This document is a solicitation for construction services to repair and modernize Lima Wharf at Naval Base Guam. The work includes replacement of steel sheet piles, mooring systems, electrical substations, wharf utilities, construction of wharf lighting, and a bilge oily water treatment system. The estimated cost is between $100-250 million. Offerors must submit technical and past performance proposals along with pricing by September 9, 2020. The NAICS code is 237990 and size standard is $39.5 million. A pre-proposal conference and site visit will be held. The Navy is the contracting agency and this is a new procurement not replacing an existing contract.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY21 SPECIAL PROJECT RM 14-1420, Repair Lima Wharf, Naval Base Guam
See Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Aug-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4019220R1300
X 9B. DATED (SEE ITEM 11)
16-Jun-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Aug-2020
CODE
COMMANDING OFFICER - NAVFAC MARIANAS
MAR MCON
PSC 455, BOX 195
FPO AP 96540-2937
N40192 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4019220R1300
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0011
A. In accordance with FAR 52.252-3 Alterations in Solicitation (APR 1984), portions of this solicitation are altered as follows:
1. Revise RFP Part A, Standard Form (SF) 1442 Section 00 21 16 Instructions To Proposers as follows:
Replace FAR clause 52.217-4 Evaluation of Options Exercised at Time of Contract Award with FAR clause 52.217-5 Evaluation of Options.
2. Incorporate the following revisions to the Price Proposal Schedule. The Price Proposal Schedule incorporating the directed changes is issued as part of this amendment and provided herein as Enclosure (1):
a. CLINs 0002 THROUGH 0007 (OPTION ITEMS 1 THROUGH 6)
Add the following text:
“Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.”
b. SCHEDULE OF PRICES - NOTE for Option Items 1 through 6 (CLINs 0002 through 0007)
Remove the following text:
“In accordance with FAR 52.217-4, Evaluation of Options Exercised at Time of Contract Award, except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate the total price for the basic requirement together with any option(s) exercised at the time of award. It is anticipated that the Government may exercise one or more option(s) at time of award.”
Replace text with the following:
“Depending on availability of funds, Option Items 1 through 6 (CLINs 0002 through 0007) may be exercised within 180 calendar days from date of contract award. In accordance with FAR 52.217-5, Evaluation of Options, except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all prices for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).”
B. Notice 11 is provided in response to requests for information and is provided herein as Enclosure (2). Notice 11 is provided for INFORMATION ONLY. The solicitation remains unchanged unless it is amended in writing.
C. The date for receipt of proposals remains unchanged at September 9, 2020 at 4:30pm local time.
D. Offerors shall acknowledge this amendment in Block 19 of the Standard Form 1442 with their proposals.
SECTION 00 10 00 - SOLICITATION
CLIN 0002
The CLIN extended description has changed from:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the construction of the Bilge Oily Water Treatment System (BOWTS) in accordance with the drawings and specifications; except for work described in CLINs 0001 and 0003-0007.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the construction of the Bilge Oily Water Treatment System (BOWTS) in accordance with the drawings and specifications; except for work described in CLINs 0001 and 0003-0007.
Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
CLIN 0003
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the wharf lighting including associated transformers and switchgear in accordance with the drawings and specifications; except for work described in CLINs 0001-0002 and 0004-0007.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the wharf lighting including associated transformers and switchgear in accordance with the drawings and specifications; except for work described in CLINs 0001-0002 and 0004-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
CLIN 0004
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the north end wharf structural repair and modernization, including one industrial power mound, in accordance with the drawings and specifications; except for work described in CLINs 0001-0003 and 0005-0007.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the north end wharf structural repair and modernization, including one industrial power mound, in accordance with the drawings and specifications; except for work described in CLINs 0001-0003 and 0005-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
CLIN 0005
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the demolition of the existing electrical ductbank in accordance with the drawings and specifications; except for work described in CLINs 0001-0004 and 0006-0007.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the demolition of the existing electrical ductbank in accordance with the drawings and specifications; except for work described in CLINs 0001-0004 and 0006-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
CLIN 0006
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the corner fender at Lima-Mike wharf intersection in accordance with the drawings and specifications; except for work described in CLINs 0001-0005 and 0007.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the corner fender at Lima-Mike wharf intersection in accordance with the drawings and specifications; except for work described in CLINs 0001-0005 and 0007.
Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
CLIN 0007
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the steam infrastructure in accordance with the drawings and specifications; except for work described in CLINs 0001-0006.
To:
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the steam infrastructure in accordance with the drawings and specifications; except for work described in CLINs 0001-0006. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
The following have been modified:
SCHEDULE OF PRICES
NOTE for Contract Line Item Numbers (CLINs): The Offeror shall use the solicitation form above and the price proposal schedule on the following pages to indicate a price for ALL CLINs and SubCLINs. In the event there is a difference between a unit price and extended total amount, the unit price will be held to be the intended offer and the total of the CLINs will be recomputed accordingly.
NOTE for Option Items 1 through 6 (CLINs 0002 through 0007): Depending on availability of funds, Option Items 1 through 6 (CLINs 0002 through 0007) may be exercised within 180 calendar days from date of contract award. In accordance with FAR 52.217-5, Evaluation of Options, except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all prices for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS
The following have been added by full text:
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
(End of provision)
The following have been deleted:
52.217-4 Evaluation Of Options Exercised At The Time Of Contract
Award
JUN 1988
(End of Summary of Changes)
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Project
Total Base Bid
FFP
Total price of Base Bid SubCLINs 0001A through 0001R for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the repair and modernization of LIMA Wharf and appurtenances in accordance with the drawings and specifications for WON 1383711; except for work described in CLINs 0002-0007. See the Schedule of Prices for SubCLINs 0001A through 0001R.
FOB: Destination
PSC CD: Z2ED
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 1 Task OPTION Option 1 BOWTS
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the construction of the Bilge Oily Water Treatment System (BOWTS) in accordance with the drawings and specifications; except for work described in CLINs 0001 and 0003-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
PSC CD: Z2ED
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0003 1 Task OPTION Option 2 Wharf Lighting
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the wharf lighting including associated transformers and switchgear in accordance with the drawings and specifications; except for work described in CLINs 0001-0002 and 0004-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
PSC CD: Z2ED
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0004 1 Task OPTION Option 3 North End Wharf
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the north end wharf structural repair and modernization, including one industrial power mound, in accordance with the drawings and specifications; except for work described in CLINs 0001-0003 and 0005-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0005 1 Task OPTION Option 4 Existing Electrical Ductbank
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the demolition of the existing electrical ductbank in accordance with the drawings and specifications; except for work described in CLINs 0001-0004 and 0006-0007.
Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
PSC CD: Z2ED
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0006 1 Task OPTION Option 5 Corner Fender at Lima-Mike
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the corner fender at Lima-Mike wharf intersection in accordance with the drawings and specifications; except for work described in CLINs 0001- 0005 and 0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0007 1 Task OPTION Option 6 Steam Infrastructure
FFP
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the steam infrastructure in accordance with the drawings and specifications; except for work described in CLINs 0001-0006. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
FOB: Destination
PSC CD: Z2ED
NET AMT
SCHEDULE OF PRICES
NOTE for Contract Line Item Numbers (CLINs): The Offeror shall use the solicitation form above and the price proposal schedule on the following pages to indicate a price for ALL CLINs and SubCLINs. In the event there is a difference between a unit price and extended total amount, the unit price will be held to be the intended offer and the total of the CLINs will be recomputed accordingly.
NOTE for Option Items 1 through 6 (CLINs 0002 through 0007): Depending on availability of funds, Option Items 1 through 6 (CLINs 0002 through 0007) may be exercised within 180 calendar days from date of contract award. In accordance with FAR 52.217-5, Evaluation of Options, except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all prices for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
CLIN SubCLIN Quantity Unit Unit Price
Extended Total
Grand Total
0001 $
0001A BASE BID ITEM A 1 LS $ $
0001B BASE BID ITEM B 44,070 MT $ $
0001C BASE BID ITEM C 1 LS $ $
0001D BASE BID ITEM D 23 EA $ $
0001E BASE BID ITEM E 1 LS $ $
0001F BASE BID ITEM F 1 LS $ $
0001G BASE BID ITEM G 1 LS $ $
0001H BASE BID ITEM H 1 LS $ $
0001I BASE BID ITEM I 1 LS $ $
0001J BASE BID ITEM J 1 LS $ $
0001Ka BASE BID ITEM Ka 1 LS $ $
0001Kb BASE BID ITEM Kb 4840 CY $ $
Description
Floating Fenders
Heavy Weather Mooring System Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the landside heavy weather mooring system, including concrete anchor blocks and piles, in accordance with the drawings and specifications.
Total price for the entire work required for the floating fenders, in accordance with the drawings and specifications. The unit price for this Base Bid SubCLIN shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work complete for price adjustment in accordance with FAR 52.243-4, Changes.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the steel sheet pile bulkhead, tie back anchor beams, anchor piles, tie rods, including replacement of the mooring and fender systems, not including the fenders themselves, in accordance with the drawings and specifications.
Total price for the entire work required for the installation of the stone columns, including test section, complete and in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Stone Columns
Wharf Structural Repair and Modernization
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the paving in accordance with the drawings and specifications.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the rehabilitation and reinstallation of the crane rails in accordance with the drawings and specifications.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for mobilizing dredge and all related equipment and personnel onto and off project site.
New Electrical Substation
Utilities
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the new electrical substation including foundation, building, and all equipment therein, in accordance with the drawings and specifications.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the new electrical ductbank extension in accordance with the drawings and specifications.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for demolition of the existing electrical substation in accordance with the drawings and specifications.
Crane Rail Rehabilitation
Paving
Existing Electrical Substation Demolition
New Electrical Ductbank Extension
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the potable water, sewer, drainage, electrical and telecommunications utilities in accordance with the drawings and specifications.
Total price for the entire work required for dredging in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Dredging
Mobilize and Demobilize Dredge
PRICE PROPOSAL SCHEDULE for
WON 1383711 (RM14-1420)
Lima Wharf Repair, NBG Apra Harbor
TOTAL BASE BID
Total price of Base Bid SubCLINs 0001A through 0001R for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the repair and modernization of LIMA Wharf and appurtenances in accordance with the drawings and specifications for WON 1383711; except for work described in CLINs 0002-0007.
RFP Amendment 0011
Price
Extended Total
Grand TotalDescription
PRICE PROPOSAL SCHEDULE for
WON 1383711 (RM14-1420)
Lima Wharf Repair, NBG Apra Harbor RFP Amendment 0011
0001L BASE BID ITEM L MEC Clearance 1 LS $ $
0001Ma BASE BID ITEM Ma 790 LF $ $
0001Mb BASE BID ITEM Mb 2000 SF $ $
0001Mc BASE BID ITEM Mc 600 CY $ $
0001Md BASE BID ITEM Md Hydrocarbon Impacted Buried Debris Removal and Disposal 100 CY $ $
0001Me BASE BID ITEM Me Pesticides and Lead Impacted Soil Removal and Disposal 130 CY $ $
0001Mf BASE BID ITEM Mf 400 SF $ $
0001Mg BASE BID ITEM Mg 7000 LF $ $
0001Mh BASE BID ITEM Mh 1000 GAL $ $
0001Mi BASE BID ITEM Mi Oily Water Greater Than 2 ppm Removal and Disposal 4000 GAL $ $
0001N BASE BID ITEM N 830 CY $ $
ACM Building 2078 Removal and Disposal Total price for the entire work required for the removal, containment, and safe disposal of ACM materials at Building 2078 in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN wil be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
PLIC Cables Removal and Disposal Total price for the entire work required for the removal, containment, and safe disposal of PLIC cable materials in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Total price for the entire work required for the removal, containment, and safe disposal of oily water greater than 2 ppm in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will b used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Fill Import Total price for the entire work required for the importation, placement and compaction of select fill where soils require replacement due to contamination in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Hydrocarbon Impacted Soil Removal and Disposal
Oily Water Less Than 2 ppm Removal and Disposal Total price for the entire work required for the removal, containment, and safe disposal of oily water less than 2 ppm in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Total price for the entire work required for the removal, containment, and safe disposal of hydrocarbon impacted buried debris materials in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Total price for the entire work required for the removal, containment, and safe disposal of lead-based paint materials in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Total price for the entire work required for the removal, containment, and safe disposal of pesticide and lead impacted soils materials in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Lead-Based Paint Removal and Disposal
ACM Sewer Line Removal and Disposal
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required in accordance with Specification 01 57 19.01 20, complete and in accordance with the Request for Proposal. These costs include, but are not necessarily limited to, MEC equipment and personnel mobilization/demobilization, MEC work plans, MEC reporting, MEC Personnel, MEC safety briefings and awareness training, reduced production rates associated with debris removal, equipment, scanning, additional costs to shield equipment operators, dredge spoils drying, screening and/or broadcasting, equipment and scanning, and anomaly clearance.
Total price for the entire work required for the removal, containment, and safe disposal of ACM sewer line in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Total price for the entire work required for the removal, containment, and safe disposal of hydrocarbon impacted soils materials in accordance with the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Price
Extended Total
Grand TotalDescription
PRICE PROPOSAL SCHEDULE for
WON 1383711 (RM14-1420)
Lima Wharf Repair, NBG Apra Harbor RFP Amendment 0011
0001O BASE BID ITEM O 500 LF $ $
0001P BASE BID ITEM P 500 CY $ $
0001Q BASE BID ITEM Q 1 LS $ $
0001R BASE BID ITEM R 11,988 LF $ $
0002 BID OPTION 1 1 LS $
0003 BID OPTION 2 1 LS $
0004 BID OPTION 3 North End Wharf Structural Repair and Modernization 1 LS $
0005 BID OPTION 4 1 LS $
0006 BID OPTION 5 1 LS $
0007 BID OPTION 6 1 LS $
0001 SUBTOTAL BASE BID $
0002 SUBTOTAL BID OPTION 1 Bilge Oily Water Treatment System (BOWTS) $ 0003 SUBTOTAL BID OPTION 2 Wharf Lighting $ 0004 SUBTOTAL BID OPTION 3 North End Wharf Structural Repair and Modernization $ 0005 SUBTOTAL BID OPTION 4 Existing Electrical Ductbank Demolition $ 0006 SUBTOTAL BID OPTION 5 Corner Fender at Lima-Mike Wharf Intersection $ 0007 SUBTOTAL BID OPTION 6 Steam Infrastructure $
Demolition of Building 2078 Total price to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the removal, containment, and disposal of Building 2078, building and foundation, including associated utilities, piping and equipment as directed in the drawings and specifications; except for work described in Base Bid Items 0001Ma thru 0001Mi.
Procurement and Installation of HP16x88 Tie Back Anchor Piles Total price for the entire work required for the procurement and installation of HP16x88 piles at the tie back anchor as directed in the drawings and specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contract price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211-18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
TOTAL BASE BID + OPTIONS
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the demolition of the existing electrical ductbank in accordance with the drawings and specifications; except for work described in CLINs 0001-0004 and 0006-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
Existing Electrical Ductbank Demolition
SUMMARY:
Corner Fender at Lima-Mike Wharf Intersection Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the corner fender at Lima-Mike wharf intersection in accordance with the drawings and specifications; except for work described in CLINs 0001-0005 and 0007.
Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the installation of the steam infrastructure in accordance with the drawings and specifications; except for work described in CLINs 0001-0006. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
Steam Infrastructure
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the north end wharf structural repair and modernization, including one industrial power mound, in accordance with the drawings and specifications; except for work described in CLINs 0001-0003 and 0005-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the wharf lighting including associated transformers and switchgear in accordance with the drawings and specifications; except for work described in CLINs 0001-0002 and 0004- 0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award.
Wharf Lighting
Demolition of Unforeseen Existing Utilities
Demolition of Unforeseen Concrete or Rubble Total price for the entire work required for the removal, containment, and disposal of unforeseen abandoned utilities as directed in specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contrac price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211- 18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
Bilge Oily Water Treatment System (BOWTS) Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the construction of the BOWTS in accordance with the drawings and specifications; except for work described in CLINs 0001 and 0003-0007. Contracting Officer may exercise this option by written notice within 180 calendar days from date of contract award
Total price for the entire work required for the removal, containment, and disposal of unforeseen abandoned utilities as directed in specifications. The unit price in this Base Bid SubCLIN will be used to adjust the contrac price for any increase or decrease in the estimated quantity for this Base Bid SubCLIN subject to FAR 52.211- 18, Variation in Estimated Quantity, and shall include all necessary labor, material, transportation, supervision, equipment, and other incidental work.
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND MARIANAS
PSC 455, BOX 195
FPO AP 96540-2937
N4019220R1300 Notice 11
26 August 2020
NOTICE 11
REQUESTS FOR INFORMATION AND RESPONSES
SOLICITATION N4019220R1300 FY21 SPECIAL PROJECT RM 14-1420
REPAIR LIMA WHARF, NAVAL BASE GUAM
QUESTION (Q) 143: – Reference RFP Amendment 0003, Price Proposal Schedule, SubCLIN 0001B Base Bid Item B - Stone Columns:
SubCLIN 0001B is indicated in a unit of MT. Please confirm that this unit is metric tons versus tons (2,000 pounds)? The rest of the project documents use imperial units versus metric units.
Answer (A) 143: Confirmed. The quantity for Stone Columns is in Metric Tons.
Q147: Options Award Schedule – Reference SF1442, Price Proposal Schedule (Schedule of Prices):
The note on page 6 of 59 of the RFP states that, “It is anticipated that the Government may exercise one or more option(s) at time of award.”
For the Factor 2 – Technical Approach construction schedule and phasing plan, please advise what date(s) Offerors should use for the award of the option item(s). Should Offerors use the Contract Award Date for the award of the option item(s)?
A147: The Contracting Officer may exercise one or more option(s) by written notice within 180 calendar days from date of contract award. Refer to RFP Amendment 0011. However, for the construction schedule and phasing plan required under Factor 2 – Technical Approach, Offerors should use the Contract Award Date for the award of the option item(s).
Q151: Bollards and Cleats – Reference RFP Part B, Specification Section 05 12 00 Structural Steel, Paragraph 2.2.4 Mooring Fittings:
Please verify that Bollards and Cleats are required to be cast using MIL-C-24707/1 and not ASTM A27 Grade 65-35.
A151: Bollards shall be cast steel meeting the requirements of MIL-C-24707/1 or ASTM A27/A27M, Class 1. Change will be included in a future amendment.
Q152: BOWTS – Reference RFP Part B, Specification Section 40 42 60.20 Bilge and Oily Waste Treatment System:
Specification section 40 42 60.20 references UFC 4-832-01N (2010) Design: Industrial and Oily Waste Control. From the Unified Facilities Criteria website UFC 4-832-01N 2010 is not available. 2004 is, however, it is watermarked “CANCELLED”. Please clarify if the 2010 standard reference is correct and if so please provide that standard.
A152: UFC 4-832-01N (2004) is the correct reference to Specification section 40 42 60.20. The document is available on the whole building design guide website. Change will be included in a future amendment.
Q153: SubCLIN 0001B Revised Quantity and Unit – Reference Amendment 0003, Price Proposal Schedule, SubCLIN 0001B Base Bid Item B Stone Columns:
Amendment 0003 included a revised PRICE PROPOSAL SCHEDULE. For CLIN 0001, SubCLIN 0001B – BASE BID ITEM 0001B Stone Columns, the quantity and unit were revised from 34,270 CY to 44,070 MT. The equivalent unit weight using the original volume measurement of 34,720 CY and the revised weight measurement of 44,070 MT is 104 pounds per cubic foot (pcf). The stone material available on Guam is limestone based and has a loose unit weight of 82 pcf to 85 pcf. From experience, placing and densifying the stone with vibroflotation equipment reduces the loose stone volume by approximately 8%. This will result in an installed unit weight of between 89.1 pcf to 92.4 pcf. When this installed unit weight range is applied to the original SubCLIN 0001B volume of 34,720 CY, the equivalent total weight is between 37,897 MT and 39,301 MT which is substantially less than the revised bid quantity of 44,070 MT.
Based on the unit weight of the stone available on Guam, the revised quantity of 44,070 MT is overstated by over 4,700 MT. Please revise the bid quantity for SubCLIN 0001B to be based on the unit weight of stone available on Guam.
A153: Bid shall be based on the quantities provided.
Q154: Marine Resources Monitoring – Reference Amendment 0006, Section 01 57 19.02 Supplemental Temporary Environmental Controls, Paragraphs 3.1.2 Marine Resources Monitoring and 3.1.3 Marine Resources Monitoring for In-water Construction Activities:
Is marine resources monitoring required for all construction activities or just the pile driving and dredging? Paragraph 3.1.2 states that it will be performed for all construction activities while paragraph
3.1.3 just references pile driving and dredging. Please clarify.
A154: Marine species monitoring is required for all in-water construction activities, including but not limted to, pile driving and dredging.
Q155: Marine Resources Monitoring – Reference Amendment 0006, Section 01 57 19.02 Supplemental Temporary Environmental Controls, Paragraph 3.3 Water Quality Monitoring (WQM) Plan, Item e:
Is continuous water quality monitoring required for all in-water work or just for in-water work that generates turbidity such as pile driving and dredging?
A155: Continuous water quality monitoring is required for all in-water construction activities that have the potential to generate turbidity.
Q156: Small Business Subcontracting Plan:
No Small Business Subcontracting Plan was mentioned or provided within the RFP. Please confirm that a Small Business Subcontracting Plan is not required.
A156: Other than small business offerors shall provide an acceptable Small Business Subcontracting Plan prior to contract award. See FAR clause 52.219-9 (Dev) Small Business Subcontracting Plan incorporated by reference into the solicitation.
Q159: Wall Finishes – Reference RFP Part C, Drawing Nos. A-201 and A-202 (Substation - Building Elevations):
Reference Sheets A-201 and A-202. Substation Exterior Elevations call for PT1, PT2, and PT3 for wall finishes. Elevations on Sheet A-301 and A-501 call for “SKIM COATED CONC WALL, PAINTED.”
Please clarify the intent.
A159: Cast-in place concrete walls must be provided with cement skim coat prior to painting. Paint colors (PT1, PT2, and PT3) must be as indicated. Refer to color paint schedule on A-201.
Q161: Quantities of Vessel Ingress & Egress – Reference RFP Part B, Specification Section 35 20 23 Dredging, Paragraph 3.14.2 Navigation Channel, Item b:
Please fill in the "X" quantities below:
"U.S. Navy use of the channel is expected to occur regularly on average X vessel ingress and X vessel egress per week. A vessel ingress/egress requires approximately 1 hour each way. During this vessel ingress/egress, completely remove the dredge and all related equipment to such an extent to afford passage. A schedule of vessel transits can be obtained from the Contracting Officer."
A161: Refer to Specification Section 01 14 00 Paragraph 1.3d. "Up to 20 vessels enter and exit inner Apra Harbor thru the PSB each day. These consist of 5-14 larger vessels (such as T-AKE) and 6-12 smaller vessels (tug size). A 100 yard standoff distance is required for escorted vessels traveling through the harbor channel. Perform work in a manner that maintains 100 yard standoff distances from vessels entering inner Apra Harbor at all times to minimize disruptions to work." Change to Specification Section 35 20 23 will be included in a future amendment.
Q162: Dredging – Reference RFP Part B, Specification Section 01 57 19.01 20 Supplemental Temporary Environmental Controls Lima Mike November Wharves Apra Harbor, Naval Base Guam, Water Areas Explosives Safety Submission (ESS), Paragraph 3.5.2 MEC Support to In-Water Operations:
Can dredging be performed from a crane directly on the dock and the material placed in a 3" grizzly that would also be located directly on the dock?
The trans-load pad would be outfitted with the proper environmental controls for turbidity as well as the 3" grid/grizzly for MEC screening and could even be built to have walls for additional shielding from potential MEC discharges.
A162: Yes, provided the contractor adheres to all contract requirements including, but not limited to: it is the Contractor's responsibility to determine safe working loads during construction, Contractor to evaluate the capacity of the wharf to select appropriate means and methods for construction and submit a report documenting the capacities and the ability of the structure to support the proposed construction equipment, MEC exclusion zones, turbidity limits, etc.
Q164: Diving Certification Requirements – Reference RFP Part B, Specification Section 01 45 00.00 20 Quality Control, Paragraph 1.5.11 Underwater QC Team:
Underwater diving QC team requires a certified diving company to be a member of the ADCI. Searching the ADCI member directory there are no current members in Guam. Please remove this requirement and allow the Contractor to use the local dive companies with all of the other requirements of this section.
A164: The second sentence of Section 01 45 00.00 20, paragraph 1.5.11 will be revised to read:
"The UWQC Team divers must be employed by a firm having current status of Member of the Association of Diving Contractor's International (ADCI), having hold a current commercial diver's license, with a minimum of five (5) years of experience with underwater inspection of structures."
This change will be included in an upcoming amendment.
Q165: Water Security Fence:
(a) What is the plan for the opening and closing of the in-water security fencing?
(b) What is the time frame from requesting it opened to the time that it is opened?
(c) Does opening and closing the fencing cost the Contractor?
(d) Where is the fence connected to the existing wharf?
(e) Is there any upgrade or modification that needs to happen?
A165: (a) Refer to Specification Section 01 14 00, Paragraphs 1.3.d and 1.5.5.
(b) Request in writing a minimum of 15 calendar days prior to the desired date of interruption.
(c) Provided the requests to open the port security barrier are kept to a minimum, there is no cost to the Contractor.
(d) The Port Security Barrier is attached near the northeast corner of Lima Wharf. Refer to drawing
SD101.
(e) The Port Security Barrier must be reattached to a new attachment point. Refer to Detail S-530/A1 and S-530/C1.
Q166: Mechanical Piping Schedule – Reference RFP Part B, Specification Section 40 05 13 Pipelines, Liquid Process Piping:
Specification Section 40 05 13 – Pipelines, Liquid Process Piping contains numerous types of piping systems including ductile iron, stainless steel, copper, PVC, CPVC, HDPE and Double Containment.
Please provide a pipe schedule that lists what piping system is associated with each type of fluid carried in piping such as for Drain, Sludge, BOW inside the BOWT facility, Air, Slop Oil, Treated Effluent, etc.
A166: A pipe schedule will be provided in an upcoming amendment.
Q167: Horizontal Cold Joint in Bulkhead – Reference RFP Part C, Drawing No. S510 (Bulkhead Cap Details - 1), Detail A4:
Due to the requirement of a different concrete mix design for the bulkhead concrete (Non Segregating Admixture), placing of concrete in the water and mass concrete requirements is it acceptable to place the bulkhead with two horizontal construction joints?
A167: In accordance with Specification 03 31 29, Paragraph 1.8.1.3, Contractor shall submit a plan indicating the type and location of each construction joint for government approval. Final joint locations are subject to Government approval.
Q168: Existing Storm Bollards – Reference RFP Part B, Specification Section 02 41 00 Demolition and Deconstruction:
Please confirm that the existing storm bollards cannot be salvaged for re-use on the new wharf structure.
A168: Existing storm bollards cannot be salvaged for re-use on the new wharf structure.
Q169: Dredging, Surveying – Reference RFP Part B, Specification Section 35 20 23 Dredging, Paragraph 3.7.1 Survey Firm:
All surveys must be performed by a Survey Firm, independent of the Contractor. The firm must have a minimum of 3 years of qualifying experience in hydrographic surveying of navigable channels and a current California Land Surveyor's license. Provide a Hydrographic Survey report with Drawings.
Is a California PLS actually required? Will PLS from other states suffice or is a PLS registered in Guam required?
A169: Deferred
Q170: Government of Guam Use Tax on Imported Equipment:
The Government of Guam requires payment of a 4% Guam Use Tax on the value of all equipment shipped to Guam based on the declared value of the equipment plus shipping costs. Please advise if the Lima Wharf project is exempt from the Government of Guam Use Tax.
A170: Deferred
Q171: BOWTS Pump Motors – Reference RFP Amendment 0003 (Amendment 22 JUL 2020), Specification Section 40 42 60.20 Bilge and Oily Waste Treatment System, Paragraph 2.8.1 Pump Motors:
Specification 40 42 60.20, Paragraph 2.8.1 states that pump motors are to be suitable for Class 1, Division 1 and fully submergible in water. Please confirm both are required. For the previous wharf projects, this requirement was removed during design as it was unnecessary and costly. Rather than installing pumps on 4" H.K. Pads, the pumps were installed on 30" elevated piers, so as to not need to be submerged in water, and could be Totally Enclosed Fan-Cooled. Our Positive Displacement Diaphram Pump Manufacturer replied to our inquiry: "A submersible motor would not be recommended due to its method of cooling requiring it to be submerged and our pumps inability to operate without damage while being submerged. I would recommend a TEFC motor as we have provided in the past.” I got a similar response from our mixer and fresh water pump vendors (i.e. they can’t provide). Further, Sheet M-301, Section Elevation B3, shows the BOW Pumps mounted on a 30" elevated pier.
Why would you want to operate a plant submerged in water? I do not understand this.
A171: Deferred
Q172: DAF Bottom Sludge Auger – Reference RFP Part B, Specification Section 40 42 60.20 Bilge and Oily Waste Treatment System, Paragraph 1.6.6 Dissolved Air Flotation (DAF) System:
Specification 40 42 60.20, Paragraph 1.6.6 states that a bottom sludge auger shall be provided to convey sludge. This is not required for our DAF design and was removed during design for the past wharf projects. It is not shown on the flow diagram, bill of materials, one-line diagram or equipment schedule.
A172: Deferred
Q173: LET Chain-and-Flight Sludge Collection + Oil Skimming – Reference RFP Part B, Specification Section 40 42 60.20 Bilge and Oily Waste Treatment System, Paragraph 1.6.2 Load Equalization Tank (LET) System:
Specification 40 42 60.20, Paragraph 1.6.2 states that an electric-motor driven chain-and-flight sludge collection and oil skimming mechanism is required. Per UFC 3-240-01, Equalization (Paragraph 16-8.1) is to be used to equalize surges in peak flows as well as variations in oil concentrations. This is critical in order for downstream processes (primary and secondary treatment) to work effectively.
Per Paragraph 16-8.2, Primary Treatment is required, and to be followed be secondary treatment (DAF) and finally tertiary treatment.. They provide two options to accomplish the primary treatment: Gravity Separation or Load Equalization Tank.
Paragraph 16-8.8 Emulsified Oil Treatment states that simple gravity settling is not effective for emulsified oils and avoidance of excessive turbulence.
Based upon Specification 40 42 60.20, the treatment processes as written include:
- No Equalization
- Primary Treatment: Load Equalization Tank operated in batch process
- Primary…