21R1339 Note 3.pdf
PDF 220 KB Posted
- Solicitation number
- N6274221R1339
About this file
This document contains questions and answers related to a solicitation for a water well field construction project on Guam. The solicitation seeks the construction of a water well system including wells, transmission lines, water treatment facilities, storage, and a pump station. Two well sites will include generator buildings while others will have electrical buildings. The Navy's Naval Facilities Engineering Command issued the solicitation. Key issues addressed in the questions and answers include consideration of an economic price adjustment clause due to materials price volatility, the evaluation of partially completed water tank projects, clarification of insulation and signage requirements, and locations for contractor facilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21R1339_AMD5.pdf | ||
| 21R1339 Note 11.pdf | ||
| 21R1339 Note 10.pdf | ||
| 21R1339_AMD4.pdf | ||
| 21R1339 Note 9.pdf | ||
| 21R1339_AMD3.pdf | ||
| 21R1339 Note 8.pdf | ||
| 21R1339_AMD2.pdf | ||
| 21R1339_AMD2_Drawings.pdf | ||
| 21R1339 Note 7.pdf | ||
| 21R1339 Note 6.pdf | ||
| 21R1339 Note 5.pdf | ||
| 21R1339_AMD1.pdf | ||
| 21R1339_AMD1_Drawings.pdf | ||
| P103 SV Sign-in.pdf | ||
| 21R1339 Note 4.pdf | ||
| 21R1339 Note 2.pdf | ||
| 21R1339 Note 1.pdf | ||
| 21R1339-RFP.pdf | ||
| P-103 Water Well Field_Specifications.pdf | ||
| P-103 Water Well Field_DWGS.pdf | ||
| 21R1339-JA_Redacted.zip | ZIP file |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice No. 3
19 August 2021
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-21-R-1339
FY18 MCON P-103 WATER WELL FIELD US NAVSUPACT ANDERSEN, GUAM
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
3. Ref. Document 00700 (RFP). Given the current extreme volatility in construction materials pricing (steel, lumber, electrical, plastic products, etc.), manufacturers and suppliers are unwilling to commit to pricing beyond 30 to 60 days. This places an enormous pricing risk on prime contractors and subcontractors including many small business firms that would like to compete for this project. With this material pricing uncertainty facing the U.S. construction industry, it’s very difficult and costly to submit firm fixed prices. There is a fair and equitable solution available under FAR 52.216-4 Economic Price Adjustment-Labor and Material. This clause protects both the Government and the contractor from price fluctuations. In reviewing the list of FAR clauses included in the RFP solicitation documents, FAR 52.216-4 was not included.
Please consider adding FAR 52-216-4 to the solicitation to provide a fair and equitable clause that will help all parties including the Government, contractor and subcontractors avoid uncontrollable price increases due to the volatile materials market.
ANSWER: The Government has considered your request, however, the RFP remains unchanged.
4. Ref. Document 00202 (RFP) Factor 1- Experience. Paragraph (a) Relevant Construction Project Item (4). Reference Document 00202 Technical Evaluation Factors, Factor 1 – Experience, page 3, Relevant Construction Project item (4) “New construction of Wire wound circular pre-stressed concrete water tank approximately 250,000 gallons or more”. Will the Government consider a project of which only the Wire Wound pre-stressed concrete water tank with a capacity of 1,600,000 gallons of the work is more than 90% complete, accompanied with a signed Past Performance Questionnaire (PPQ) from the Owner? Please confirm if this will be considered relevant under the Relevant Construction Project item (4).
ANSWER: The Government does not pre-evaluate proposals. RFP Document 00202 remains unchanged.
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC
258 MAKALAPA DRIVE, SUITE 100
JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134
5. The RFP for P103 Water Well scope of work requires construction of Treatment/Transfer Pump Station, Generator Building and Electrical Building. There is nothing mentioned on the drawing and specification about the Termite Control for soil treatment under the slab on grade or wall footing foundation. Please confirm if Termite Control is required.
ANSWER: Termite control is required. The requirement for termite control will be issued under a forthcoming amendment.
6. Ref. Drawing Sheet 171 of 377 A-103. Gypsum board on Metal Framing with Air Barrier Insulation R-11. On the drawing A-103, Electrical Room shows the two internal walls having the gypsum board and air barrier insulation installation. However, the drawing A-101 and A-105 show only one side of the internal wall is required to install the gypsum board and air barrier insulation. Please confirm which internal walls needs installation of the gypsum board and insulation on electrical room.
ANSWER: All the exterior walls at the Electrical and Telecom Room require gypsum board and air barrier insulation as shown on NAVFAC Drawing Number 17241597, A-101. Interior demising walls do not require insulation.
7. Ref. Drawing Sheet 183 of 377 A-503. Eave/Gutter Detail #2. Please confirm if the Fluid Applied Roofing with Reinforcing Fabric is not required on the horizontal inner surface of the gutter as shown on the drawing A-503, Eave/Gutter Detail #2. Only the vertical surface with 100mm and 200mm is required to apply.
ANSWER: Provide reinforcing fabric on the horizontal surfaces of the gutter in accordance with Specification Section 07 14 00 FLUID APPLIED WATERPROOFING. See forthcoming amendment.
8. Ref. Drawing Sheet 172 of 377 A-104. Exterior Signage. On the drawing A-104, the Treatment/Transfer Pump Station doesn’t have any building exterior signage. Please confirm if there is a need to install a building exterior signage for the Treatment/Transfer Pump Station.
ANSWER: Provide exterior signage at the Treatment/Transfer Pump Station. See forthcoming amendment.
9. Ref. Specification Section 01 57 19 Page 21. 3.2.4 Contractor Facilities and Work Areas.
Specification Section 01 57 19 Paragraph 3.2.4: The Contractor Facilities and Work Areas states that "Place field offices, staging areas, stockpile storage, and temporary buildings in areas designated on the drawings or as directed by the Contracting Officer." However, there is nothing shown on the drawing the location for field offices, staging areas and/or stockpile storage. Please provide the location for these temporary facilities.
ANSWER: The locations of the Contractor’s facilities and work areas will be directed by the Contracting Officer.
10. Ref. Drawing Sheet 92 of 377 CU-501. Trench Detail Pipe A1, A4, B4 and C1.
Specification Section 31 23 00.00 20 Page 17. 3.7.5.1 Pipe Bedding (Initial Backfill). There is nothing mentioned about the material specification for pipe bedding on the drawing CU-501 and Specification Section 31 23 00.00 20 paragraph 3.7.5.1 “Pipe Bedding (Initial Backfill)”. Please provide.
ANSWER: The pipe bedding material specification is stated in Specification Section 31 23
00.00 20 Paragraph 2.3 Utility Bedding Material.
11. Ref. Drawing Sheet 185, 193, and 194 of 377 F-001, F-103, and F-104. Fire Protection Symbols and Abbreviations. On drawings F-103 and F-104, the “S▲” was used multiple times.
The “Fire Protection Symbols and Abbreviations” table on drawing F-001 does not indicate the description of this symbol. Please provide the description for this symbol.
ANSWER: The symbol represents fire alarm speakers. Horns will be required instead of fire alarm speakers. See forthcoming amendment.
End of Notice