This document is a comprehensive Price Schedule for Project P1080, dated 30 DEC 2025, detailing a complex electrical infrastructure improvement project at a naval shipyard. The base scope (CLIN 0001) and 14 optional line items cover extensive work including power distribution upgrades, water main installations, hazardous material abatement, utility infrastructure improvements, building renovations, and associated site work. Key work areas include electrical systems, water storage, water mains, pump stations, sea water systems, roadway improvements, and multiple building modifications at Portsmouth Naval Shipyard (PNSY).
The price schedule provides unit pricing for numerous specific tasks, with particular emphasis on hazardous material handling, excavation, pipe installations, and infrastructure upgrades. The government reserves the right to award optional line items (CLINs 0002-0016) within 180 calendar days after contract award, with a total contract completion timeline of 1930 calendar days. Pricing is firm fixed, and actual quantities may vary. Notable requirements include off-site parking for contractor personnel, natural gas generator installations, and comprehensive environmental and site restoration components. All hazardous materials must be delivered to the PNSY Hazardous Waste Facility in Building 357 for proper disposal.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P1080 PRICE SCHEDULE
30 DEC 2025
Provide line item prices, where indicated by blank underlines, for the following items:
Line
Item
Description Quantit y
Unit Unit Price Sub-Total Total Price
0001. BASE PRICE: Total CLIN 0001 Price for
Project P-1080 On-Base Power Electrical
Improvements CLINs 0001.A thru
0001.AC for Drawing Work Areas A, B, C, D, E, F, G, H, J, L, M, N, O, and Other
Costs as noted below. The project objectives are to provide upgrades and modifications to shipyard power distribution, energy storage, and onsite generation to increase capacity, capability, and resiliency of the power system in accordance with the drawings and specifications complete, but excluding work provided in another Priced line Item. See Drawings G-015 thru G-023 for Work Area Designations.
1 LS $_____________ $_____________
0001.A Subtotal Price for the CLIN 0001 Base
Price Scope that is NOT PRICED in
SubCLINs Line Items 0001.B thru
0001.AC. Note that the Option pricing identified in CLINs 0002 thru 00016 are specific to those work scopes and are not to be included in CLIN0001.
1 LS $_____________ $_____________
0001.B Subtotal of Base Price to Furnish and
Install the AC Ductbanks as shown on the drawings complete in accordance with the details on drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.C Subtotal of Base Price to Furnish and
Install DC Ductbank as shown on the
Drawings complete in accordance with the details on the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.D Subtotal of Base Price for Building 72
Demolition, Renovations and New
Construction as shown on the Drawings complete (incl. switchgear, & electrical equipment) in accordance with the details on the drawings and specifications but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.E Subtotal of Base Price for Hazardous
Materials within buildings and structures including but not limited to asbestos, low-level radiological contaminants, lead based or other hazardous paint, PCBs, and heavy metals that the contractor may encounter in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.F Subtotal of Base Price to Furnish and
Install Wearing Course Pavement complete in accordance with the details on the drawings
1 LS $_____________ $_____________
and specifications, but excluding work provided in another line item.
0001.G Subtotal of Base Price to Furnish and
Install 8 inch Water Main complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.H Subtotal of Base Price to Furnish and
Install 12 inch Water Main complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.I Subtotal of Base Price to Furnish and
Install Water Service Connections complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.J Subtotal of Base Price to Furnish and
Install 15-inch Storm Drain complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.K Subtotal of Base Price to Furnish and
Install 18-inch Storm Drain complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.L Subtotal of Base Price for Excavation and
Removal of Hazardous Soils during Base
Bid Work including, but not limited to sampling, excavation, stockpiling, and testing compete in accordance with the drawings and or specifications, excluding Disposal and or work provided in another line item.
1 LS $_____________ $_____________
0001.M Subtotal of Base Price to Furnish and
Install Gas Main complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.N Subtotal of Base Price to Furnish, Install
B162 and B72 Gas Regulating Stations complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.O Subtotal of Base Price for Excavation of
Non-Hazardous Soils (common earth) complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.P Subtotal of Base Price for providing
Structural Fill complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.Q Subtotal of Base Price for providing
Ordinary Fill complete in accordance with the drawings and specifications, but excluding work provided in another line item.
0001.R Subtotal of Base Price for providing ¾”
Crushed Stone Materials complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.S Subtotal of Base Price for providing 1-1/2”
Crushed Stone Materials complete in accordance with the drawings and specifications, but excluding work provided in another line item.
1 LS $_____________ $_____________
0001.T Base Scope Unit Price for Ledge Removal and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with Notes Item “i” below.
24,750 CY $_____________ $_____________
0001.U Base Scope Unit Price for providing
Excavation and Removal of Hazardous
Soils for areas not characterized in the contract documents as having Hazardous
Soils including not limited to sampling, temporarily stockpiling to accommodate the
Government's scheduling of trucks for disposal, and testing (expedited), complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below.
5,100 CY $_____________ $_____________
0001.V Base Scope Unit Price to provide
Hazardous Underground Pipe and/or
Hazardous Pipe/Insulation Removal per location (up to 10 feet in Length). Pricing to include all testing (expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below.
100 EA $_____________ $_____________
0001.W Base Scope Unit Price to provide
Hazardous Material Abatement for Paint
Containing Lead, Cadmium, or Chromium
Removal within Buildings). Pricing to include all testing (expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
1,200 SF $_____________ $_____________
0001.X Base Scope Unit Price to provide
Hazardous Material Abatement for Lead
Dust within Buildings). Pricing to include all testing (expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
1,000 SF $_____________ $_____________
0001.Y Base Scope Unit Price to provide
Hazardous Uranium Tiles Removal within
Buildings to Government Provided
Dumpsters. Pricing to include all testing
(expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
400 SF $_____________ $_____________
0001.Z Base Scope Unit Price to Furnish and
Install Hazardous Pipe Insulation Glove
Bag Removal (6”-12” Dia. Pipe). Pricing to testing (expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
250 LF $_____________ $_____________
0001.AA Base Scope Unit Price to provide
Hazardous Pipe Insulation Glove Bag
Removal (3/4”- 4” Dia. Pipe). Pricing to include all testing (expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
250 LF $_____________ $_____________
0001.AB Base Scope Unit Price to provide
Hazardous Joint Compound Abatement within Buildings to Government Provided
Dumpsters. Pricing to include all testing
(expedited), hazardous plan development, required controls and implementation, performance of the work, hygienist, 400 SF $_____________ $_____________ monitoring, replacement with select material and appropriate disposal, complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
0001.AC Base Scope Unit Price to provide
Temporary Response to unplanned shipyard rail movements and rapidly restore rail. Pricing to include minor
Backfill, Ballast, Crushed Stone, Wood Ties, 100lb Two Rail installation for 60 LF of
Roadway (120 lf of rail), certification complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “h” below
60 LF $_____________ $_____________
0002. OPTION ITEM No. 1: Total CLIN 0002
Price to Furnish and Install the New 16”
Water Main from the connection at the
Kittery Water District Main to Gate #2
Metering Pit, across Bridge #2, Wyman
Ave to the Bldg. 163 Pump Station, and any associated work with regards to intersecting Sanitary Sewer, the Storm
Drainage and any Rail Impacts as shown in
Work Areas R, S F, and T. Pricing to include excavation, shoring, Bridge 2 Pipe
Structural Framing and Supports, New pipe main installation, Testing, Insulation and
Jacketing above ground, Backfill, Temporary
Paving, Traffic Control, Bridge and Surface
Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological
Monitoring, Site Improvements, Site
Restoration, etc., and General Conditions as required per plans and specifications to complete this Option Item. See Drawings G-
015 thru G-023 for Work Area Designations.
1 LS $_____________ $_____________
0002.A Subtotal Price Option No. 1 CLIN 0002 for
Scope in this Work Area that is NOT
PRICED in the following SubCLINs Line
Items 0002.B and 0002.C.
1 LS $_____________ $_____________
0002.B Option Item No. 1 Unit Price for Ledge
Removal and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “i” below.
2,000 CY $_____________ $_____________
0002.C Option Item No. 1 Unit Price for providing
Excavation and Removal of Hazardous
Soils for areas not characterized in the contract documents as having Hazardous
Soils including not limited to sampling, temporarily stockpiling to accommodate the
550 CY $_____________ $_____________
Government's scheduling of trucks for disposal (if applicable), and testing
(expedited), complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with Notes Item “h” below.
0003. OPTION ITEM No. 2: Total CLIN 0003
Price to furnish and install the work shown in WORK AREA U: WATER STORAGE
TANK. Included is the Site Work, and the
Tank Structure, tie-in to the Meade Ave
Water Main and SCADA to create a fully functioning and integrated water storage tank.
1 LS $_____________ $_____________
0003.A Subtotal Price Option No. 2 CLIN 0003 for
Scope in this Work Area that is NOT
PRICED in the following SubCLINs Line
Items 0003.B and 0003.C.
1 LS $_____________ $_____________
0003.B Option Item No. 2 Unit Price for Ledge
Removal and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “i” below.
550 CY $_____________ $_____________
0003.C Option Item No. 2 Unit Price for providing
Excavation and Removal of Hazardous
Soils for areas not characterized in the contract documents as having Hazardous
Soils including not limited to sampling, temporarily stockpiling to accommodate the
Government's scheduling of trucks for disposal (if applicable), and testing
(expedited), complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with Notes Item “h” below.
150 CY $_____________ $_____________
0004. OPTION ITEM No. 3: Total CLIN 0004
Price to Remove the Existing 8” Water
Main. Furnish and Installation of the 12”
Water Main along Meade Ave to the connection @ Building 403, the abandonment and fill of the existing 8”, and any associated work with regards to intersecting Sanitary Sewer, the Storm
Drainage shown in Work Area R. Pricing to include excavation, shoring, pipe bedding, pipe main installation, testing, backfill, temporary paving, traffic control, and surface restoration as required per plans and specifications
1 LS $_____________ $_____________
0004.A Subtotal Price Option No. 3 CLIN 0004 for
Scope in this Work Area that is NOT
PRICED in the following SubCLINs Line
Items 0004.B and 0004.C.
0004.B Option Item No. 3 Unit Price for Ledge
Removal and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “i” below.
600 CY $_____________ $_____________
0004.C Option Item No. 3 Unit Price for providing
Excavation and Removal of Hazardous
Soils for areas not characterized in the contract documents as having Hazardous
Soils including not limited to sampling, temporarily stockpiling to accommodate the
Government's scheduling of trucks for disposal (if applicable), and testing
(expedited), complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with Notes Item “h” below.
200 CY $_____________ $_____________
0005. OPTION ITEM No. 4: Total CLIN 0005
Price to Clean & Line the Existing 16”
Water Main along Sicard Street and the
Existing 16” Water Main along John Paul
Jones Street shown in Work Area R.
Pricing includes excavation, shoring, cleaning, lining installation, testing, backfill, temporary paving, traffic control, and surface restoration as required per plans and specifications
1 LS $_____________ $_____________
0006. OPTION ITEM No. 5: Total CLIN 0006
Price to Furnish and Install the New 20”
Water Main from the connection at the
Kittery Water District Main to Gate #1
Metering Pit, across Bridge #1 to the Bldg.
163 Pump Station, Removal of the Existing
12” Main, and any associated work with regards to intersecting Sanitary Sewer, the
Storm Drainage and Rail Impacts shown in
Work Areas R, S, and T. Pricing to include excavation, shoring, Bridge 1 Pipe Structural
Framing and Supports, New pipe main installation, Testing, Insulation and Jacketing above ground, Backfill, Temporary Paving, Traffic Control, Bridge and Surface
Restoration, Environmental Mitigation, Dewatering, Shoring, HAZMAT, SCADA, Vibration Monitoring, Archaeological
Monitoring, Third Party Commissioning, Site
Improvements, Site Restoration, etc., and
General Conditions as required per plans and specifications to complete this Option Item.
See Drawings G-015 thru G-023 for Work
Area Designations.
1 LS $_____________ $_____________
0007 OPTION ITEM No. 6: Total CLIN 0007
Price to furnish, install and modify the work shown in Work Area T: WATER
PUMP STATION (B163). Included in this
CLIN are the Exterior and Interior
Improvements, as well as SCADA system improvements to result in a fully integrated system per plans and specifications to complete this Option Item.
0008 OPTION ITEM No. 7: Total CLIN 0008
Price for the entire work to furnish and install the work in Work Area V:
AUXILIARY SEA WATER SYSTEM
(ASW) as required per plans and specifications to complete this Option Item.
1 LS $_____________ $_____________
0008.A Subtotal Price Option No. 7 CLIN 0008 for
Scope in this Work Area that is NOT
PRICED in the following SubCLINs Line
Items 0008.B and 0008.C.
1 LS $_____________ $_____________
0008.B Option Item No. 7 Unit Price for Ledge
Removal and Disposal complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with
Notes Item “i” below.
375 CY $_____________ $_____________
0008.C Excavation and Removal of Hazardous
Soils for areas not characterized in the contract documents as having Hazardous
Soils including not limited to sampling, temporarily stockpiling to accommodate the
Government's scheduling of trucks for disposal (if applicable), and testing
(expedited), complete in accordance with the drawings and specifications, but excluding work provided in another line item, and in accordance with Notes Item “h” below.
100 CY $_____________ $_____________
0009. OPTION ITEM No. 8: Total CLIN 0009
Price for the entire work to furnish and install WORK AREA K: BUILDING 243
(SUBSTATION 4). Included in this Subtotal is renovation of the existing Building 243
(Substation 4), and new 15kV Gear, and
SCADA system.
1 LS $_____________ $_____________
0010. OPTION ITEM No. 9: Total CLIN 0010
Price for the entire work to furnish and install the Capacitor Banks as required per plans and specifications to complete this
Option Item.
1 LS $_____________ $_____________
0011. OPTION ITEM No. 10: Total CLIN 0011
Price for the entire work to furnish and install Complete Roadway Milling and
Pavement Overlay on roads impacted, including Striping, Markings, and Loop
Detectors as required per plans and specifications to complete this Option Item.
1 LS $_____________ $_____________
0012. OPTION ITEM No. 11A: Total CLIN 0012
Contractor Personal Owned Vehicle Off
Installation Parking as required per plans and specifications to complete this Option
TOTAL PRICE FOR CLINs 0001 - 0016 _
GENERAL BID NOTES
a. All work required in accordance with the drawings and specifications must be included in the Contractor’s proposed price.
Item. Included in this bid option, the
Contractor to provide off installation parking and transport for all P1080 Prime and
Subcontractor Personal Owned Vehicles
(POV). Parking shall be at an offsite parking facility and transport their employees as required to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure either privately owned or coordinated with the Seacoast area commuting options as required per plans and specifications to complete this Option Item.
0013. OPTION ITEM No. 11B: Total CLIN 0013
PNSY Employee Parking of Personal
Owned Vehicle (POV) at Off Installation
Parking Location required per plans and specifications to complete this Option Item.
Included in this bid option, Contractor to provide a minimum of 100 parking spots at one or multiple designated parking locations within approximately 1.5 Miles or less of one or both access points to PNSY. The contractor is required to utilize a pre-established parking lot or parking structure that has continuous public walkway paths between PNSY and established parking lot or parking structure.
1 LS $_____________ $_____________
0014. OPTION ITEM No. 12: Total CLIN 0014
Price for the entire work to furnish and install Two Additional Natural Gas
Generators in Work Area P as required per plans and specifications to complete this
Option Item.
1 LS $_____________ $_____________
0015. OPTION ITEM No. 13: Total CLIN 0015
Price for the entire work to furnish and install One Additional Natural Gas
Generator in Work Area P as required per plans and specifications to complete this
Option Item.
1 LS $_____________ $_____________
0016. OPTION ITEM No. 14: Total CLIN 0016
Price for the entire work to furnish and install FF&E for buildings B72, and B162 as required per plans and specifications to complete this Option Item.
Gov’t
Est’d
Price:
$14,104
HAR Percent
(NTE 5%)
3%
HAR Subtotal
$436
Total FF&E
Estimated Price
$14,540
b. Evaluation will be made on the total sum of Contract Line Item (CLIN) 0001, and the extended total under
Contract Line items 0002, through 0016. For CLINs 0001 through 0016, enter unit price and extended total in space provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provided a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price. Award is expected to be made on
CLIN 0001.
c. The Government reserves the unilateral right to award CLIN(s) 0002 through 0016 to the Contractor at the proposed price within 180 calendar days after the contract award. A firm fixed proposed price is required for all
CLINs. No provision is made for economic price adjustment. If Option(s) 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11A, 11B, 12, 13, and/or 14 are exercised, the contract completion date remains 1930 calendar days after award of the contract.
d. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the CLINS 0002 through 0016 (Options 1 through 14) to the total price for CLIN 0001. In accordance with
FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the
Option(s).
e. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
f. If any of the CLIN(s) 0002 through 0016 are exercised, additional bonding and consent of surety is required.
Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.
g. All hazardous material and contaminated soils shall be delivered to the PNSY Hazardous Waste Facility in
Building 357 for disposal in accordance with the project specifications.
h. The quantities shown for CLIN(s) 0001.U through 0001.AC, and Bid Option CLIN(s) 0002.C, 0003.C, 0004C, and 0008.C, are estimated quantities for the described work that are in addition to the scope of work indicated in the drawings and specifications and must be executed in accordance with the requirements of the contract documents.
These quantities are in addition to the base bid and bid option quantities, as determined by the bidder, that must be included in CLIN(s) 0001.A through 0001.S, and Bid Option CLIN(s) 0002.A, 0003.A, and 0004.A, and 0008.A to complete the full scope of work. The bidder is to utilize these quantities to establish unit prices and include this subtotal and quantity in the total bid price for the Base Scope and applicable Bid Options. The actual quantities may vary in location and/or amount. Contractor’s Quality Control Manager is to track actual quantities and locations, coordinated with and verified by the Contracting Officer’s Representative prior to execution of the work, for each line item as the work progresses and invoice for actual quantities when completed. Applicable locations for these unit price quantities will be any location within the entire project site such that any variation in location will not be cause for a contract modification or change in scope. Actual quantities greater than the estimated amount will be increased via a modification to the contract. Should any quantities not be utilized in performance of the associated scope, the resulting credits shall be available for Government recapture or repurpose.
i. The quantities shown for CLIN(s) 0001.T and Bid Option CLIN(s) 0002.B, 0003.B, 0004.B and 0008.B associated with ledge are estimated quantities that represent the full amount of ledge anticipated to require removal and disposal for the total contract. The bidder is not to include any other ledge removal and disposal scope or cost in other CLINs. The bidder is to utilize these quantities to establish unit prices and include this subtotal and quantity in the total bid price for the Base Scope and applicable Bid Options. The actual quantities may vary in location and/or amount. Contractor’s Quality Control Manager is to track actual quantities and locations, coordinated with and verified by the Contracting Officer’s Representative prior to execution of the work, for each line item as the work progresses and invoice for actual quantities when completed. Applicable locations for these unit price quantities will be any location within the entire project site such that any variation in location will not be cause for a contract modification or change in scope. Actual quantities greater than the estimated amount will be increased via a modification to the contract. Should any quantities not be utilized in performance of the associated scope, the resulting credits shall be available for Government recapture or repurpose.