This document is a Task Group Instruction (TGI) for a hydrostatic test on Boiler #1A Desuperheater for the USS Blue Ridge (LCC-19), dated 06-MAY-2025. The TGI provides detailed instructions for contractor, quality assurance (QA), and support/field (S/F) work to accomplish and document the hydrostatic test in accordance with technical procedure TP 22111-2-101KTR. The document includes preparation details such as the preparing activity (Nakajima, Hisato), approval (Ohta, Jason Y.), and zone management (Takahashi, Yasuhiko), with a focus on executing a tightness test for the specified boiler component. The document is marked FOUO (For Official Use Only) and contains specific technical and administrative tracking information for the naval maintenance task.

View the file

Other files

File Type Posted
N6264925RA059-0006.pdf PDF
Attachment II Price Proposal Breakdown Form N6264925RA059_REV1.xlsx XLSX spreadsheet
N6264925RA059-0005.pdf PDF
TGI 3819P65416A01_c1v2.pdf PDF
N6264925RA059-0004.pdf PDF
TGI 3819P22114A12_c0v1.pdf PDF
N6264925RA059-0003.pdf PDF
DWG_NMP-162_D_.pdf PDF
TGI 3819P43701A01_c2v1.pdf PDF
DWG_2492510_81994_C_.pdf PDF
N6264925RA059-0002.pdf PDF
TGI_3819P22114A11_c1v2.pdf PDF
N6264925RA059-0001.pdf PDF
TGI_3819P123AGT02_c0v0-TT_rev.pdf PDF
TGI_3819P22114A11_c1v1.pdf PDF
TGI_3819P123AGT08_c0v0.pdf PDF
Attachment III Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_3819P25001T03_c0v0.pdf PDF
TGI_3819P22114A13_c0v1.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P43701T01_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P22124A01_c0v0.pdf PDF
TGI_3819P22114A17_c0v0.pdf PDF
TGI_3819P25001A01_c1v0.pdf PDF
TGI_3819P65416A01_c0v1.pdf PDF
TGI_3819P22114A08_c1v1.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
TGI_3819P22115A10_c0v0.pdf PDF
TGI_3819P22115A04_c0v0.pdf PDF
TGI_3819P22115A08_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P22115A02_c1v1.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114A09_c1v1.pdf PDF
TGI_3819P123AGT06_c0v0.pdf PDF
TGI_3819P22115T03_c0v0.pdf PDF
TGI_3819P123AGT05_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
TGI_3819P22114A03_c2v2.pdf PDF
TGI_3819P22114A04_c1v1.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P25507A01_c0v0.pdf PDF
TGI_3819P43701T02_c0v0.pdf PDF
TGI_3819P123AGT07_c0v0.pdf PDF
TGI_3819P25001T02_c0v0.pdf PDF
TGI_3819P22114A06_c1v1.pdf PDF
TGI_3819P22115A12_c0v0.pdf PDF
EXHIBIT - Contract Data Requirements List (CDRL).pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

06-MAY-2025 1554

20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: T06

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-2-101KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: BOILER 1A, DESUPERHEATER (T) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

EM01ZAG1 * EM01ZAG3 * EM01ZAK5 * EM01ZAG9 * EM01ZAH0 * EM01ZAH3 * EM01ZAH6 * EM01ZAH8 * EM01ZAI0 *

EM01ZAI1 * EM01ZAI3 * EM01ZAI7 * EM02L194

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

NAKAJIMA, HISATO 246.2 3152434197 17-APR-2025

APPROVED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 05-MAY-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM01-ZAG1 * EM01-ZAG3 * EM01-ZAG9 * EM01-ZAH0 * EM01-ZAH3 * EM01-ZAH6 * EM01-ZAH8 * EM01-ZAI0 * EM01-ZAI1 *

EM01-ZAI3 * EM01-ZAI7 * EM01-ZAK5 * EM02-L194

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

TAKAHASHI, YASUHIKO U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1114, more...

Tightness Test for Boiler #1A, Desuperheater.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

06-MAY-2025 1554

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: T06

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 22111-2-101KTR TT T 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 22111

CU PHASE TITLE: BOILER 1A, DESUPERHEATER (T) - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 22111-2-101KTR BOILER 1A (S & T) - KTR LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the hydrostatic test in accordance with reference, TP 22111-2-101KTR.

22/KE PC N

(G) QA work:

Accomplish/document the hydrostatic test in accordance with reference, TP 22111-2-101KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the hydrostatic test in accordance with reference, TP 22111-2-101KTR.

/ EM02 N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22114 KEY OP: T06