Attach 01 PPI Response Sheet.pdf

PDF 438 KB Posted

Attached to
NORTHWEST MULTIPLE AWARD CONSTRUCTION CONTRACT (NW MACC) Federal contract opportunity
Solicitation number
N4425521R4000
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document contains responses to questions from potential offerors on a solicitation for an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) to provide construction services primarily within the Naval Facilities Engineering Systems Command (NAVFAC) Northwest area of responsibility. The solicitation involves new construction, renovation, alteration, demolition and repair work done by design-build or design-bid-build methods on various types of facilities. It is a partial small business set-aside with a NAICS code of 236220 and size standard of $36.5 million in average annual receipts. Key details addressed in the questions and answers include clarifying the use of attachments, past performance evaluation criteria, confirming points of contact, and eligibility of small business awardees to compete on larger task orders over $20 million in value.

View the file

Other files for this federal contract opportunity

Other files attached to NORTHWEST MULTIPLE AWARD CONSTRUCTION CONTRACT (NW MACC), newest first.
File Type Posted
21R4000_Amend 0013_8.11.22.pdf PDF
21R4000_Amend_0011_7.16.22.pdf PDF
SF30_Amend_0010.pdf PDF
21R4000_Amend_0008_06.15.22.pdf PDF
21R4000_Amend_0007_6.02.22.pdf PDF
21R4000_Amend_0006_6.01.22.pdf PDF
Attach 1_GSA 60 day Extension01.PNG PNG image
Attachment G Financial Questionnaire Form01.docx DOCX document
21R4000_Amend_0005_5.27.22.pdf PDF
Attach 2_PPI Response Sheet.pdf PDF
Attach 1_PPI Response Spreadsheet.pdf PDF
21R4000_RFP_Amend 0004.pdf PDF
Attach 3_pre_proposal conference attendees.pdf PDF
Attach 4_NW MACC PreProposal Conf.pdf PDF
Attach K Safety Data Sheet Safety Narrative.docx DOCX document
Attach 2_PPI Response Spreadsheet.pdf PDF
Attach 1_GSA 60 day Extension.PNG PNG image
Attach L_PPI Form.doc DOC document
21R4000_Amend_0003_5.20.22.pdf PDF
Attachment A PIEE Vendor Access Instructions.pdf PDF
Attachment I Post Award Contractors Limitations Subcontracting SB Cert.doc DOC document
Attachment C Construction Design Experience Data Sheet.docx DOCX document
Attachment G Financial Questionnaire Form.docx DOCX document
Attachment E SB Subcontracting Record.docx DOCX document
Attachment B Offeror Team Composition Management.docx DOCX document
21R4000_Amend0002.pdf PDF
Attachment D PPQ Construction Experience.docx DOCX document
Attachment H HOOH and FOOH Analysis Form.xlsx XLSX spreadsheet
Attachment F SB Participation.docx DOCX document
Attachment G Surety Form.docx DOCX document
Attachment J Task Order Editable Clauses and Provisions.docx DOCX document
Attachment D PPQ Design Experience.docx DOCX document
21R4000_Amend-0001.pdf PDF
Attachment 1 PPI Form.doc DOC document
Attachment 2 PPI Response Spreadsheet.pdf PDF
Attachment C2 PPQ Design Experience.docx DOCX document
Attachment D Safety Data Sheet Safety Narrative.docx DOCX document
Attachment H HOOH and FOOH Analysis Form.xlsx XLSX spreadsheet
Attachment J Post Award Limitation on Subcontracting Certif.doc DOC document
Attachment G PIEE Vendor Access Instructions.pdf PDF
Attachment C1 PPQ Construction Experience.docx DOCX document
Attachment A Offeror Team Composition Management.docx DOCX document
Attachment M Task Order Editable Clauses and Provisions.docx DOCX document
Attachment L SB Subcontracting Record.docx DOCX document
Attachment F PPI Form.doc DOC document
N4425521R4000 RFP_Final.pdf PDF
Attachment E2 Financial Questionnaire Form.docx DOCX document
Attachment K SB Participation.docx DOCX document
Attachment E1 Surety Form.docx DOCX document
Attachment B Construction Design Experience Data Sheet.docx DOCX document
Show all 50

NORTHWEST MULTIPLE AWARD CONSTRUCTION CONTRACT (NW MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Govt Tracking

PPI Tech/CS Govt Response:

Addressed in Amendment

Number

RFP Section: Part 1 Page Number: 6 Paragraph: PROPOSAL DUE DATE, SUBMISSION, AND FORMAT

The RFP states "Proposals shall be submitted by email to: nancy.m.coffee.civ@us.navy.mil AND jason.a.lewis34.civ@us.navy.mil" and the following sentence instructs offerors to submit through the Procurement Integrated Enterprise Environment (PIEE) portal. Please confirm offerors are to submit proposals via PIEE and not submit via email.

CS The solicitation is revised. See Amendment 0001 Amend 0002

RFP Section: Part 1 Page Number: 9 & 10 Paragraph: Factor 2 - Corporate Experience (1) Construction Experience and (2) Design Experience The RFP states to use Attachment C for Construction & Design Experience; however, Attachment C is PPQ is for Construction and Design Experience. Please confirm Attachment B is to be used for the Construction & Design experience for Factor 2 Experience.

CS The solicitation is revised. See Amendment 0002 Amend 0002

RFP Section: Part 1 Page Number: 11 & 12 Paragraph: Factor 3 - Past Performance

a) Please confirm Offerors are to use Attachments C1 and C2 for the construction and design Past Performance Questionnaires and not Attachment D Safety Data Sheet Safety Narrative. b) If the Offeror has a Past Performance Questionnaire (PPQ-0) on file previously completed by the Client that matches all fields of the required Attachment C, may this be submitted in lieu of requesting a new PPQ specific to this solicitation?

CS The solicitation is revised. See Amendment 0002 Amend 0002

Reference: Attachment E2

a) Please confirm that Attachment E2 Financial Questionnaire Form is part of the Phase II proposal requirements and is not required for the Phase I proposal response. b) Please confirm attachment E1 Surety Form is required in the Phase I proposal response

CS See Price Factor Phase II Price Submission Amend 0002

RFP Section: Attachments A, D, E, F

Attachments A, D, E, F have an incorrect solicitation number N44255-21-R-2001 listed, please confirm these are the correct attachments for this Northwest AOR MACC N44255-21-R-4000, or revise these attachments to show the correct information.

CS The solicitation is revised. See Amendment 0002 Amend 0002

RFP Section: Part 1 Page Number: 8 Paragraph: Factor 1 - Technical Approach and Attachment A

The RFP states that Factor 1 - Technical Approach is not to exceed (1) one single-sided page; however, attachment A Offeror Team Composition and Management states not to exceed two (2) pages. Please clarify the page limit for Factor 1 Technical Approach.

CS The solicitation is revised. See Amendment 0002 Amend 0002

RFP Section: Part 1 Page Number: 4 Paragraph: Pre-Proposal Inquires

Attachment F PPI Form states: "PCO Email: AMANDA.R.BONUS.CIV@US.NAVY.MIL"; however, the RFP indicates that Nancy Coffee and Jason Lewis are the POCs for Pre-Proposal Inquiries (PPI). Please clarify who the Government POCs are for PPIs.

CS The solicitation is revised. See Amendment 0001 Amend 0002

RFP Section: Part 1 Page Number: 6 Paragraph: PROPOSAL DUE DATE, SUBMISSION, AND FORMAT

The RFP states "Proposals shall be submitted by email to: nancy.m.coffee.civ@us.navy.mil AND jason.a.lewis34.civ@us.navy.mil" and "Provide a copy, dated prior to the proposal due date and time, along with an emailed copy of the submission to the Government POCs: nancy.m.coffee.civ@us.navy.mil & amanda.r.bonus.civ@us.navy.mil." Please confirm these are the correct POCs.

CS The solicitation is revised. See Amendments 0001 and 0002 Amend 0002

Reference: Attachment E2

Attachment E2 has Amanda Bonus listed as a POC; however, in the RFP Amanda Bonus is only listed as the Government POC if the PIEE portal is down on the date and time of the proposal due date. Please confirm Amanda Bonus is the correct POC for Attachment E2.

CS The solicitation is revised. See Amendment 0002 Amend 0002

Reference: General

Would it be acceptable for Offerors to submit their RFIs in a single Excel log file that includes all of the required fields in the PPI form provided in the RFP? This assists with ease of tracking for both the Government and Offerors.

CS

The Pre-Proposal Inquiry form provided as an attachment is the only accepted method of submitting questions regarding this solicitation, which shall be submitted in writing and individually as an attachment.

Amend 0002

Reference RFP Page 49 of 96: The last paragraph under ‘Task Order Procedures’ indicates that failure to submit on a reasonable number of proposals may impact future consideration for proposed Task Orders or exercise of the option.

Under the next section ‘Competition’ on the same page, Item a. states that Task Orders valued at or below $20,000,000 are set-aside for Small Business awardees, and that Task Orders valued above $20M offer all awardees a fair opportunity to be considered for Task Order Award.

Question: Does the Government expect Small Business awardees to submit on some and/or most Task Orders valued above $20,000,000? If not, please confirm that a Small Business’ lack of response to Task Orders valued above $20,000,000 will not impact future consideration for proposed Task Orders or exercise of the option. Please also clarify whether Small Business awardees are required to notify the Government if they cannot submit an offer for a Task Order valued above $20M.

CS The solicitation is revised. See Amendment 0002 Amend 0002

Section 00 10 00 – Solicitation

“7. This acquisition will be solicited as an unrestricted procurement with an internal small business set-aside and full and open competition. Price evaluation preference will be given to HUBZone firms, in accordance with FAR 52.219-4.”

Will the price evaluation preference be given to HUBZone firms within the small business set-aside competition, or will the preference apply for all task orders regardless of set-aside status?

CS

The Price Evaluation Preference (PEP) will only be applied to work procured on a unrestricted basis. The PEP will not be applied when work is set aside for small businesses.

Amend 0002

Section 00 10 00 – Solicitation

“7. This acquisition will be solicited as an unrestricted procurement with an internal small business set-aside and full and open competition. Price evaluation preference will be given to HUBZone firms, in accordance with FAR 52.219-4.”

Will the HUBZone preference apply in the case of a large business-HUBZone firm joint venture, or will it only apply within the framework of a Mentor-Protégé relationship?

CS See response from PPI 022 Amend 0002

Reference: Evaluation Factors, Factor 3 – Past Experience

This question pertains to both the Offeror and the Designer of Record:

Will the Government allow us to present previously received PPQs (if needed), rather than asking our clients to provide new PPQs for this submittal?

CS Yes Amend 0002

Reference: Block 13.B of the Solicitation’s SF1442 –

Can you confirm that an offer guarantee is NOT required for the Phase I proposal, since there is no Task Order to bond at this time?

CS The solicitation is revised. See Amendment 0002 Amend 0002

Attachments with Amendment 0002:

Attach 01 PPI Response Sheet Attach A PIEE Vendor Access Instructions Attach B Offeror Team Composition Management Attach C Construction Design Experience Data Sheet Attach D PPQ Construction Experience/PPQ Design Experience Attach E Small Business Subcontracting Record Attach F Small Business Participation Attach G Financial Questionnaire Form/Surety Form Attach H HOOH and FOOH Analysis Form Attach I Post Award Contractors Limitations Subcontracting SB Cert Attach J Task Order Editable Clauses and Provisions