About this file

This document includes a notice and questions and answers related to solicitation N62742-21-R-1337. The notice provides responses to three questions from potential offerors. Question one asks if concrete encased duct banks require reinforcing, to which the response is that the designer of record will determine if reinforcement is required based on conditions. Question two asks about minimum burial depth of telecom ducts, with the response that the designer of record will determine the depth. Question three asks if all metal parts of telecom handholes need to be 316 stainless steel, with the response that no new telecom handholes are included in this project's scope of work.

The related federal contract opportunity is solicitation N6274221R1337 for the construction of eight new earth covered munitions storage igloos and magazines at Andersen Air Force Base, Guam. The work includes structural, lightning protection, mechanical and earth berm work for the igloos, along with site improvements, roadways, aprons, utilities and incidental work. Four optional igloos are also included to be constructed if options are exercised within 365 days of award. The Department of the Navy Naval Facilities Engineering Command is the contracting agency.

View the file

Other files

File Type Posted
21R1337_AMD5.pdf PDF
21R1337 Note 8.pdf PDF
21R1337 Note 7.pdf PDF
21R1337_AMD4.pdf PDF
21R1337 Note 5.pdf PDF
21R1337 Note 6.pdf PDF
21R1337_AMD3.pdf PDF
21R1337 Note 4.pdf PDF
21R1337 Note 3.pdf PDF
21R1337_AMD2.pdf PDF
P1366 SV SignIn.pdf PDF
21R1337 Note 2.pdf PDF
21R1337_AMD1.pdf PDF
1a_P-1366 - Final RFP - DB RFP.pdf PDF
1b_P-1366 - Final RFP - Drawings.pdf PDF
21R1337-RFP.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Notice No. 1 20 July 2021

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-21-R-1337

FY 22 MCAF P-1366/AJJY073105P2, APR-MUNITIONS STORAGE IGLOOS, PHASE 2,

ANDERSEN AIR FORCE BASE, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

1. Do the concrete encased duct banks require reinforcing?

ANSWER: Part 3, ESR G40, paragraph G403004 Ductbanks, Manholes, and Handholes does not specifically require reinforcing of concrete encased ductbanks. However, it is the responsibility of the Designer of Record to determine if reinforcement is required due to conditions such as insufficient burial depth, crossings with other utilities, seismic conditions, etc.

2. What is the minimum burial depth of the telecom ducts.

ANSWER: To be determined by Designer of Record. Duct banks must tie into stub-outs constructed under a separate project, FY20 MCAF Project P-3105/AJJY073105P3 Hayman Munition Storage Igloos (Phase 3).

3. Please advise if all metal parts of the telecom handhole need to be 316 stainless steel.

ANSWER: This project does not include the construction of new telecom handholes. All telecom handholes are constructed under a separate project, FY20 MCAF Project P- 3105/AJJY073105P3 Hayman Munition Storage Igloos (Phase 3).

End of Notice

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, PACIFIC

258 MAKALAPA DRIVE, SUITE 100

JOINT BASE PEARL HARBOR HICKAM, HAWAII 96860-3134