This Task Group Instruction (TGI) details preservation work for the USS Blue Ridge's Fire Room (8-76-0-E) bilge area and boiler foundation. The preservation area covers 822 square feet located between Frames 75 and 81 on the starboard side, with work focused on cleaning, drying, and preparing the area free from oil, debris, and foreign matter. The contractor work is scheduled from January 12, 2026, to May 15, 2027, with potential lead hazards noted and a critical coated area identified by document CCNY-LCC19-070-25.

The Task Group Instruction specifies that SRF-JRMC will provide supporting services including crane and rigging, utility services (electrical, low pressure air, water, and steam), safety inspections, gas-free inspections, and quality assurance review of coating application. The work is in response to a Boiler Inspection and Repair Management Information System (BIRMIS) report dated October 17, 2024, and is associated with Job Control Number EM02-L194. No government-furnished material is required, and the preservation work involves labor hours for painters, safety technicians, and quality assurance personnel.

View the file

Other files

File Type Posted
N6264925RA059-0006.pdf PDF
Attachment II Price Proposal Breakdown Form N6264925RA059_REV1.xlsx XLSX spreadsheet
N6264925RA059-0005.pdf PDF
TGI 3819P65416A01_c1v2.pdf PDF
N6264925RA059-0004.pdf PDF
TGI 3819P22114A12_c0v1.pdf PDF
N6264925RA059-0003.pdf PDF
DWG_NMP-162_D_.pdf PDF
TGI 3819P43701A01_c2v1.pdf PDF
DWG_2492510_81994_C_.pdf PDF
N6264925RA059-0002.pdf PDF
TGI_3819P22114A11_c1v2.pdf PDF
N6264925RA059-0001.pdf PDF
TGI_3819P123AGT02_c0v0-TT_rev.pdf PDF
TGI_3819P22114A11_c1v1.pdf PDF
TGI_3819P123AGT08_c0v0.pdf PDF
Attachment III Government Furnished Property (GFP-GFM listings).xlsx XLSX spreadsheet
TGI_3819P25001T03_c0v0.pdf PDF
TGI_3819P22114A13_c0v1.pdf PDF
Attachment V Contract Data Sheet.pdf PDF
TGI_3819P43701T01_c0v0.pdf PDF
TGI_3819P123AGT04_c0v0.pdf PDF
TGI_3819P123AGT12_c0v0.pdf PDF
TGI_3819P22124A01_c0v0.pdf PDF
TGI_3819P22114A17_c0v0.pdf PDF
TGI_3819P25001A01_c1v0.pdf PDF
TGI_3819P65416A01_c0v1.pdf PDF
TGI_3819P22114A08_c1v1.pdf PDF
TGI_3819P22114T06_c0v0.pdf PDF
Attachment VI Quality Assurance Surveillance Plan (QASP).pdf PDF
TGI_3819P22115A10_c0v0.pdf PDF
TGI_3819P22115A04_c0v0.pdf PDF
TGI_3819P22115A08_c0v0.pdf PDF
TGI_3819P22114T03_c0v0.pdf PDF
TGI_3819P22115A02_c1v1.pdf PDF
TGI_3819P22114T05_c0v0.pdf PDF
TGI_3819P22114A09_c1v1.pdf PDF
TGI_3819P123AGT06_c0v0.pdf PDF
TGI_3819P22115T03_c0v0.pdf PDF
TGI_3819P123AGT05_c0v0.pdf PDF
TGI_3819P123AGT01_c0v0.pdf PDF
TGI_3819P22114A03_c2v2.pdf PDF
TGI_3819P22114A04_c1v1.pdf PDF
TGI_3819P123AGT11_c0v0.pdf PDF
TGI_3819P25507A01_c0v0.pdf PDF
TGI_3819P43701T02_c0v0.pdf PDF
TGI_3819P123AGT07_c0v0.pdf PDF
TGI_3819P25001T02_c0v0.pdf PDF
TGI_3819P22114A06_c1v1.pdf PDF
TGI_3819P22115A12_c0v0.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

03-MAR-2025 1339

20.14.15.2.9020 (September 2024) ICN: 3819P22114 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-76-0-E MS A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13011

CU PHASE TITLE: *(D74C-01) F/O - PRESERVE BILGE AREA AND FOUNDATION IN 8-76-0-E

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

EM02L194

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

KUROKAWA, NAOKI 231B 3152430108 24-JAN-2025

APPROVED BY: CODE: PHONE: DATE:

NAKANO, SEIICHI 231B 3152434519 24-JAN-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EM02-L194

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

TAKAHASHI, YASUHIKO 8-76-0-E 8 U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

221A1114

1. SCOPE/PURPOSE:

1.1 Title: Bilge Area and Foundation in 8-76-0-E; preserve

1.2 Location of Work:

1.2.1 Fire Room (8-76-0-E)

1.3 Identification:

1.3.1 Quantity (822 SF), Bilge Area including Boiler Foundation in 8-76-0-E, Frame between 75 and 81, Starboard Remarks: The area is surface where mechanical tool, roller, and brush can be reachable, and the area except chock and fastener.

See Sketch Enclosure-01 for location detail.

1.4 Security Classification: None.

TGI Short Form

03-MAR-2025 1339

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-76-0-E MS A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13011

CU PHASE TITLE: *(D74C-01) F/O - PRESERVE BILGE AREA AND FOUNDATION IN 8-76-0-E

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5 Initial Condition:

1.5.1 Potential Lead Hazard

1.5.2 Critical Coated Area: CCNY-LCC19-070-25 for the area listed in 1.3.1.

1.6 Contractor Work start date: 1/12/2026

1.7 Contractor Work completion date: 5/15/2027

2. PROCEDURE:

2.1 Pump out, clean and dry the bilge area located in 1.2.1 free from oil, debris, and other foreign matter.

2.2 Accomplish the requirements of 009-32 of Ref. No One, including Table 3, Line(s) 13, for each area listed in 1.3.1.

2.3 Notes:

2.3.1 Planner: Code 231B N. Kurokawa, 243-0108

2.3.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.3.3 Provision of oily/chemical water barge will be coordinated by Project Team.

2.3.4 This TGI is response to Boiler Inspection and Repair Management Information System (BIRMIS) for 1A Boiler report dated 17 OCT 2024, Line Item(s) D74C-01.

2.3.5 JCN EM02-L194 is related to this TGI.

2.4 Government Furnished Material (GFM): None.

2.5 SRF-JRMC will provide the following service work: (TGI No. 3819P22114S02)

2.5.1 [C740] Crane and crane rigging service.

2.5.2 [X99E] Utility service, electrical.

2.5.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.5.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.5.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.5.6 [C133] QA inspection for (G) symbol(s) and review coating application data.

03-MAR-2025 1339

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P22114 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 8-76-0-E MS A 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 13011

CU PHASE TITLE: *(D74C-01) F/O - PRESERVE BILGE AREA AND FOUNDATION IN 8-76-0-E

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 LBR HRs 22/KE PC N

2.2 PNTR HRs, SFTR HRs, QA HRs 22/KE PC N

Preservation Work CFM for all paints, thinners, sampler/analyze lead, and MISC such as covering material and other consumable.

22/MQ CS N

Process Funding Document 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 3819P22114A01-Sketch.pdf 24-JAN-2025 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P22114 KEY OP: A01

A

Sheet 1 of 23819P22114A01

SKETCH

ENCLOSURE-01

Naoki.Kurokawa.ja Rectangle

Naoki.Kurokawa.ja_1 Typewritten Text

PLAN VIEW

Naoki.Kurokawa.ja_2 Typewritten Text

INNER BOTTOM

Naoki.Kurokawa.ja_3 Line

Sheet 2 of 23819P22114A01

SKETCH

ENCLOSURE-01

SECTION 2-A

Area excepts chock and fasteners

Naoki.Kurokawa.ja_4 Polygon

Naoki.Kurokawa.ja_5 Polygon

Naoki.Kurokawa.ja_6 Polygon

Naoki.Kurokawa.ja_7 Polygon

File details come from the government source that posted it. Updated .