TGI_3819P22115A07_c0v0.pdf

PDF 55 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA TYCOM 7 (YOKOSUKA, JAPAN)
Solicitation number
N6264925RA059
Issued by

About this file

This Task Group Instruction (TGI) details an inspection of the 1B Boiler handhole and manhole seats and plates on the USS Blue Ridge (LCC-19), scheduled for execution between January 12, 2026, and May 15, 2027. The comprehensive inspection involves examining multiple components across various boiler headers and drums, including 7 handhole seats/plates on the rear wall header, 15 each on superheater inlet and outlet headers, 5 on screen wall header, 8 on side wall header, 2 manhole seats/plates on the steam drum, and 1 on the water drum.

The TGI specifies that SRF-JRMC will provide supporting services including crane and rigging, electrical and utility services, safety and gas-free inspections, and quality assurance inspections. The work is in response to a Boiler Inspection and Repair Management Information System (BIRMIS) report dated October 17, 2024, and is associated with Job Control Number EM02-L192. The inspection requires adherence to specific naval standard items and technical manual guidelines, with a cleanliness requirement for piping system/equipment at Level II.

View the file

Other files

File Type Posted
N6264925RA059-0006.pdf PDF
Attachment II Price Proposal Breakdown Form N6264925RA059_REV1.xlsx XLSX spreadsheet
N6264925RA059-0005.pdf PDF
TGI 3819P65416A01_c1v2.pdf PDF
N6264925RA059-0004.pdf PDF
TGI 3819P22114A12_c0v1.pdf PDF
N6264925RA059-0003.pdf PDF
DWG_NMP-162_D_.pdf PDF
TGI 3819P43701A01_c2v1.pdf PDF
DWG_2492510_81994_C_.pdf PDF
N6264925RA059-0002.pdf PDF
TGI_3819P22114A11_c1v2.pdf PDF
N6264925RA059-0001.pdf PDF
TGI_3819P123AGT02_c0v0-TT_rev.pdf PDF
TGI_3819P22114A11_c1v1.pdf PDF
TGI_3819P123AGT08_c0v0.pdf PDF
Attachment III Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_3819P25001T03_c0v0.pdf PDF
TGI_3819P22114A13_c0v1.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P43701T01_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P22124A01_c0v0.pdf PDF
TGI_3819P22114A17_c0v0.pdf PDF
TGI_3819P25001A01_c1v0.pdf PDF
TGI_3819P65416A01_c0v1.pdf PDF
TGI_3819P22114A08_c1v1.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
TGI_3819P22115A10_c0v0.pdf PDF
TGI_3819P22115A04_c0v0.pdf PDF
TGI_3819P22115A08_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P22115A02_c1v1.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114A09_c1v1.pdf PDF
TGI_3819P123AGT06_c0v0.pdf PDF
TGI_3819P22115T03_c0v0.pdf PDF
TGI_3819P123AGT05_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
TGI_3819P22114A03_c2v2.pdf PDF
TGI_3819P22114A04_c1v1.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P25507A01_c0v0.pdf PDF
TGI_3819P43701T02_c0v0.pdf PDF
TGI_3819P123AGT07_c0v0.pdf PDF
TGI_3819P25001T02_c0v0.pdf PDF
TGI_3819P22114A06_c1v1.pdf PDF
TGI_3819P22115A12_c0v0.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

05-MAR-2025 1725

20.14.15.2.9020 (September 2024) ICN: 3819P22115 KeyOp: A07

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BOILER BO A 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: *(BIRMIS) F/O - INSPECT 1B BOILER HANDHOLE, MANHOLE SEAT AND PLATE

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

EM02L192

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

KIMURA, REIYA 234 7076038983 11-FEB-2025

APPROVED BY: CODE: PHONE: DATE:

HARADA, HIDEO 234 3152435176 12-FEB-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM02-L192

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE 8-76-0-E U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1115

1. SCOPE/PURPOSE:

1.1 Title: 1B Boiler Handhole, Manhole Seat and Plate; inspect

1.2 Location of Work:

1.2.1 Fire Room (8-76-0-E)

1.3 Identification:

1.3.1 Quantity (One EA), Boiler, Main Propulsion, 1B

Mfr: Foster Wheeler Corp Mfr ID: N/A Design Pressure: 705 PSIG Max Operating Pressure: 655 PSIG

CAGE: 23230

APL: 021550096

TGI Short Form

05-MAR-2025 1725

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A07

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BOILER BO A 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: *(BIRMIS) F/O - INSPECT 1B BOILER HANDHOLE, MANHOLE SEAT AND PLATE

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

1.3.1.1 Quantity (7 EA), Seat and Plate, Handhole, Rear Wall Header

1.3.1.2 Quantity (15 EA), Seat and Plate, Handhole, Superheater Inlet Header

1.3.1.3 Quantity (15 EA), Seat and Plate, Handhole, Superheater Outlet Header

1.3.1.4 Quantity (5 EA), Seat and Plate, Handhole, Screen Wall Header

1.3.1.5 Quantity (8 EA), Seat and Plate, Handhole, Side Wall Header

1.3.1.6 Quantity (2 EA), Seat and Plate, Manhole, Steam Drum

1.3.1.7 Quantity (1 EA), Seat and Plate, Manhole, Water Drum

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor Start Date: 1/12/2026

1.7 Contractor Work Completion Date: 5/15/2027

2. PROCEDURE:

2.1 Accomplish the requirements of 009-62 of Ref. No. One for the handhole and manhole listed in 1.3.1.1 through 1.3.1.7, using Ref. No. 3 for guidance.

2.1.1 Accomplish the requirements of 099-906YO of Ref. No. 2.

2.1.1.1 Accomplish the requirements of 009-09 of Ref. No. One.

2.2 Notes:

2.2.1 Planner: Code 234 R. Kimura, 070-7603-8983

2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.2.3 Removal and Installation of each handhole plate and manhole plate is covered by TGI No. 3819P22102A01.

2.2.4 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1B Boiler report dated 17 OCT 2024, Line item “F14-01, G13-01, and I-01”.

2.2.5 JCN EM02-L192 is related to this TGI.

2.3 Government Furnished Material (GFM): None.

2.4 SRF-JRMC will provide the following service work: (TGI No: 3819P22115S08)

05-MAR-2025 1725

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A07

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BOILER BO A 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: *(BIRMIS) F/O - INSPECT 1B BOILER HANDHOLE, MANHOLE SEAT AND PLATE

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

2.4.1 [C740] Crane and crane rigging service.

2.4.2 [X99E] Provide utility service, electrical.

2.4.3 [X99M] Provide utility service, including low pressure air supply, water supply, and steam supply.

2.4.4 [C106.1] Provide safety inspection for SRF-JRMC employees.

2.4.5 [C106.2] Provide gas free inspection for SRF-JRMC employees.

2.4.6 [C133] Provide QA inspection for (G) symbols.

05-MAR-2025 1725

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22115 KeyOp: A07

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 1B BOILER BO A 8 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: *(BIRMIS) F/O - INSPECT 1B BOILER HANDHOLE, MANHOLE SEAT AND PLATE

FOUO Pg 4 of 4

OTHER SPECIAL REQUIREMENTS:

CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL II.

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

3 TM S9221-C1-GTP-

MAIN PROPULSION BOILERS;

VOL 1, REPAIR & OVERHAUL

5 N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 BLRM HRs, QA HRs 22/KE PC N

CFM for MISC such as temporary enclosure and covering material, plastic bags, and etc.

22/MQ CS N

Process Funding Document 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22115 KEY OP: A07