard System Operational Test BM

View the file

Other files

File Type Posted
Admendment_0002.pdf PDF
Attachment_17-_Woodword_L-Series_Integrate_Speed_Control.pdf PDF
Attachment_15-_WT CFPM_SWBD_Layout.pdf PDF
Attachment_20-_BM_SWBD_Layout.pdf PDF
Attachment_21-_BM_Field_Termination_Drawings.pdf PDF
Attachment_16-_WT CPFM_Field_Termination_Drawings.pdf PDF
Attachment_7_Rev.__1-_Attachment_7_-_Switchboard_System_Wiring_Diagram.pdf PDF
Attachment_24-_DEIF_Crompton_Site_Visit_Power_Point_Part_2.pdf PDF
Attachment_5_Rev.__1-Attachment_5_-_Crompton_Configuration_Parameter.pdf PDF
Attachment_19-_DEIF_Layout.pdf PDF
Attachment_23-_DEIF_Crompton_Site_Visit_Power_Point.pdf PDF
Attachment_22-_ASME_Y14.100.pdf PDF
N64498-16-R-5019-0001.pdf PDF
N64498-16-R-5019.pdf PDF
Attachment_10_-Generator_System_Operational_Test_BM.docx DOCX document
Attachment_6_-_Generator_System_Wiring_Diagram.pdf PDF
Attachment_4b_-_Welding_Tasks_Electrical_Isolation_Tech_Refresh.pdf PDF
Attachment_1_-_Alarm_Set_Points_(2).pdf PDF
Copy_of_Attachment_3_-_DEIF_Configuration_Parameter.xlsx XLSX spreadsheet
Attachment_2_-_Crafts_Network_Diagram_(2).pdf PDF
Attachment_7_-_Switchboard_System_Wiring_Diagram.pdf PDF
Attachment_5_-_Crompton_Configuration_Parameter.pdf PDF
cdrls.pdf PDF
Attachment_8_-_Generator_and_Switchboard_System_Input_Output_Test.docx DOCX document
Attachment_11_-Switchboard_System_Operational_Test_WT_PM.docx DOCX document
Attachment_8_Appendix_-_Generator_and_Switchboard_System_IO_Table.pdf PDF
Attachment_14_-_S9074-AR-GIB-010_278.pdf PDF
Attachment_4a_-_Welding_Tasks_Electrical_Isolation_Non_Tech.pdf PDF
Attachment_13_-_S0400-AD-URM-010_TUM.pdf PDF
N64498-16-R-5019.pdf PDF
Attachment_9_-_Generator_System_Operational_Test_WT_PM.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IMPROVED NAVY LIGHTERAGE SYSTEM (INLS)

CONTRACT NO.

CDRL DATA ITEM NO:

Test Title:Switchboard System Operational Test
(Beach Module)
Test No:

Revision:

Hull:

TEST PROCEDURE PREPARATION/APPROVAL

PREPARED BY:

K. Fischer

DATE:

July 2015

APPROVED BY:

DATE:

TEST PROCEDURE CONDUCT

CONTRACTOR:
DATE:
GOV. WITNESS:
DATE:
TEST TITLE:TEST NO:HULL NO:
Beach Module Bow Ramp Operational Test169-00001BM X

REVISION RECORD

REV
AFFECTED

PAGES

DESCRIPTION
APPROVED

Original Issue

TEST OBJECTIVE:

The objective of this test is to demonstrate satisfactory SSDG control features, manual and automatic.

EQUIPMENT INVOLVED:

1. Ship Service Generator

2. Ship Service 460V Distribution Switchboard

REFERENCES:

1. IEEE – 45, section 34.2.1, Ship Test, New Installations, Circuits

2. Electrical One Line diagram, NAVFAC Dwg 1600428

3. BM Switchboard drawing

SAFETY PRECAUTIONS:

1. Test personnel shall strictly adhere to all shipyard safety precautions including, but not limited to all CAUTION and WARNING notes contained in this test procedure and applicable documents.

2. All unauthorized personnel shall be kept clear of test areas for duration of test. Persons in adjacent areas shall be notified of testing being done.

3. Arc Flash safety gear must be worn when exposed to energized circuits above 230 VAC.

4. Ensure all power sources are de-energized during insulation resistance tests.

5. Observe Wattmeter and Ammeter during voltage adjustment demonstration to prevent overloading generator.

6. In the event of unusual noise or vibration, shut down the unit.

PREREQUISITES:

1. Generator and Switchboard System Cable Test

2. Generator and Switchboard System Input Output Test

3. Generator System Operational Test BM

ADDITIONAL INSTRUCTIONS:

1. Prior to the performance of this test, ascertain that the minimum requirements necessary for the start of this test have been met. Enter all deviations from the minimum requirements on the comment sheet. Verify test equipment is in current calibration and record the information on the Test Equipment data Sheet.

2. The test conductor will list on comment sheet, any discrepancies requiring corrective action, any unusual response observed while performing test or any significant events and observations occurring during performance of the test. If hazardous conditions exist, test is to be stopped until conditions are corrected.

3. Verify calibration of installed instruments and equipment to be used during test is complete.

4. All breakers on switchboard shall be secured during test. Vessel lighting electrical loads should be fed from a shore power supplied source the duration of the test.

5. Controls and indicators not specifically mentioned in this procedure shall be observed for proper operation.

6. Read the entire test procedure prior to initiating the tests described herein. Verify test equipment calibration is current and record equipment used on Test Equipment Log Sheet in this test procedure.

TEST EQUIPMENT REQUIRED TO ACCOMPLISH THIS TEST PROCEDURE:

QTY DESCRIPTION DESIGN TEST READING (DTS)

(1)Multi Meter
(1)Megger500 VDC, Conforming to type GC or
GM of MIL-0-16485 (or equal) SCAT
4452.
(1)Stop Watch

PERSONNEL REQUIRED TO ACCOMPLISH THIS TEST PROCEDURE:

1. Two Electricians and one Machinery Installer

GOVERNMENT SUPPORT PERSONNEL:

1. Subject Matter Expert (SME): One SME, ISEA/SSA/PE or equivalent to witness and sign off on testing as Government Representative.

2. Ship’s Force personnel to stand by as safety watch, as necessary.

3. Ship’s Force engineer to align machinery as required.

4. Ship’s Force ET to support electrical checks and system alignment.

5. Contractor will require 4 hours of ISEA or SSA support. This support must be scheduled with the ISEA or SSA at least two weeks in advanced.

EQUIPMENT CONFIGURATION:

1. Propulsion engines and marine gears shall have all fluids checked and filled to their service levels.

2. Ensure starting batteries have been charged.

3. Align fuel oil system for normal operation.

4. Ensure LOS panel is turned on and ready for operation.

TEST INSTRUCTIONS:

1.
INSULATION RESISTANCE OF THE BUSSES

1. Disconnect all generator terminations and remove all fuses at the switchboard.

2. Test the insulation resistance of each phase of the bus to ground and phase to phase at 500 VDC. Record the readings on the data sheet.

3. Reconnect all generator terminations and reinstall the fuses at the switchboard.

4. Verify the following connections:a. 460 VAC from each generator and shore power breaker.
b. 120 VDC for each space heater and control power at the switchboard.
c. 24 VDC control power for each generator and the switchboard.

5. Align all auxiliary equipment to support the SSDG under full load conditions.

6. Inspect all relays, circuit breakers and fuses. Ensure they are clean and properly installed.

INSULATION RESISTANCE DATA
MEASUREMENT

A-PHASE BUS TO GROUND

B-PHASE BUS TO GROUND

C-PHASE BUS TO GROUND

A-PHASE BUS TO B-PHASE BUS

B-PHASE BUS TO C-PHASE BUS

A-PHASE BUS TO C-PHASE BUS

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
2.
24VDC CONTROLS OPERATION

1. Place the SSDG MODE switch in the MANUAL position and verify the 1MSR relay has energized.

2. Rotate the MODE switch to AUTO and verify the 1ASR relay has energized and input 1 on the PLC Input module has energized.

3. Rotate the MODE switch to PM and verify the 1PMR relay has energized and input 2 on the PLC Input module has energized.

4. Using an ohmmeter, verify contact closure between 1FTB1 terminals 6 and 7 when the speed adjust switch is in the raise position and terminals 6 and 8 when the speed adjust switch is in the lower position.

5. Using an ohmmeter, verify the change of resistance between 1FTB1 terminals 9 and 10 when the voltage adjust switch is in raise position then lower position.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
3.
460 VAC SWITCHBOARD OPERATIONS

1. Manually start the generator and bring up to rated speed.

2. Verify proper operation of the following devices:

a.Generator voltmeter and switch operation
b.Generator frequency meter operation
c.Generator Power Available light
d.Circuit Breaker Open light

3. At the main switchboard, verify the proper operation of the SPR (Crompton System Protection Relay) metering functions.

4. Place the MODE switch in the MANUAL position.

5. Push the circuit breaker CLOSE push button and verify the following:

a.Generator circuit breaker closes
b.Generator CIRCUIT BREAKER CLOSE light illuminates
c.Generator CIRCUIT BREAKER OPEN light extinguishes

6. Push the circuit breaker OPEN push button and verify the following:

a.Generator circuit breaker opens
b.Generator CIRCUIT BREAKER OPEN light illuminates
c.Generator CIRCUIT BREAKER CLOSE light extinguishes

7. Record satisfactory or unsatisfactory performance on the data sheet.

460 VAC CIRCUIT BREAKER AND METER OPERATION

SSDG

VOLTMETER AND SWITCH

SAT
UNSAT

FREQUENCY METER

SAT
UNSAT

POWER AVAILABLE LIGHT

SAT
UNSAT

CIRCUIT BREAKER OPEN LIGHT

SAT
UNSAT

SPR METERING FUNCTIONS

SAT
UNSAT

CIRUIT BREAKER CLOSES

CIRCUIT BREAKER CLOSE LIGHT ILLUMINATES

CIRCUIT BREAKER OPEN LIGHT EXTINGUISHES

SAT
UNSAT

CIRCUIT BREAKER OPENS

CIRCUIT BREAKER CLOSE LIGHT EXTINGUISHES

CIRCUIT BREAKER OPEN LIGHT ILLUMINATES

SAT
UNSAT
______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
4.
GENERATOR SPACE HEATER OPERATION

1. Connect a 120VAC, 1 Ø power source at terminals 1 and 2 of 1FTB. Turn the GENERATOR HEATER switch to the ON position.

2. With the SSDG circuit breaker open the GENERATOR SPACE HEATER light should be illuminated.

3. Close the generator circuit breaker; the GENERATOR SPACE HEATER light should be extinguished.

4. Remove the power source from 1FTB.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
5.
SWITCHBOARD SPACE HEATER OPERATION

1. Connect a 120 VAC, 1 Ø power source at TB1 terminals 1 and 2. Turn the switchboard heater to the ON position and verify 120 VAC is available at the cabinet heater.

2. Use a heat gun to warm the element on the cabinet heater thermostat and verify the thermostat de-energizes the cabinet heater.

3. Turn the heater switch to the OFF position and remove the power source.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
6
GENERATOR AUTO OPERATION

1. Place SSDG mode switch in AUTO. SSDG circuit breaker should close automatically.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
7
GENERATOR POWER MANAGEMENT OPERATION

1. Place SSDG mode switch in PM. Close the breaker from MCC/LOS console. SSDG circuit breaker should close automatically.

2. Activate the 1PM1 relay; SSDG circuit breaker should open.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
8
GROUND DETECTION

1. With either of the generators on-line verify that all ground phase green LED lights are flashing and all red LED lights are off.

2. Using a jumper, ground the Phase A bus of the switchboard. The Phase A green LED should go out and the Phase A red LED should flash. Remove the ground wire and press the LAMP TEST pushbutton. Verify the LED lights return to the pre-test condition.

3. Repeat step 2 on the Phase B bus.

4. Repeat step 2 on the Phase C bus.

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE
9
VOLTAGE REGULATOR TEST

NOTE: This test is conducted in a NO LOAD condition. Place the AUTO/MANUAL switch on the circuit breaker to MANUAL. The generator circuit breakers should remain open.

1. Manually start SSDG and bring it up to rated speed.

2. Verify the line voltage is 460 VAC and the frequency is 60 HZ.

3. Adjust the voltage to the minimum and maximum limits and record on data sheet. Reset the voltage adjustment to 460 VAC.

4. Adjust the speed control to the minimum and maximum limits and record on data sheet. Record the elapsed time from minimum to maximum on the data sheet.

VOLTAGE REGULATOR TEST
SSDG #2
460 VAC
SAT
UNSAT

426.5 VAC MINIMUM

481.5 VAC MAXIMUM

SAT
UNSAT

SPEED CONTROL OPERATION

MINIMUM FREQUENCY

MAXIMUM FREQUENCY

ELAPSED TIME FROM MINIMUM TO MAXIMUM

______________________________________________________________________________________
TEST CONDUCTORGOVERNMENT WITNESSDATE

SHUTDOWN PROCEDURES:

1. Return all machinery and switchboards to pre-test conditions.

2. Perform a visual inspection of the generator sets for liquid leaks, loose fittings, or loose connections.

TEST EQUIPMENT

NAME
MODEL

NUMBER

SERIAL

NUMBER

CALIBRATION

DUE DATE

REMARKS/WITNESS

CONTRACTOR:
DATE:
GOVERNMENT REP:
DATE:

TEST TITLE: TEST NO: REV

Switchboard System Operational Test BM

NUMBER
COMMENTS
CONTRACTOR:
DATE:
GOVERNMENT REP:
DATE:
NUMBER
OPEN ITEMS AND CORRECTIONS
CONTRACTOR:
DATE:
GOVERNMENT REP:
DATE:
NUMBER
TEST RESULTS SUMMARY

This test was conducted in accordance with this test procedure; no adjustments were made to equipment under test except as required by the test procedure, and the results of the test are as stated in this report.

CONTRACTOR:
DATE:
GOVERNMENT REP:
DATE: