This solicitation seeks proposals for maintenance, repair, and preservation services for Caisson One. Key details include the vessel characteristics of 94 feet long with a draft of 20 feet 11 inches. The contractor must have a drydock facility located in the Puget Sound, WA region capable of servicing the vessel. Required work includes hull preservation, tank cleaning and inspection, valve replacement, grease line renewal, mimic board installation, and operational testing. The period of performance is expected from June 28, 2022 to December 12, 2022. The government intends to award a firm-fixed price contract to the responsible contractor with the lowest price using FAR part 15 procedures. The NAICS code is 336611 and maximum employee size is 1,250. Proposals are due by the dates outlined in Section L and drawings can be requested by February 9, 2022.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A X B X C
D
EX
X G F 43 - 54
55 - 69 H 70 - 73
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 73
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N4523A 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
BRITTANY CHARTIER (360) 476-6438
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
2 - 7
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
8 - 21 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
22 - 23
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 25 - 28 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
29 - 41
PART II - CONTRACT CLAUSES
N4523A PSNS&IMF
COMMAND SPECIALTY CONTRACTING SUPPORT
CODE 440
1400 FARRAGUT AVE
BREMERTON WA 98314-2026
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
20 Jan 2022
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N4523A22R1050
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
CLIN
Number
Caisson 1
FFP
Accomplish maintenance, repair, and preservation of Caisson 1 in accordance with the Statement of Work (SOW), Attachment J-1.
NET AMT
0001AA
1 Job
Caisson 1 - Base Package
FFP
Accomplish maintenance, repair, and preservation of Caisson 1 in accordance with the Statement of Work (SOW), Attachment J-1. This SLIN supports the base work package.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MILSTRIP: TBD
PSC CD: J019
0001AB
Caisson 1 - LOE to Completion
FFP
Accomplish maintenance, repair and preservation of the Caisson 1 in accordance with the Statement of Work (SOW), Attachment J-1. This SLIN supports authorized Level of Effort (LOE) to Completion.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MILSTRIP: TBD
Over and Above Work - Caisson 1
FFP
Additional repairs not specified under CLIN 0001 (e.g. within scope new work identified during execution of the contract), per DFARS 252.217-7028 "Over and Above Work (DEC 1991)".
FOB: Destination
Required Reports (CDRLs)
FFP
Contract Data Requirements List (CDRL / DD Form 1423) - Submittals as required by CLINs 0001 and 0002. See Exhibit A. CDRLs ARE NOT
SEPARATELY PRICED (NSP).
CLAUSES INCORPORATED BY FULL TEXT
B-231-H002 WORKSITE TRAVEL COSTS (NAVSEA) (OCT 2018)
(a) The contractor shall not charge, and the Government shall not pay, as an allowable cost under this contract, any manhour costs (whether straight-time or overtime) for contractor personnel or subcontractor personnel traveling to or from worksites, including travel to worksites other than the contractor's facility for performance of contract work.
(b) Workers being paid under this contract, as prime contractor personnel or subcontractor personnel, will complete a full shift at the worksite, and no compensation will be paid for travel time before or after the shift.
(c) This requirement pertains only to payments for travel time before or after these workers' regular shifts (commuting costs), and does not apply to legitimate travel costs incurred during normal working hours, provided that those costs are otherwise reasonable, allocable and allowable and approved in writing by the Government. This requirement does not apply to manufacturer's representatives or Original Equipment Manufacturer (OEM) representatives when specifically required by the Government work specifications.
(d) Additionally, the contractor shall not charge, and the Government shall not pay, any transportation costs under this contract associated with transporting contractor or subcontractor personnel between the contractor's facility (or subcontractor's facility), and any other worksite to perform ship repair, maintenance or modernization.
Transportation costs include, but are not limited to, bus fare, car fare, train fare, or boat fare, paid by the work force, or paid by the contractor on behalf of the work force.
(End of text)
SECTION B: NOTES
Note A: Growth Management Program:
The Government has elected to utilize the Growth Management Program which is comprised of two procedures: (1) Small Dollar Value Growth (SDVG) and, (2) Level of Effort (LOE) to Completion. The purpose of this program is to manage growth work in an effective and efficient manner. The award resulting from this solicitation will not utilize the SDVG process; it will only utilize the LOE to Completion procedure.
This note describes the process of LOE to Completion in detail, whereas Section B, Note B provides further information about what falls under the procedure, limits of use, and the specific amounts to be awarded under this solicitation. The following steps shall be used for executing growth work when utilizing LOE to Completion:
1. The Contractor shall report proposed growth through the normal Condition Found Report (CFR) process per contract terms.
2. The Contracting Officer (KO) shall determine if the identified work is within contract scope. If within scope, the PM (or designated representative) will set forth on the Growth Management Request Form (Attachment J-7) the requirements to be accomplished. If not within scope, the Request for Contract Change (RCC) method must be used to process the work.
3. Once started, the Growth Management Request Form will be sent to the Contractor to provide pricing and supporting data to support the growth work requirements. An authorized representative of the Contractor and the PM or Shipbuilding Specialist (SBS) shall evaluate the proposed hours and material to determine if the price reflects the full technical scope.
4. The PM shall endorse the Growth Management Request Form and forward the Growth Management Request Form to the Contracting Officer for review and coordination.
5. The Contracting Officer will negotiate the hours and material, verify the correct application of labor/G&A/profit rates as applicable, and issue the Growth Management Request Form signed by the Contracting Officer to direct the work. All growth work under the LOE to Completion process must be directed by the Contracting Officer. The PM and Contracting Officer (or designated representatives) will ensure the growth data is captured in the Growth Management Program Tracking Log (Attachment J-8).
6. Once the work under a directed Growth Management Request Form has been accomplished, the Contractor and the Contracting Officer’s Representative will sign off for final acceptance/completion of the requirement.
In the event that additional growth is required and not funded under the Growth Management Program, the Request for Contract Change (RCC) process shall be utilized.
Note B: Level of Effort to Completion – Growth:
1. The Contractor agrees to provide the Level of Effort (LOE) to Completion under CLIN 0001AB which will be a combination of 13,813 man hours and $91,776.34 materials (to include the application of burdened labor, G&A and profit rates as proposed under the base contract, as applicable) for the performance of growth work related to work items defined in CLIN 0001AA. Both of these subCLINS reside with CLIN 0001.
2. The total LOE to Completion for the performance of the above SLIN shall be man-hours of direct labor and associated material required to support that labor and effort. The mix of labor and material may be adjusted, but may not exceed the dollar value of CLIN 0001AB.
3. The Contractor and the Contracting Officer will utilize the Growth Management Program Tracking Log (Attachment J-8) to identify/record the expended effort associated with this Note. This tracker shall assist with identifying the remaining funds under the LOE to Completion and serve as a declining balance log.
All growth work meeting the criteria of paragraph 1 above shall be accepted under this program without delay and disruption in vessel redelivery.
4. Effort performed in fulfilling the LOE to Completion obligations specified above shall only include effort performed in direct support of this contract and shall not include time and effort expended on such things as local travel (i.e.to and from an employee's usual work location), uncompensated effort while on travel status, truncated lunch periods, work (actual or inferred) at an employee's residence or other non-work locations.
5. The LOE to Completion labor hours and material are within the general scope of the work stated in the contract and may not be used to: (1) direct a change as defined in the clause FAR 52.243-1 CHANGES – FIXED PRICE (AUG 1987) or (2) change any of the terms or conditions of the contract.
6. If, in the opinion of the Contractor, any effort directed in the Growth Management Request Form (Attachment J-7) calls for effort outside the scope of the contract, the Contractor shall notify the Contracting Officer in writing within two (2) working days after the receipt of any such direction. The Contractor shall not proceed with the work affected by the Growth Management Request Form unless and until the Contractor is notified by the Contracting Officer that directed work is within the scope of this contract. Thereafter, any remaining disagreement on the scope issue shall be a dispute under the Disputes clause; however, nothing in this clause shall excuse the Contractor from proceeding with the subject growth work as directed by Contracting Officer.
7. After the scheduled period of performance is complete and when it is evident that no additional work will be tasked, the remaining funds under the LOE to Completion SLIN, 0001AB, are subject to a descope Request for Contract Change and shall be descoped (deobligated) in their entirety through a bilateral contract modification.
Note C: Rates for Contract Modifications:
The Government intends to establish rates under the base contract which shall be used by the Contractor in proposals for in-scope growth work and any identified out of scope new work during the execution of this contract.
The rates shall also be utilized, in the same methodology as proposed, for the LOE to Completion process. The rates and methodology/formulas will be input under this Note upon contract award.
Burdened Labor Rate/Manhour: TBD at Award Fringe Rate: TBD at Award Overhead Rate: TBD at Award G&A Rate: TBD at Award Profit Rate: TBD at Award FCCOM Rate: TBD at Award
The Government expects that 3,500 square inches of base metal repair through weld build-up will be required.
Additionally, the Government expects that 240 linear inches of base metal repair through “V” out and weld fill will be required. The Government shall establish rates (per square inch and per linear inch, respectively) under the base contract which will be used for base metal repairs exceeding 3,500 sq. in. and 240 lin. in. The weld build up rate will be calculated as the fully burdened rate (Labor and Materials) for 3,500 sq. in. divided by 3,500 to establish the per square inch rate for weld build up repairs in excess of 3,500 square inches. The “V” out excavate and weld fill fully burdened rate will be calculated as the fully burdened rate (Labor and Materials) for 240 lin. in. divided by 240 to establish the per linear inch rate for “V” out excavation and weld fill repairs in excess of 240 linear inches. G&A and Profit will be added to these rates at the contract modification level.
Over And Above Base Metal Repair
- Weld Build Up: (H14)/3,500 = price per square inch
- “V” Out & Weld Fill: (H15)/240 = price per linear inch
The cells referred to above are found in Attachment J-2 Price Proposal Worksheet.
(end of note)
Section C - Descriptions and Specifications
GENERAL CONTRACT REQUIREMENTS
C-1.0 GENERAL CONTRACT REQUIREMENTS
The Northwest Regional Maintenance Center (NWRMC), Puget Sound Naval Shipyard & Intermediate Maintenance Facility (PSNS & IMF), Industry Management Department, Code 400 intends to utilize this contract to procure Caisson 1 upkeep and repairs. Repairs to include the following: Replace the port rubber seal and perform required inspections and maintenance. Conduct ultrasonic and visual inspections of the hull, weather deck, tanks, piping and operations deck. Clean and pump tanks. Maintain deck hatches. Remove existing and install new mimic board. Test alarm systems. Clean ventilation and add air filter box. Renew all valves. Install super flood discharge piping covers.
Renew dewatering pumps. Renew grease lines and steady bearings. Renew actuator stands. Renew actuators. Renew valve-stem extension shafts. Remove, clean and reinstall rubber fendering. Install handrail swing gate. Renew boarding ladders. Preserve hull, weather deck, weather deck handrails, tanks, piping and operations deck. Renew zinc anodes. Conduct operational testing. Dock and undock the vessel at the contractor’s facility. Coordinate the delivery of vessel to and from Puget Sound Naval Shipyard and Intermediate Maintenance Facility, Bremerton, WA.
All work to be performed during this requirement will be in accordance of this statement of work. Complete descriptions of all work items can be found in Attachment J-1.
The following work items shall be accomplished while in dry-dock:
119-10-001 Rubber Seal; replace 120-11-001 Hull Exterior Surfaces; inspect 123-16-002 Tank Interior Surfaces; inspect 167-11-002 Deck Hatches; repair 529-11-001 Piping, Drainage and Ballasting System; inspect 529-11-002 Valves; replace 529-11-003 Super flood Pump Discharge Piping Covers; install 529-21-001 Dewatering pump valve piping; inspect 529-21-002 Grease Lines and Steady Bearings; replace 529-21-003 Actuator stands; replace 529-21-004 Actuators; replace, 529-21-005 Valve Stem Assemblies; renew 611-11-001 Rubber Fendering; inspect 623-12-001 Boarding Ladder; renew 631-10-001 Tank Preservation; accomplish 631-10-002 Operations Deck Compartment; preserve 631-21-001 Handrails and Stanchions; preserve, 631-31-001 Hull Preservation; accomplish, 633-11-001 Zinc Anodes; install, 634-11-001 Non-skid; replace, 982-31-001 Operational Test Support; provide, paragraph 3.3.
Operate existing, newly installed, or repaired shipboard equipment in the performance of the Contractor’s work effort only while vessel is in dry-dock. Only Navy Shipyard Personnel will operate shipboard equipment while vessel is waterborne.
a. The Contractor shall meet the following Contract Production Milestones:
No later than Production Start + 60 days: Exterior Hull and Weather Deck SSPC-SP-6 completion, and grit removal. Complete steel inspections and submit required inspection CFRs of item 120-11-001 paragraphs
3.1 and 3.2 and item 130-11-001 paragraphs 3.1 and 3.2.
No later than Production Start + 70 days: Government answers Inspection CFRs for Exterior Hull and Weather Deck.
No later than Production Start + 80 days: All Tanks SSPC-SP-6 completion and grit removal. Complete steel inspections of steel inspections and submit required inspection CFRs of item 123-16-002 paragraphs
3.1 and 3.2 for all tanks, and 529-11-001 paragraphs 3.1 and 3.2 for all tanks.
No later than Production Start + 90 days: Government answers Inspection CFRs for all tanks, piping and the operations deck.
No later than Production Start +100 days: Exterior hull and weather deck weld repairs completed.
No later than Production Start +120 days: Tank, piping and operations deck weld repairs completed.
b. The Contractor shall accomplish base metal repairs as described in 042-10-001 based on results of the CFR process. Additional base metal repairs (in excess of 3,500 square inches. or 240 linear inches) will be priced at the same rates as the per inch price for 042-10-001 paragraphs 3.1.1 and 3.1.2.
c. Supervisor – means the Contracting Officer (KO)
d. Production Start – means the first day of the period of performance (POP)
C-202-H001 ADDITIONAL DEFINITIONS–BASIC (NAVSEA) (OCT 2018)
(a) Department - means the Department of the Navy.
(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA)
(OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) (OCT 2018)
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
C-211-H004 HEAVY WEATHER PLAN (NAVSEA) (OCT 2018)
(a) In order to ensure that Naval vessel(s), material and Government property are protected during destructive weather such as gales, storms, hurricanes, high winds, heavy snow, ice and high water, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69 dated 18 November 2016. A copy of Standard Item (SI) 009-69 can be obtained from via the internet by going to:
http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI/ and selecting the NAVSEA Standard Items (NSI) tab then select the applicable FY standard item link and then select SI 009-69. In accordance with SI 009- 69, the Contractor shall furnish to the cognizant Regional Maintenance Center (RMC), a copy of such HWP, and shall make such changes in the plan as the RMC considers necessary and reasonable to protect and care for vessel(s), material and Government property.
(b) In the event the RMC directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such Government direction.
C-211-H010 TUG AND PILOT SERVICES (NAVSEA) (OCT 2018)
The Contractor shall provide necessary tug and pilot services to move the vessel(s) from the fairway of the plant to the pier or dock, and upon completion of all work from the pier or dock, to the fairway of the plant.
C-211-H017 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (DEC 2018)
The contractor may request that this contract be updated to include the current version of the applicable specification or standard if the update does not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval of its request to update by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with the detailed obligations to which the Contractor committed itself in Proposal TBD dated TBD in response to Solicitation No.
N4523A22R1050.
(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following "the specifications" in the order of precedence.
C-217-H005 GROWTH AND NEW WORK (NAVSEA) (JAN 2019)
(a) The Contractor is required to notify the Contracting Officer via email regarding growth and new work within 30 days of discovery:
(1) of any apparent errors or omissions in the contract (SF 33, specifications, drawings, etc.); and,
(2) of any/all conflicts between the contract package and actual conditions observed during ship check(s) and/or contract execution.
(b) Growth work is synonymous with over and above work, which is described in DFARS 252.217-7028, Over and Above Work and it provides the process for adjudication.
(c) New work is distinguished from over and above work and is outside the scope of the competitively procured requirement. New work will be approved in accordance with FAR Part 6 and associated policies and procedures.
(d) The Government will NOT negotiate modifications to increase the contract price to address errors or omissions to the contract package which were reasonably apparent to the contractor prior to proposal submission.
(End of Text)
C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST 5510.2D.
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non- U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "Default (Fixed-Price Supply and Service)" (FAR 52.249-8), "Default (Fixed-Price Research and Development)" (FAR 52.249-9) or "Termination (Cost Reimbursement)" (FAR 52.249- 6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S.
Navy personnel who are non-U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.
C-222-H002 DEPARTMENT OF LABOR SAFETY AND HEALTH STANDARDS FOR SHIPBUILDING
(NAVSEA) (OCT 2018)
Attention of the Contractor is directed to Public Law 91-596, approved December 29, 1970 (84 Stat. 1590, 29 USC
655) known as the "Occupational Safety and Health Act of 1970" and to the "Occupational Safety and Health Standards for Shipyard Employment" promulgated thereunder by the Secretary of Labor (29 CFR. 1910 and 1915).
These regulations apply to all shipbuilding and related work, as defined in the regulations. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
C-223-H002 SAFETY, HEALTH AND FIRE REQUIREMENTS FOR SHIP REPAIR (NAVSEA) (JAN 2019)
(a) Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.13). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations which it may have for compliance with the aforesaid regulations.
(b) SAFETY INSPECTOR/FIRE MARSHAL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshal shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.
(c) PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:
(1) Protective hard hats that meet the following specifications:
(i) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated by the Contractor to be equally effective.
(ii) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1-1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR 1910.135 Head Protection]
(2) Approved type Plano or prescription glasses meeting the following specifications:
(i) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1- 1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.
(ii) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1-1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF 1910.133 Protective eye and face devices.]
(3) Safety toe shoes, with built-in protective toe box that meet the following specifications:
(i) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.
(ii) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]
C-223-H004 MANAGEMENT AND DISPOSAL OF HAZARDOUS WASTE (NAVSEA) (MAR 2019)
(a) General
(1) The Contractor shall comply with the Resource Conservation and Recovery Act (RCRA), the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), 10 U.S.C. 7311 and all other applicable Federal, State and local laws, codes, ordinances and regulations for the management and disposal of hazardous waste.
(2) Nothing contained in this special contract requirement shall relieve the Contractor from complying with applicable Federal, State, and local Laws, codes, ordinances, and regulations, including obtaining licenses and permits, giving notices and submitting reports, in connection with hazardous waste management and disposal in the performance of this contract. Nothing contained herein shall serve to alter either party's liability or responsibility under CERCLA.
(3) Materials contained in ship systems are not waste until after removal from the system.
(b) Identification of Hazardous Wastes – 077-11-001 of this contract identifies the types and amounts of hazardous wastes that are required to be removed by the Contractor, or that are expected to be generated, during the performance of work under this contract.
(c) Generator Identification Numbers
(1) Documentation related to hazardous waste generated solely by the physical actions of ship's force or Navy employees on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law.
(2) Documentation related to hazardous waste generated solely by the physical actions of Contractor personnel shall only bear a generator identification number issued to the Contractor pursuant to applicable law. Regardless of the presence of other materials in or on the shipboard systems or structures which may have qualified a waste stream as hazardous, where the Contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator identification number issued to the Contractor.
(3) Documentation related to hazardous waste generated by the combined physical actions of Navy and Contractor personnel shall bear a generator identification number issued to the Contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law.
(4) Notwithstanding paragraphs (c)(1) - (c)(3) above, hazardous wastes are considered to be co-generated in cases where: (a) the Contractor merely drains a system and such drainage creates hazardous waste or (b) the Contractor performs work on a system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste. Documentation related to such co-generated waste shall bear a generator identification number in accordance with the provisions of paragraph (c)(3) above.
(5) In the event of a failure by the parties to agree to the assignment of a generator identification number to any hazardous waste as set forth in paragraphs (c)(1) through (c)(4) above, the Government may direct which party or parties shall provide generator identification numbers for the waste and such number(s) shall be used on all required documentation. Any disagreement with this direction shall be a dispute within the meaning of clause of this contract entitled "Disputes" (FAR 52.233-1). However, the Contractor shall not stop any work but shall continue with performance of all work under this contract as specified in the "DISPUTES" clause.
(6) Hazardous Waste Manifests - For wastes described in (c)(2), (c)(3), and (c)(4) above (and (c)(5) as applicable), the Contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the Manifest is required for disposal. The Contractor shall obtain COR concurrence with the categorization of wastes under paragraphs (c)(3) and (c)(4) above before completion of the manifest. Manifests prepared pursuant to paragraph (c)(1) above shall be presented to the COR for completion after the hazardous waste has been identified.
(7) RESERVED.
C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit A, attached hereto.
C-228-H001 INDEMNIFICATION FOR ACCESS TO VESSEL (NAVSEA) (DEC 2018)
Notwithstanding any provision in the "Access to Vessel" clause (DFARS 252.217- 7011), or any other clause of the contract, the Contractor agrees to allow officers, employees, and associates of the Government, or other prime contractors with the Government and their subcontractors, and officers, employees, and associates of offerors on other contemplated work, admission to the Contractor's facilities and access to the vessel without any further request for indemnification from any party, which has not been previously included in the contract price.
C-233-H001 DOCUMENTATION OF REQUESTS FOR EQUITABLE ADJUSTMENT--BASIC (NAVSEA) (OCT 2018)
(a) For the purposes of this special contract requirement, the term "change" includes not only a change that is made pursuant to a written order designated as a "change order" but also (1) an engineering change proposed by the Government or by the Contractor and (2) any act or omission to act on the part of the Government in respect of which a request is made for equitable adjustment.
(b) Whenever the Contractor requests or proposes an equitable adjustment of $100,000 or more per vessel in respect to a change made pursuant to a written order designated as a "change order" or in respect to a proposed engineering change and whenever the Contractor requests an equitable adjustment in any amount in respect to any other act or omission to act on the part of the Government, the proposal supporting such request shall contain the following information for each individual item or element of the request:
(1) A description (i) of the work required by the contract before the change, which has been deleted by the change, and (ii) of the work deleted by the change which already has been completed. The description is to include a list of components, equipment, and other identifiable property involved. Also, the status of manufacture, procurement, or installation of such property is to be indicated. Separate description is to be furnished for design and production work.
Items of raw material, purchased parts, components and other identifiable hardware, which are made excess by the change and which are not to be retained by the Contractor, are to be listed for later disposition;
(2) Description of work necessary to undo work already completed which has been deleted by the change;
(3) Description of work not required by the terms hereof before the change, which is substituted or added by the change. A list of components and equipment (not bulk materials or items) involved should be included. Separate descriptions are to be furnished for design work and production work;
(4) Description of interference and inefficiencies in performing the change;
(5) Description of each element of disruption and exactly how work has been, or will be disrupted:
(i) The calendar period of time during which disruption occurred, or will occur;
(ii) Area(s) aboard the vessel where disruption occurred, or will occur;
(iii) Trade(s) disrupted, with a breakdown of manhours for each trade;
(iv) Scheduling of trades before, during, and after period of disruption;
(v) Description of measures taken to lessen the disruptive effect of the change;
(6) Delay in delivery attributable solely to the change;
(7) Other work attributable to the change;
(8) Supplementing the foregoing, a narrative statement of the direct "causal" relationship between any alleged Government act or omission and the claimed consequences therefor, cross-referenced to the detailed information provided as required above; and
(9) A statement setting forth a comparative enumeration of the amounts "budgeted" for the cost elements, including the material costs, labor hours and pertinent indirect costs, estimated by the Contractor in preparing its initial and ultimate proposal(s) for this contract, and the amounts claimed to have been incurred and/or projected to be incurred corresponding to each such "budgeted cost" elements.
(c) Each proposal in excess of $100,000 submitted in support of a claim for equitable adjustment under any requirement of this contract shall, in addition to the information required by paragraph (b) hereof, contain such information as the Contracting Officer may require with respect to each individual claim item.
(d) It is recognized that individual claims for equitable adjustment may not include all of the factors listed in paragraph
(b) above. Accordingly, the Contractor is required to set forth in its proposal information only with respect to those factors which are comprehended in the individual claim for equitable adjustment. In any event, the information furnished hereunder shall be in sufficient detail to permit the Contracting Officer to cross-reference the claimed increased costs, or delay in delivery, or both, as appropriate, submitted pursuant to paragraph (c) of this requirement, with the information submitted pursuant to paragraph (b) hereof.
C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018)
(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
C-242-H002 POST AWARD MEETNG (NAVSEA) (OCT 2018)
(a) A post-award meeting with the successful offeror will be conducted within [ * ] days after award of the [contract / task order]. The meeting will be held at the address below:
Location/Address: [ * ]
(b) The contractor will be given [ * ] working days notice prior to the date of the meeting by the Contracting Officer.
(c) The requirement for a post-award meeting shall in no event constitute grounds for excusable delay by the contractor in performance of any provisions in the [contract / task order].
(d) The post-award meeting will include, but is not limited to, the establishment of work level points of contact, determining the administration strategy, roles and responsibilities, and…
This is the start of the file's text. The full file is on GovTribe.