This document is a Request for Proposal (RFP) for the P1080 Power Reliability and Water Resiliency Upgrades project at Portsmouth Naval Shipyard (PNSY). The project aims to provide increased reliability, resiliency, and capacity to electric and water utility systems critical for protecting nuclear-powered submarines and nuclear support facilities. Key scope elements include constructing a new elevated water tower, upgrading electrical infrastructure like switchgear and substations, installing water mains across bridges, renovating pump stations, and implementing an upgraded microgrid control system. The total contract duration is 1,930 days, with an assumed award date of August 12, 2026, and a proposal response deadline of February 25, 2026.

The solicitation follows a tradeoff source selection process, evaluating proposals based on five non-price factors: Corporate Experience, Scheduling, Small Business Utilization, Safety, and Past Performance. The government requires a minimum of 20% small business participation, with specific targets for different small business categories including 40% Small Business, 3% HUBZone, 5% Service-Disabled Veteran-Owned Small Business, 5% Small Disadvantaged Business, and 9% Women-Owned Small Business. Pricing will be evaluated on a total price basis, including base requirements and option items, with non-price factors considered significantly more important than price. The NAICS code is 237130 for Power and Communication Line and Related Structures Construction, with a size standard of $45,000,000.

View the file

Other files

File Type Posted
Solicitation Amendment 0010.pdf PDF
Attachment G - Price Proposal Form (Revised Amendment 0009).pdf PDF
Solicitation Amendment 0009.pdf PDF
CSRA Risk Capture Form.xlsx XLSX spreadsheet
Solicitation Amendment 0008.pdf PDF
Attachment G - Price Proposal Form (Revised Amendment 0008).pdf PDF
Unitil Subcontracting Redacted.pdf PDF
Solicitation Amendment 0007.pdf PDF
Attachment G - Price Proposal Form (Revised Amendment 0006).pdf PDF
Solicitation Amendment 0006.pdf PDF
Foster Adaptor Redacted.pdf PDF
Attachment M - SITE VISIT ATTENDANCE LOG.pdf PDF
Solicitation Amendment 0004.pdf PDF
Attachment G - Price Proposal Form (Revised Amendment 0004).pdf PDF
Solicitation Amendment 0003.pdf PDF
PPI Responses Amendment 0003.pdf PDF
Solicitation Amendment 0002.pdf PDF
Solicitation Amendment 0001.pdf PDF
Fire Hydrant Redacted.pdf PDF
Backflow Preventer Redacted.pdf PDF
Flow Meter and Strainer Redacted.pdf PDF
Programmable Logic Controllers Redacted.pdf PDF
Attachment E - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment L - Economic Price Adjustment Unit Price Form.pdf PDF
Attachment A - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
Attachment C - Past Performance Questionnaire.docx DOCX document
Attachment D - Historical Small Business Utilization.docx DOCX document
Attachment H - PIEE Vendor Access Instructions.pdf PDF
Attachment I - Approved Identity Proofing Documents.pdf PDF
Solicitation - N6247026R0004.pdf PDF
Attachment B - Construction Experience Project Data.docx DOCX document
Attachment F - Individual Small Business Subcontracting Plan.docx DOCX document
Attachment G - Price Proposal Form.docx DOCX document
Attachment J - Criteria for Denying Access to Navy Installations.pdf PDF
Attachment K - DOD CUI Non-Disclosure Agreement.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): The purpose of this amendment is to:

1) Provide response to PPIs - Supporting documents for Amendment 0004 responses are available via email request to Stephanie Wray at Stephanie.L.

Wray2.civ@us.navy.mil, AND Ed Flint at edward.d.flint.civ@us.navy.mil. Contractors must provide or have provided a completed Attachment K to obtain.

2) Update the specifications as indicated in the attached specification continuation sheet.

3) Extend the proposal due date to 25 February 2026.

4) Provide additional J&A.

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Response Due Date 10 Feb 2026 25 Feb 2026

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

The following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO CHANGED

BY

Description

BASE PRICE: Total Price for Project P- 1080 On-Base Power Electrical Improvements for Drawing Work Areas A, B, C, D, E, F, G, H, J, L, M, N, O, and Other Costs as noted below. The project objectives are to provide upgrades and modifications to shipyard power distribution, energy storage, and onsite generation to increase capacity, capability, and resiliency of the power system in accordance with the drawings and specifications complete, but excluding work provided in another Priced line Item.

BASE PRICE: Total Price for Project P-1080 On- Base Power Electrical Improvements CLINs 0001.A thru 0001.AC for Drawing Work Areas A, B, C, D, E, F, G, H, J, L, M, N, O, and Other Costs as noted below. The project objectives are to provide upgrades and modifications to shipyard power distribution, energy storage, and onsite generation to increase capacity, capability, and resiliency of the power system in accordance with the drawings and specifications complete, but excluding work provided in another Priced line Item. See Drawings G-015 thru G-023 for Work Area Designations.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0002

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 1: Total Price to Furnish and Install the New 16" Water Main from the connection at the Kittery Water District Main to Gate #2 Metering Pit, across Bridge #2, Wyman Ave to the Bldg. 163 Pump Station, and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage and any Rail Impacts as shown in Work Areas R, S F, and T. Pricing to include excavation, shoring, Bridge 2 Pipe Structural Framing and Supports, New pipe main installation, Testing, Insulation and Jacketing

OPTION ITEM No. 1: Total Price to Furnish and Install the New 16" Water Main from the connection at the Kittery Water District Main to Gate #2 Metering Pit, across Bridge #2, Wyman Ave to the Bldg. 163 Pump Station, and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage and any Rail Impacts as shown in Work Areas R, S F, and T.

Pricing to include excavation, shoring, Bridge 2 Pipe Structural Framing and Supports, New pipe main installation, Testing, Insulation and Jacketing above ground, Backfill, Temporary

N6247026R00040005 above ground, Backfill, Temporary Paving, Traffic Control, Bridge and Surface Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological Monitoring, Site Improvements, Site Restoration, etc., and General Conditions as required per plans and specifications to complete this Option Item.

Paving, Traffic Control, Bridge and Surface Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological Monitoring, Site Improvements, Site Restoration, etc., and General Conditions as required per plans and specifications to complete this Option Item.

See Drawings G-015 thru G-023 for Work Area Designations.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0003

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0004

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 3: Total Price to Remove the Existing 8" Water Main. Furnish and Installation of the 12" Water Main along Meade Ave to the connection @ Building 403, the abandonment and fill of the existing 8", and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage shown in Work Area R. Pricing to include excavation, shoring, pipe bedding, pipe main installation, testing, backfill, temporary paving, traffic control, and surface restoration as required per plans and specifications

OPTION ITEM No. 3: Total Price to Remove the Existing 8" Water Main. Furnish and Installation of the 12" Water Main along Meade Ave to the connection @ Building 403, the abandonment and fill of the existing 8", and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage shown in Work Area R. Pricing to include excavation, shoring, pipe bedding, pipe main installation, testing, backfill, temporary paving, traffic control, and surface restoration as required per plans and specifications.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0005

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0006

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 5: Total Price to Furnish and Install the New 20" Water Main from the connection at the Kittery Water District Main to Gate #1 Metering Pit, across Bridge #1 to the Bldg. 163 Pump Station, Removal of the Existing 12" Main, and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage and Rail Impacts shown in Work Areas R, S, and T. Pricing to include excavation, shoring, Bridge 1 Pipe Structural Framing and Supports, New pipe main installation, Testing, Insulation and Jacketing above ground, Backfill, Temporary Paving, Traffic Control, Bridge and Surface Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological Monitoring, Third Party Commissioning, Site Improvements, Site Restoration, etc., and General Conditions as required per plans and specifications to complete this Option Item.

OPTION ITEM No. 5: Total Price to Furnish and Install the New 20" Water Main from the connection at the Kittery Water District Main to Gate #1 Metering Pit, across Bridge #1 to the Bldg. 163 Pump Station, Removal of the Existing 12" Main, and any associated work with regards to intersecting Sanitary Sewer, the Storm Drainage and Rail Impacts shown in Work Areas R, S, and T. Pricing to include excavation, shoring, Bridge 1 Pipe Structural Framing and Supports, New pipe main installation, Testing, Insulation and Jacketing above ground, Backfill, Temporary Paving, Traffic Control, Bridge and Surface Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological Monitoring, Third Party Commissioning, Site Improvements, Site Restoration, etc., and General Conditions as required per plans and specifications to complete this Option Item. See Drawings G-015 thru G-023 for Work Area Designations.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0007

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0008

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0009

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 8: Total Price for the entire work to furnish and install WORK AREA K:

BUILDING 243 (SUBSTATION 4). Included in this Subtotal is renovation of the existing Building 243 (Substation 4), and new 15kV Gear, and SCADA system.

OPTION ITEM No. 8: Total Price for the entire work to furnish and install WORK AREA K:

BUILDING 243 (SUBSTATION 4). Included in this Subtotal is renovation of the existing Building 243 (Substation 4), and new 15kV Gear, and SCADA system.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0010

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0011

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0012

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 11A: Total Price for Contractor Personal Owned Vehicle Off Installation Parking as required per plans and specifications to complete this Option Item.

Included in this bid option, the Contractor to provide off installation parking and transport for all P1080 Prime and Subcontractor Personal Owned Vehicles (POV). Parking shall be at an offsite parking facility and transport their employees as required to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure either privately owned or coordinated with the Seacoast area commuting options as required per plans and specifications to complete this Option Item.

OPTION ITEM No. 11A: Total Price for Contractor Personal Owned Vehicle Off Installation Parking as required per plans and specifications to complete this Option Item.

Included in this bid option, the Contractor to provide off installation parking and transport for all P1080 Prime and Subcontractor Personal Owned Vehicles (POV). Parking shall be at an offsite parking facility and transport their employees as required to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure either privately owned or coordinated with the Seacoast area commuting options as required per plans and specifications to complete this Option Item.

Option Line Item 0013

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 11B: Total PNSY Employee Parking of Personal Owned Vehicle (POV) at Off Installation Parking Location required per plans and specifications to complete this Option Item. Included in this bid option, Contractor to provide a minimum of 100 parking spots at one or multiple designated parking locations within approximately 1.5 Miles or less of one or both access points to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure that has continuous public walkway paths between PNSY and established parking lot or parking structure.

OPTION ITEM No. 11B: Total for PNSY Employee Parking of Personal Owned Vehicle (POV) at Off Installation Parking Location required per plans and specifications to complete this Option Item. Included in this bid option, Contractor to provide a minimum of 100 parking spots at one or multiple designated parking locations within approximately 1.5 Miles or less of one or both access points to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure that has continuous public walkway paths between PNSY and established parking lot or parking structure.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Option Line Item 0014

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0015

INFORMATION FROM TO CHANGED BY

Pricing Arrangement Fixed Price with Economic Price Adjustment - Actual Costs Firm Fixed Price

Option Line Item 0016

INFORMATION FROM TO CHANGED

BY

Description

OPTION ITEM No. 14: Total Price for the entire work to furnish and install FF&E for buildings B72 and B162 as required per plans and specifications to complete this Option Item.

OPTION ITEM No. 14: Total Price for the entire work to furnish and install FF&E for buildings B72, and B162 as required per plans and specifications to complete this Option Item.

Pricing Arrangement

Fixed Price with Economic Price Adjustment - Actual Costs

Firm Fixed Price

Section 00 21 00 - Instructions

Miscellaneous text in this section has been modified to:

INSTRUCTIONS TO OFFERORS:

TABLE OF CONTENTS

1. GENERAL

1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS

1.2 GENERAL OVERVIEW OF CONTRACT

2. BASIS FOR AWARD

3. EVALUATION FACTORS FOR AWARD

4. PROPOSAL REQUIREMENTS

4.1 PROPOSAL SUBMISSION INSTRUCTIONS

4.2 PRE-PROPOSAL INQUIRIES (PPIs)

4.3 CONTRACT OPPORTUNITIES (SAM.GOV)

5. INCORPORATION OF TECHNICAL PROPOSAL

6. ATTACHMENTS

1. GENERAL

1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS

This acquisition is being solicited on an unrestricted basis, with Full and Open Competition.

The NAICS code for this procurement is 237130 - Power and Communication Line and Related Structures Construction and the size standard is $45,000,000.

In accordance with DFARS 236.204(v), the magnitude of construction for this project is over $500,000,000.

This solicitation is formatted as a Request for Proposal according to FAR Part 15. This method permits evaluation of proposals based on price competition, technical merit and other factors; permits impartial and comprehensive evaluation of offerors' proposals; permits discussions if necessary; and ensures selection of the source whose performance provides the best value to the Government.

1.2 GENERAL OVERVIEW OF CONTRACT

Description of Work: The purpose of the P1080 Power Reliability and Water Resiliency Upgrades project is to provide increased reliability, resiliency and capacity to the existing electric and water utility systems primarily responsible for the protection of nuclear-powered submarines and nuclear support facilities at Portsmouth Naval Shipyard (PNSY). It also provides improvements at the water treatment plant and water lines within the Town of Kittery in partnership with the Kittery Water District (KWD), transmission lines and new transformer in partnership with Central Maine Power (CMP), and water and power improvements within the facility boundary. The P1080 project includes the following major components:

The Power reliability and water resiliency project provides increased reliability, resiliency, and capacity to the existing electric and water utility systems primarily responsible for the protection of nuclear-powered submarines and nuclear support facilities at PNSY. In order to support this on-base effort, there are two off-base private utility projects which are currently in design phase and will be needed to ultimately connect with the on-base work.

Off-Base Electrical: Provides modifications to the commercial power supply provided by Central Maine Power (CMP) to PNSY.

Off-Base Water: Provides modifications to the commercial water utility supply provided Kittery Water District (KWD) to PNSY

THIS PROJECT is for the On-Base work. The On-Base project on PNSY provides upgrades and modifications to shipyard power distribution, energy storage, and onsite generation to increase capacity, capability, and resiliency of the microgrid. The scope of this project includes:

Provides increased reliability, resiliency, and capacity to the existing electric and water utility systems primarily responsible for the protection of nuclear-powered submarines and nuclear support facilities at Portsmouth Naval Shipyard (PNSY). This project will include the following major components:

Constructs a new elevated water tower to provide water storage. Provides new footprint to replace Building 362 and expand Building 72 in order to accommodate new electrical equipment to meet code requirements. Adds new footprint to the Building 163 to accommodate new equipment to support and distribute new water flows and storage.

Provides new switchgear for the new transmission line from Bolt Hill Substation as part of Electrical Distribution Building. Upgrades the Franklin Substation Yard and Annex to include replacement of 15KV switchgear and feed to accommodate the proposed available short-circuit current and corresponding improvements to support the new redundant line.

Replaces the 15KV switchgear at Building 72 / Powerplant with equipment rated for the new power requirements.

Upgrades/renovates Substations 3 and 4 to include replacing existing switchgear and providing ancillary support equipment.

Provides an upgraded microgrid control system to manage electrical system throughout PNS.

The project will connect to the privatized electrical utility system owned by CMP (SO).

Provides for new pumps, controls, station piping, distribution piping, back-up power generation, to include electrical, structural, and mechanical improvements to accommodate the required improvements for Dry Dock 2 - Sea Water Cooling.

Installs water mains to cross the river at Bridges 1 and 2, installs/replaces water mains on-yard to provide connection from KWD connection to the bridges, from the bridges to Building 163, from Building 163 to the new water storage tank, as well as metering pits and required valving.

Upgrades the existing Building 163 pump station to include replacement of pumps with larger pumps, new piping and larger piping connections to accommodate new lines from the bridges, improvements to electrical, and mechanical systems.

Upgrades and provides new SCADA system to support the new water tower and existing water infrastructure.

The project will connect to the privatized water system owned by KWD (SO).

Facility-related control systems include cybersecurity features in accordance with current DoD criteria.

This project will provide Antiterrorism (AT) features and comply with applicable service and Geographic Combatant Commander policies and directive per Unified Facilities Criteria (UFC) and DoD Minimum Antiterrorism Standards for Buildings.

Provides costs for contractor leased space off-yard for laydown and storage and for parking for shipyard personnel.

Provides installation support for services required during construction.

Includes Operations and Maintenance Support Information

(OMSI).

DoD and DON principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders.

Low Impact Development will be included in the design and construction of this project as appropriate.

Includes clearing, excavation, hazardous materials abatement, and contaminated soil disposal required for site preparation to support construction.

Includes utility trench paving, sidewalk repairs, new concrete pads for electrical equipment, and site restoration required for project construction under paving and site improvements.

Provides electrical utilities including ancillary improvements required for primary project objectives including installation of new alternating current (AC) and direct current (DC) ductbanks to create a micro-grid and provides new electrical equipment, additional power generation, and distribution to support future shipyard loads.

Provides mechanical utilities including cleaning and lining of some existing water lines and new water lines on-yard to support new water flow requirements.

Environmental mitigation includes potential signage and improvements needed to mitigate impacts on archaeological and historical resources, as well as archaeological monitoring that will be required during invasive construction activities.

Provides for the demolition of Building 362.

2. BASIS FOR AWARD

2.1 The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to the contract; to negotiate with Offerors in the competitive range; and to award the contract to the Offeror submitting the proposal determined to represent the best value--the proposal most advantageous to the Government, price, non-price and other factors considered.

As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with 2.2

Offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to 2.3 allow consideration of award to other than the lowest priced Offeror or other than the highest technically rated Offeror.

The relative order of importance of the non-price evaluation factors is the technical factors (Factors 1, 2, 3, and 4) are of 2.4 equal importance to each other and, when combined, are equal in importance to the past performance evaluation/performance confidence assessment factor (Factor 5). When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-price evaluation factors) are significantly more important than price.

The importance of price will increase if the Offerors' non-price proposals are considered essentially equal in terms of 2.5 overall quality, or if price is so high as to significantly diminish the value of a non-price proposal's superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.

Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be 2.6 considered ineligible for award, unless the deficiency is corrected through discussions. An Unacceptable rating in any of the non-price/price factors will result in an overall rating of "Unacceptable" for the non-price/price factors, unless corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal.

3. EVALUATION FACTORS FOR AWARD

FAR Part 9.6 defines Contractor team arrangements. Contractor team arrangement, as used in this subpart, means an 3.1 arrangement in which -- (1) Two or more companies form a partnership or joint venture to act as a potential prime Contractor; or (2) A potential prime Contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent /LLC/LTD member companies (name is 3.2 not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent/LLC/LTD member companies will have involvement in the performance of the contract in order for the experience information of the affiliate/subsidiary/parent/LLC/LTD member companies to be considered. The proposal shall state specific commitments of technical resources (e.g., personnel, management, equipment that the affiliate/subsidiary/parent/LLC/LTD member companies shall commit to the performance of this contract). In particular, the proposal shall clearly state the specific commitments of resources of the affiliate/subsidiary/parent/LLC/LTD member companies in terms of the work it will either self-perform or manage on behalf of the Offeror in the performance of the contract.

Vague commitments to support are insufficient; rather, they must demonstrate intent/manner of actual performance on the 3.3 contract action being solicited.

The Offeror shall submit a signed copy of partnership agreement, teaming agreement, or letter of commitment for each 3.4 member of the Offeror's team (e.g., partner, team member, subcontractor, parent company, subsidiary, or other affiliated company, etc.) whose projects are submitted to demonstrate Construction or Design Experience. The Government will not consider any project submitted for Factor 1 if it was performed by a firm other than the Offeror and there is no supporting partnership agreement, teaming agreement, or letter of commitment.

3.5 The solicitation requires the evaluation of price and the following non-cost/price factors:

Factor 1 - Corporate Experience Factor 2 - Scheduling Factor 3 - Small Business Utilization Factor 4 - Safety Factor 5 - Past Performance

The distinction between corporate experience and past performance is that corporate experience pertains to the types of 3.6 work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

3.7 PRICE FACTOR

(a) Solicitation Submittal Requirements

All submissions shall include the following:

Executed SF1442 - Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide a cover page with solicitation number, solicitation title, Offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, and Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address, with its proposal.

- Completed Price Proposal Form Price shall be submitted on the Price Proposal Form included in the solicitation (Attachment G). The offeror shall submit one (1) electronic copy via PIEE, of the solicitation submittal requirements identified below. Also, price information included in the non-price/technical proposal will not be considered. Likewise, non-price/technical information included in the price proposal will not be considered. The Offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00 10 00 - Solicitation Contract Form in SF 1442. All required proposal documents shall be submitted in accordance with FAR 15.208.

The offeror shall submit with its proposal the Unit Price Form (Attachment Economic Price Adjustments:

L). Attachment L lists the materials/commodities subject to FAR 52.216-4, Economic Price Adjustment-Labor and Material. Offerors shall include a unit cost (excluding indirect costs and profit) for any commodity in the schedule. Note: Offeror does not have to propose on any or all materials/commodities. Only those materials /commodities that the Offeror proposed a unit cost will be subject to adjustments in accordance with FAR 52.216-

4. If a unit cost is not proposed, adjustments will not be allowed. FAR 52.211-18 Variation in Estimated Quantity does not apply to Attachment L. The estimated quantities are strictly for the purpose of administering the clause. Price adjustments subject to FAR 52.216-4 are limited to, at a maximum, the quantities listed in Attachment L.

Bid Bond (SF-24) - Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.

SAM registration - Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00 45 00 of the RFP is not provided in SAM, include the representation or certification in your price proposal.

SAM Contractor Responsibility - The Offeror shall ensure their System for Award Management (SAM) Contractor's responsibility Certification is up to date as required by FAR 52.209-7, Information Regarding Responsibility Matters.

VETS-4212 registration - Confirmation of filing of Veterans' Employment and Training (VETS-4212) for the 2024 /2025 filing cycle. Offeror shall ensure a current VETS- 4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal.

If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.

Small Business Subcontracting Plan - See details below in "Additional Information to be submitted with price proposal package"

NOTE: A small business joint venture Offeror must submit, with its offer, the representation required in paragraph (c) of FAR solicitation provision 52.212-3, Offeror Representations and Certifications-Commercial Products and Commercial Services, and paragraph (c) of FAR solicitation provision 52.219-1, Small

Business Program Representations, in accordance with FAR 52.204-8(d) and FAR 52.212-3(b) for the following categories:

Small business (SB);

Service-disabled veteran-owned small business (SDVOSB);

Women-owned small business (WOSB) under the WOSB Program;

Economically disadvantaged women-owned small business under the WOSB Program (SDB); or Historically underutilized business zone small business (HUBZone)

Additional Information to be submitted with price proposal package:

Responsibility Determination Information - In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards. In a separate Tab, the offeror shall provide the following information in the price proposal package:

One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror's firm has a line of credit -provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures - exact line of credit is not required).

The latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror. Offerors are not required to submit financial information as detailed in the price submission instructions via PIEE. However, if this is the case, the submitted copies in the hard copy proposal must be received no later than the established due date and time.

Description of offeror's facilities and equipment.

Other offeror's work presently under contract. Although required to be submitted with offeror's price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm's responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.

Small Business Subcontracting Plan (April 2020) (REFERENCE FAR 52.219-9 ALT II AND DFARS 252.219-7003) Information. In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the template provided as Attachment F. Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the Offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.

NAVFAC's command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars. These goals will be incorporated into the solicitation.

Small Business (SB) 40% HUBZone SB 3% Service-Disabled Veteran-Owned Small Business (SDVOSB) 5% Small Disadvantaged Business 5% Woman-Owned Small Business (WOSB) 9%

The SBSP shall be consistent with the commitments offered in the Small Business Participation and Commitment Strategy (Attachment E). In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.

Please note that SBSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products /services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD. Although required to be submitted with offeror's price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm's responsibility determination should your firm be considered for award.

Proposal packages from unsuccessful offerors will not be returned to the offeror but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.

(b) Basis of Evaluation:

The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items. The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in the solicitation. In accordance with FAR 52.217-5, the evaluation of options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price.

Comparison of proposed prices received in response to the RFP.

Comparison of proposed prices with the IGCE.

Comparison of proposed prices with available historical information.

Comparison of market survey results.

3.8 NON-PRICE FACTORS

Factor 1 - Corporate Experience

(a) Solicitation Submittal Requirements:

The Offeror shall submit the following information regarding Construction Experience:

Submit a maximum of five (5) relevant construction projects that best demonstrate your experience on relevant projects that are similar in size, scope, and complexity to aspects of the utility distribution work anticipated under this contract. For the purposes of this evaluation, relevance is further defined as a project including ALL of the following:

Construction of distribution systems for power, water, steam, or gas.

A construction value equal to or exceeding $50,000,000, however, offerors shall provide the value as of the day of project award.

Completed or substantially completed (80% completed) within ten years of the date of issuance of this solicitation.

Further, the Offeror's collective set of submitted projects shall also aggregately demonstrate experience performing construction services satisfying EACH of the following:

One project with a construction value equal to or exceeding $100,000,000.

One project constructing a distribution system for power. For example, these types of projects would include equipment such as transformers, substations, and switchgears.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.

The attached Construction Experience Project Data Sheet (Attachment B) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) double-sided pages (or four (4) single-sided pages) 8.5" x 11", 1" margin left/right/top/bottom, and 10-point font or larger. Attachment B submittals that do not comply with these requirements will not be evaluated.

For all submitted projects, the description of the project shall clearly describe the relevancy to the project requirements of this RFP.

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features.

Provide applicable documentation on projects that were validated and/or certified through a Sustainable Third-Party Certification program.

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. If a project was performed by a JV, and not all partners from that JV are on the JV proposed for this contract, the offeror shall clearly demonstrate what portion of the work was performed by the JV member, including the overall percentage, offering on this contract and shall not include work performed by the JV as a whole. The Offeror shall also submit a SIGNED copy of the Joint Venture agreement indicating the proposed participation of each Joint Venture member. Offerors are still limited to a total of five (5) projects combined.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract. The proposal shall state specific commitments of technical resources (e.g. personnel, equipment) that the affiliate/subsidiary/parent/LLC/LTD member companies commit to the performance of this contract. In particular, the proposal will clearly state the specific commitments of resources of the affiliate/subsidiary/parent/LLC/LTD member that will be located at the worksites and company offices in the city /area of the project. The proposal shall also describe specific roles of the affiliate/subsidiary/ parent/LLC/LTD member companies in terms of the work it will either self-perform or manage on behalf of the Offeror in performance of the contract. Failure to submit this information may result in a lower rating.

(b) Basis of Evaluation:

The basis of evaluation will include the Offeror's demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror's relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects for construction and projects will be evaluated in the order they are listed. Any projects submitted in excess of the five (5) for Construction Experience will not be considered.

Proposals demonstrating experience self-performing relevant features of work may be considered more favorably than those that do not demonstrate self-performance.

Factor 2 - Scheduling

(a) Solicitation Submittal Requirements:

Project Schedule Narrative:

The Offeror shall provide a narrative limited to ten (10) single-sided pages or, five (5) double sided pages, 8.5" x 11", 1" margin left/right/top/bottom, and 10-point font or larger.

The narrative shall be based upon a total contract duration of 1930 days, an assumed award date of 12 August 2026 and Notice to Proceed for Full site access no later than 29 September 2026.

The offeror at a minimum, shall clearly identify the proposed dates for the following: Ordering and delivery of long lead materials impacting the critical path and meeting all defined milestones of the Division I specification.

Provide a project schedule using P6 software. Submit with the proposal, the PDF of the full schedule output via PIEE and the native (.xer) file via email to Stephanie Wray at Stephanie.L.Wray2.civ@us.navy.mil. The proposed project schedule need not be cost-loaded; however, it shall serve as the basis for the Offeror's price proposal. The above completion dates in item shall be reflected in this schedule along with major construction activities, milestones, and critical path items. The schedule shall be on 11"x17" pages, single-sided, and there is no page limit.

NOTE:

Narrative and schedule are not allowed to propose variances from Contract requirements. For example, Offerors are not allowed to propose contractual conditions that shift schedule risk to the Government or propose limitations on the ability of the Government to properly administer the contract.

Failure to address any of the submission requirements will result in a deficiency.

The assumed award date is stated for proposal evaluation purposes only and does not infer or guarantee that an award will be made by that date.

(b) Basis of Evaluation:

The Offeror's proposed construction completion dates, project schedule, and narratives will be evaluated to ensure timely completion of the project within the dates and milestones specified.

The evaluation will consider how well the Offeror understands the major construction activities, task predecessors, and critical path items to execute the project.

Proposals that identify innovative approaches and lessons learned from previous completed projects that will be applied to this project to mitigate schedule risk and recover schedule time in the event of project delays may be rated more favorably.

Factor 3 - Small Business Utilization and Participation

It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Small Disadvantaged Business (SDB), Woman-Owned Small Business (WOSB), Historically Underutilized Business Zone Small Business (HUBZone SB), Veteran-Owned Small Business (VOSB), Service- Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance. This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation commitment for this requirement. The offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and the level of commitment to small business if awarded a contract under this solicitation.

(a) Solicitation Submittal Requirements:

All Offerors (large, non-profits, AND small businesses) shall use Attachment D (Historical Small Business Utilization) to demonstrate their historical utilization of SBs. Each project submitted under Factor 1, Corporate Experience, shall be included on Attachment D. Failure to include each project submitted under Factor 1, Corporate Experience, on Attachment D, or the failure to fully complete Attachment A for each project may result in a deficiency. Only complete Attachment D. Information provided in a different format and/or on a form created by the offeror will not be evaluated.

Attachments or addendums to Attachment D will not be evaluated. Offerors are permitted to expand portions of the form, as needed, to provide sufficient response. Instructions regarding how to complete Attachment D are included at the beginning of the attachment.

All Offerors (large, non-profits, AND small businesses) shall use Attachment E (Small Business Participation Commitment Document (SBPCD)) to submit the following required information for evaluation of this factor:

To demonstrate commitment to use small business concerns in the performance of this contract, identify by name the subcontractors that will be used to support each small business category, including SDB, WOSB, HUBZone SB, VOSB, and SDVOSBs. Identify the type and complexity of product/service to be subcontracted, and the type of commitment (i.e., teaming agreement, joint venture agreement, mentor protege agreement, letter of commitment, etc.) with each subcontractor.

If subcontractors are not identified by name, offerors shall provide a detailed explanation why subcontractors are not identified. If firm written commitments with SBs are not in place, offerors shall provide an explanation and rationale on the ability to achieve the proposed participation. (See Attachment E, paragraph 5)

If an LB offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance. SBs intending to 100% self-perform are not required to provide an explanation. (See Attachment E, paragraph 6).

To demonstrate maximum practicable participation of small businesses, identify (in terms of dollar value and percentage of the total contract value) the offeror's proposed small business participation. The minimum required small business participation (i.e.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .