C09.0 Government Response to RFC 007 N4523AR221050 Caisson 1.pdf
PDF 178 KB Posted
- Solicitation number
- N4523A22R1050
About this file
This document includes a government response to a request for clarification and the related federal contract opportunity solicitation. The government response indicates that it is reviewing current statement of work requirements in light of global supply chain issues with long lead time materials, and anticipates adjusting requirements no later than March 17, 2022.
The federal contract opportunity solicitation is to award a firm-fixed price contract for maintenance, repair and preservation of Caisson One. Work will be performed at the contractor's ship repair facility located in the Puget Sound, Washington region, and includes tasks such as hull cleaning and preservation, tank cleaning, valve replacement, and operational testing. The period of performance is scheduled from June 28, 2022 to December 12, 2022. The Navy intends to make award to the responsible contractor submitting the lowest priced technically acceptable proposal in accordance with FAR 15.101-2.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Government Responses to RFC 007
7) Question: Contractor has solicited multiple equipment suppliers to source the valves, valve operators, pumps and motors for Work Items 529-11-002, 529-21-001 and 529-21-004. Suppliers are reporting significant lead times due to the ongoing global supply chain challenges. (Longest lead time being quoted for material is 40 weeks.)
If the Contractor were to order all Long Lead Time Material within 5 days of contract award as required, the equipment listed above would not be received by the Contractor until after the current Delivery Date of 12-DEC-2022.
Contractor requests that the Government reevaluate the Period of Performance due to the lead time challenges presented. It is recommended that Production Start be delayed to allow sufficient time for the procurement of all Long Lead Time Material.
Response: The Government is reviewing the current Statement of Work (SOW)/requirements in light of global supply chain issues with long lead time material and anticipates adjusting the
SOW/requirements no later than 17 March 2022.