This document provides an amendment to a solicitation for munitions response services at Vieques, Puerto Rico and other sites. The solicitation is being advertised as a 100% small business set-aside with a NAICS code of 562910 and small business size standard of 750 employees. The cost plus award fee, indefinite delivery/indefinite quantity contract has a maximum value of $95 million over one base year and four option years. Services include munitions response such as investigations, removals and remedial actions at former Navy sites in compliance with explosives safety and environmental regulations. Tasks involve work plans, sampling, safety plans, explosives submissions and determination requests, completion reports, monitoring, technology implementation and support to other contractors. The amendment answers questions on the solicitation, revises forms and instructions, and provides clarification on key personnel and past performance submittals.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
MUNITIONS RESPONSE ACTIONS AT VIEQUES, PUERTO RICO AND OTHER SITES IN NAVFAC'S AREA OF RESPONSIBILITY OR WORLDWIDE
PLEASE SEE SF-30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
R 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-May-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247020R2004
X 9B. DATED (SEE ITEM 11)
06-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-May-2021
CODE
COMNAVFACSYSCOM ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247020R2004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
The purpose of this amendment is to disseminate the below information.
1. Address questions received in response to the solicitation.
2. Section C – Revision to C3. See amendment details below.
3. Section J – The following list of attachments have been revised.
Attachment JL.11 – Factor 1 Corporate Experience Example Project Form for IDIQ (Amendment 0001)
Attachment JL.12 – Factor 1 Corporate Experience Example Project Form for a Standalone Contract or Task Order not on an IDIQ Contract provided as an Example Project (Amendment 0001)
4. Section L – Revision to L2. See amendment details below.
Questions and Answers:
1. Reference: RFP Page 125, Instruction to Offerors, L1 Instructions for submitting Questions Regarding this Solicitation, directs that questions must be received within 15 day in advance of the closing date.
Question: Will the government provide contractors with answers/responses to questions as soon as they are developed following initial receipt, and not wait until some point within the 15 day period prior to the solicitation closing date to answer all question in one mass response? Distributing answers to questions as soon as they are available will allow contractors to incorporate the responses more efficiently into proposals.
Response: The government intends to respond to questions as they are received.
2. Reference: RFP Page 129, (1) Factor 1, Corporate Experience, (i) Solicitation Submittal Requirements, states that standalone or task order projects must be completed or substantially completed within 3 years of the issuance date of this solicitation. IDIQ contracts must be awarded within 8 years of the issuance date of this solicitation and must have substantial munitions response field work performed within the last 3 years. However, the JL.11 and JL.12 forms reflect 2012 and November 2017 as the years/month for the period relating to IDIQ, task order, and work completion.
Question: Will the government re-issue amended forms that reflect the correct year/month that are associated with the period that is within 3 years of the issuance date of the solicitation?
Response: Yes, see amendment details below.
3. Reference: Section L, Factor 1, Corporate Experience aligns a 3-year time period for completed/ substantially completed standalone contracts or task orders projects, and for the level of munitions response field work completion under an IDIQ contract.
At the same time Factor (3) Safety requires that offerors submit detailed safety information for period covering the previous 5-years, while the majority of the Key Personnel reflected within Section C are required to have 5 years of experience in their roles in order to be considered qualified to perform on this contract. In addition, Section F states that the contract will cover an overall 5-year future period of performance.
Question: Given the predominance within the RFP for a 5-year period being used to represent an offeror’s capability and experience to perform on this contract, along with the contract being planned to cover a future duration of 5-years, will the government also align a period of 5-years from the issuance date of this solicitation for completed standalone contracts or task orders projects, and for the level of munitions response field work completion under an IDIQ contract?
Response: No, the solicitation remains unchanged.
4. Reference: Section L, Page 125, “Volume 1: Non-Cost (Technical and Past Performance) Proposal - Submit in 8- 1/2 x 11 format, font size 11-12.”
Question: Can charts, captions, and tables use font size 10?
Response: Yes, 10 point font size may be used for charts, captions, and tables.
5. Reference: RFP Section J, Form JL.11, Section II–Specific Project Information for Relevant Task Orders, Table 1
Question 1: Since project titles and overall munitions response services information can be long, could Table 1 form be changed to “landscape” format, 11 x 17 size and counted as one page?
Response: Table 1 of Attachment JL.11 may be changed to landscape format, column widths may be adjusted, and the table may be submitted in 8.5 x 11 or 11 x 17 format. If submitted in 11 x 17 format, table should be printed single sided and each 11 x 17 single sided page will be counted as one page.
Question 2: Would you allow a 9 point or 10 point font for Table 1 in form JL.11?
Response: Yes, 10 point font size may be used in form JL.11.
6. Reference: General Overall
Question: Can 10-point size be used to complete the contractual information for JL.11 and JL.12, but the narrative remains 11-point font?
Response: Yes, 10 point font size may be used in forms JL.11 and JL.12.
7. Reference: RFP page 130, (2) Factor 2, Management Approach; (i) Solicitation Submittal Requirements: “1) Provide a one-page organizational chart demonstrating the organizational structure of both corporate and field management personnel, and provide a related narrative.”
Question 1: May we use an 11 x 17 sheet to show our organizational structure, and may that count as one page?
Response: Yes, see revision to section L2.
Question 2: May we use either 9-point or 10-point font for the organizational chart?
Response: Font 10 point size may be used for the organizational chart.
8. Reference: Page 9, Section C, paragraph 3.3.2 Conditions for Substitutions, Deletions, or Additions; and pages 9 & 10, paragraphs C.3.5.1, Program Management Key Personnel and 3.5.2 Project Level Key Personnel reference “Key Personnel” resumes submitted in the technical proposals. Attachment JL.14 “Resume of Key Personnel” is included within the RFP.
However, in Sections L and M, under Factor 2, Management Approach, there are no references to include Key Personnel or which Key Personnel specified in Section C require resumes using Attachment JL.14.
Question: Are Key Personnel resumes required to be submitted with the technical proposal using Attachment JL.14 and if so, which Key Personnel resumes are required?
Response: No, resumes are not required for the technical proposal.
9. Reference: Pages 130 and 131, Section L requires within subsections (i), (1), and (2) that an offeror presents both DART and TCR rates for a 5 year period, along with an explanation for any negative trends/corrective actions and a detailed descriptions of any fatalities experienced within this 5-year timeframe. Within subsection (3), the Technical Approach Safety narrative is limited to two (2) single-sided pages or one (1) double-sided page.
Question: Please confirm that the stated page limitation only applies to the Technical Approach to Safety, and that there is no page limitation for offerors to present DART and TCR rates, along with explanations for negative trends, corrective actions, or fatalities within the 5-year timeframe.
Response: As stated in the solicitation, the Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page. DART and TCR rates will not count against the page limitation for the narrative.
10 Reference: Page 132, Factor 4 Past Performance, paragraph (i) Solicitation Submittal Requirements states “If a completed CPARS evaluation is available, it shall be submitted with the proposal for each of the projects listed under Factor 1, Corporate Experience. This includes all IDIQ contracts (meaning the entire IDIQ contract as a whole) submitted on Attachment JL.11; all task orders submitted in Table 2 of Section II of Attachment JL.12; and all standalone contracts submitted on Attachment JL.12.”
However, Attachment JL.12 does not include a Section II or a Table 2, while JL.11 does include a Section II and a Table 1 that pertains to task orders associated with the IDIQ contract. In addition, this Factor 4 text does not specifically indicate that a CPARS or PPQ is required for each of the task orders that offerors include in JL11, Table 1 for the IDIQ contract.
Question: Given that no table is contained within JL.12 and the lack of a requirement associated with CPARS for the task orders included in JL.11, Table 1, will the government amend Factor 4 to something similar to the following (suggested text edits are underlined):
“If a completed CPARS evaluation is available, it shall be submitted with the proposal for each of the projects listed under Factor 1, Corporate Experience. This includes all IDIQ contracts (meaning the entire IDIQ contract as a whole) submitted on Attachment JL.11 and for each task order included in JL.11, Table 1; all individual task orders submitted on Attachment JL.12; and all standalone contracts submitted on Attachment JL.12.”
Response: See revisions to section L2.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
SECTION C REVISIONS 0001
The following revisions have been made to Section C:
FROM:
3.3 Key Personnel Changes.
3.3.1 Substitution Limitations. The Contractor shall assign to this contract those key personnel whose resumes were submitted and approved by the Government. No substitutions shall be made except in accordance with this clause.
3.3.2 Conditions for Substitutions, Deletions, or Additions. The Contractor agrees that during the first 180 days of the contract performance period, no key personnel whose resumes were provided with the technical proposal shall be substituted or deleted unless such changes are necessitated by an individual’s sudden illness, death, or termination of employment. In any of these events, the Contractor shall promptly notify the Contracting Officer. In addition, substitutions of all key personnel and UXO personnel shall be approved in advance by the Contracting Officer. Proposed substitutions shall have qualifications that are equal to or higher than the qualifications of the person to be replaced. Proposed substitutions, deletions, or additions shall be submitted in writing to the Contracting Officer, at least 15 days in advance, (45 days if security clearance is to be obtained), with the following information:
(a) a detailed explanation of the circumstances necessitating proposed substitutions or additions,
(b) a complete resume for the proposed substitute or addition,
(c) for a substitution request, a qualification comparison matrix comparing the qualifications of the existing personnel with that of the one being proposed, and
(d) any other information requested by the Contracting Officer.
The Contracting Officer will evaluate such requests and notify the Contractor in writing of approval or disapproval.
3.3.3 Key Personnel List. The list of key personnel may be amended from time to time by contract modification to either add, delete, or substitute personnel in accordance with key personnel substitution requirements specified herein. The Contractor shall submit a list of key personnel with the technical proposal.
3.4 Personnel Training. The Contractor shall have personnel with the requisite skills to perform the requirements of this contract. Therefore, the Government will not allow, nor reimburse as direct costs, those costs associated with the training of Contractor personnel in any effort to initially attain requirements of this contract. If allowable under FAR Part 31, these costs may be included as indirect costs. Attendance at workshops or symposiums is considered training for purposes of this clause. The Contractor shall establish an explosive certification and documentation process for all Contractor and subcontractor personnel working within exclusion zones.
3.5 Key Personnel and Other Personnel.
3.5.1 Program Management Key Personnel. The Contractor shall provide Program Management Key Personnel to perform the duties of the following key positions. See Paragraph 3.6 for duties and minimum required qualifications.
The personnel performing the required duties shall meet the minimum qualifications for that key position.
• Program Manager (Resume) *
• Program Quality Control Manager (Resume)*
• Corporate Health and Safety Manager
• Program Geophysicist
*A resume for this labor category is required to be submitted with the contractor’s technical proposal in accordance with Section L of the solicitation.
TO:
3.3 Key Personnel Changes.
3.3.1 Substitution Limitations. The Contractor shall assign to this contract those key personnel whose resumes were submitted and approved by the Government. No substitutions shall be made except in accordance with this clause.
3.3.2 Conditions for Substitutions, Deletions, or Additions. The Contractor whose proposal is accepted shall, within ten (10) days after award furnish resumes for the key positions listed in paragraphs 3.5.1 and 3.5.2. The Contractor agrees that during the first 180 days following approval by the Contracting Officer of the contract performance period, no key personnel whose resumes were provided with the technical proposal shall be substituted or deleted unless such changes are necessitated by an individual’s sudden illness, death, or termination of employment. In any of these events, the Contractor shall promptly notify the Contracting Officer. In addition, substitutions of all key personnel and UXO personnel shall be approved in advance by the Contracting Officer.
Proposed substitutions shall have qualifications that are equal to or higher than the qualifications of the person to be replaced. Proposed substitutions, deletions, or additions shall be submitted in writing to the Contracting Officer, at least 15 days in advance, (45 days if security clearance is to be obtained), with the following information:
(a) a detailed explanation of the circumstances necessitating proposed substitutions or additions,
(b) a complete resume for the proposed substitute or addition,
(c) for a substitution request, a qualification comparison matrix comparing the qualifications of the existing personnel with that of the one being proposed, and
(d) any other information requested by the Contracting Officer.
The Contracting Officer will evaluate such requests and notify the Contractor in writing of approval or disapproval.
3.3.3 Key Personnel List. The list of key personnel may be amended from time to time by contract modification to either add, delete, or substitute personnel in accordance with key personnel substitution requirements specified herein. The Contractor shall submit a list of key personnel with the technical proposal.
3.4 Personnel Training. The Contractor shall have personnel with the requisite skills to perform the requirements of this contract. Therefore, the Government will not allow, nor reimburse as direct costs, those costs associated with the training of Contractor personnel in any effort to initially attain requirements of this contract. If allowable under FAR Part 31, these costs may be included as indirect costs. Attendance at workshops or symposiums is considered training for purposes of this clause. The Contractor shall establish an explosive certification and documentation process for all Contractor and subcontractor personnel working within exclusion zones.
3.5 Key Personnel and Other Personnel.
3.5.1 Program Management Key Personnel. The Contractor shall provide Program Management Key Personnel to perform the duties of the following key positions. See Paragraph 3.6 for duties and minimum required qualifications.
The personnel performing the required duties shall meet the minimum qualifications for that key position.
• Program Manager (Resume) *
• Program Quality Control Manager (Resume)*
• Corporate Health and Safety Manager
• Program Geophysicist
*A resume for this labor category is required to be submitted with the contractor’s technical proposal in accordance with Section L of the solicitation.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
LIST OF ATTACHMENTS
Attachment JL.1 – Directives, Regulations, and Definitions
Attachment JL.2 - Direct Labor Bid and Billing Rate Submission
Attachment JL.2A - Direct Labor Rate Escalation Submission
Attachment JL.3 - Identification of Uncompensated Overtime Ratios
Attachment JL.4 - Indirect Ceiling Rates Build-Up, Award Fee Application and Distribution of Cost- Reimbursable Work
Attachment JL.5 - Indirect Ceiling Rate Form, Award Fee Application and Distribution of Cost- Reimbursable Work
Attachment JL.6 - Service Contract Labor Standards (SCA) and Wage Rate Requirements (Construction) (DBA) Ceiling Labor Rate Form
Attachment JL.7 - Proposed, Historical and Year to Date Indirect Rates
Attachment JL.8 - Cost Model Worksheet
Attachment JL.8A - Cost Model Summary Sheet
Attachment JL.8B - Direct Cost Annual Sick Leave Calculations
Attachment JL.9 – Award Fee Plan
Attachment JL.10 - Service Contract Labor Standards and Wage Rate Requirements
Attachment JL.11 – Factor 1 Corporate Experience Example Project Form for IDIQ (Amendment 0001)
Attachment JL.12 – Factor 1 Corporate Experience Example Project Form for a Standalone Contract or a Task Order not on an IDIQ Contract provided as an Example Project (Amendment 0001)
Attachment JL.13 - Specialized Technical Experience on Example Projects
Attachment JL.14 – Key Personnel Experience/Qualifications
Attachment JL.15 – Past Performance Questionnaire
Attachment JL.16 – Quality Assurance Surveillance Plan
Attachment JL.17 – Commercial Vehicle and Truck Inspection Procedures
Attachment JL.18 – Standard Operating Procedure Field Data Collection and Management
Attachment JL.19 – Site Visit Map
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
SECTION L REVISIONS 0001
The following revisions have been made to Section L:
FROM:
2. PROPOSAL FORMAT
The Non-Cost (Technical and Past Performance) and Cost Proposals shall be submitted in separate files, labelled appropriately, and must include a cover page with the name of the prime contractor, addresses, phone and fax numbers, email addresses, solicitation number, and point of contact.
Offerors must submit required information for non-cost and cost proposals as follows:
Volume 1: Non-Cost (Technical and Past Performance) Proposal - Submit in 8-1/2 x 11 format, font size 11-12.
The document should be submitted as both an Adobe Acrobat file (.pdf format) and as an MS Word file. (Note:
cover page, letters of commitment, Joint Venture/teaming/partnership agreements, award fee determinations, and Past Performance Questionnaires may be submitted in Adobe Acrobat only). Additionally, it is acceptable for offerors to submit multiple MS Word files that are organized by subfolders instead of submitting one MS Word file.
Proposal submission is limited to 65 pages. Note that letters of commitment and Joint Venture/ teaming/ partnership agreements, organizational conflicts of interest statements, Attachment JL.13 – Specialized Technical Experience on Example Projects, past performance questionnaires, award fee determinations, or CPARS evaluations are not applied against the overall page limit. Further, introductory sheets (e.g. Table of Contents, List of Figures, List of Acronyms, and Cross-Reference Sheet), a one-page coversheet to identify the contractor and the proposal, and the listing of team member’s corporatenames and point of contact information are not applied against the overall page limit. The coversheet and listing of team members shall be limited to two pages in total (one-page each). There is not a page limitation for the introductory sheets. All information provided on the introductory sheets is not evaluated. Offerors are requested to number the pages consecutively for each factor. Within the factors, only the pages that are applied to the overall page limit should contain consecutive page numbers. If a form that is provided as a JL attachment in this solicitation is a form that is applied to the overall page number limit, a page number should be added to the form. Any pages in excess of the maximum limits stated herein shall be removed and not evaluated.
TO:
2. PROPOSAL FORMAT
The Non-Cost (Technical and Past Performance) and Cost Proposals shall be submitted in separate files, labelled appropriately, and must include a cover page with the name of the prime contractor, addresses, phone and fax numbers, email addresses, solicitation number, and point of contact.
Offerors must submit required information for non-cost and cost proposals as follows:
Volume 1: Non-Cost (Technical and Past Performance) Proposal - Submit in 8-1/2 x 11 format, font size 10-12.
The Organizational Chart submitted for Factor 2 Management Approach may be submitted in 8-1/2 x 14 or 11 x 17 format. The document should be submitted as both an Adobe Acrobat file (.pdf format) and as an MS Word file.
(Note: cover page, letters of commitment, Joint Venture/teaming/partnership agreements, award fee determinations, and Past Performance Questionnaires may be submitted in Adobe Acrobat only). Additionally, it is acceptable for offerors to submit multiple MS Word files that are organized by subfolders instead of submitting one MS Word file.
Proposal submission is limited to 65 pages. Note that letters of commitment and Joint Venture/ teaming/ partnership agreements, organizational conflicts of interest statements, Attachment JL.13 – Specialized Technical Experience on Example Projects, past performance questionnaires, award fee determinations, or CPARS evaluations are not applied against the overall page limit. Further, introductory sheets (e.g. Table of Contents, List of Figures, List of Acronyms, and Cross-Reference Sheet), a one-page coversheet to identify the contractor and the proposal, and the listing of team member’s corporate names and point of contact information are not applied against the overall page limit. The coversheet and listing of team members shall be limited to two pages in total (one-page each). There is not a page limitation for the introductory sheets. All information provided on the introductory sheets is not evaluated. Offerors are requested to number the pages consecutively for each factor. Within the factors, only the pages that are applied to the overall page limit should contain consecutive page numbers. If a form that is provided as a JL attachment in this solicitation is a form that is applied to the overall page number limit, a page number should be added to the form. Any pages in excess of the maximum limits stated herein shall be removed and not evaluated.
FROM:
(4) Factor 4, Past Performance:
(i) Solicitation Submittal Requirements
If a completed CPARS evaluation is available, it shall be submitted with the proposal for each of the projects listed under Factor 1, Corporate Experience. This includes all IDIQ contracts (meaning the entire IDIQ contract as a whole) submitted on Attachment JL.11; all task orders submitted in Table 2 of Section II of Attachment JL.12; and all standalone contracts submitted on Attachment JL.12. If a final CPARS evaluation is not available or if the final CPARS evaluation does not provide cumulative information, Offeror(s) are to submit all interim evaluations, if available, for the entire period for any and all projects that are submitted for Factor 1. Offeror(s) should include a summary sheet with its proposal of all CPARS being submitted to include contract number, task order number and indicate if the CPARS evaluation was an interim or final. IF THERE IS NOT A COMPLETED CPARS EVALUATION, the Past Performance Questionnaire (PPQ), Attachment JL.15 included in the solicitation is provided for the Offeror to submit to the client for each project the Offeror includes in its proposal for Factor 1, Corporate Experience. PPQ’s should be included in the non-cost proposal and only be submitted for the example projects. AN OFFEROR SHALL NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.
TO:
(4) Factor 4, Past Performance:
(ii) Solicitation Submittal Requirements
If a completed CPARS evaluation is available, it shall be submitted with the proposal for each of the projects listed under Factor 1, Corporate Experience. This includes all IDIQ contracts (meaning the entire IDIQ contract as a whole) submitted on Attachment JL.11; all task orders submitted in Table 1 of Section II of Attachment JL.11; and all standalone contracts and/or task orders submitted on Attachment JL.12. If a final CPARS evaluation is not available or if the final CPARS evaluation does not provide cumulative information, Offeror(s) are to submit all interim evaluations, if available, for the entire period for any and all projects that are submitted for Factor 1.
Offeror(s) should include a summary sheet with its proposal of all CPARS being submitted to include contract number, task order number and indicate if the CPARS evaluation was an interim or final. IF THERE IS NOT A COMPLETED CPARS EVALUATION, the Past Performance Questionnaire (PPQ), Attachment JL.15 included in the solicitation is provided for the Offeror to submit to the client for each project the Offeror includes in its proposal for Factor 1, Corporate Experience. PPQ’s should be included in the non-cost proposal and only be submitted for the example projects. AN OFFEROR SHALL NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS
AVAILABLE.
(End of Summary of Changes)