This solicitation seeks construction services for repair and modernization of Lima Wharf and appurtenances at Naval Base Guam. The work includes replacement of the steel sheet pile bulkhead, replacement of the mooring system, restoration of heavy weather mooring systems, fender system restoration, replacement of the existing electrical substation and wharf utilities, construction of wharf lighting and pavement. A bilge oily water treatment system will also be constructed to process waste from vessels berthing at Lima Wharf. The estimated cost of construction is between $100 million and $250 million. Offerors must submit technical and past performance proposals as well as price proposals for evaluation. A bid bond of $3 million or 20% of the bid price is required. The pre-proposal conference and site visit details will be provided. Foreign nationals must complete a visitor request form. The Navy is the contracting agency and point of contact is Janeen Bais.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY21 SPECIAL PROJECT RM 14-1420, Repair Lima Wharf, Naval Base Guam

See Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Aug-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4019220R1300

X 9B. DATED (SEE ITEM 11)

16-Jun-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Aug-2020

CODE

COMMANDING OFFICER - NAVFAC MARIANAS

MAR MCON

PSC 455, BOX 195

FPO AP 96540-2937

N40192 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4019220R1300

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0010

A. In accordance with FAR 52.252-3 Alterations in Solicitation (APR 1984), portions of this solicitation are altered as follows:

Incorporate the following revision to NAVFAC Specifications WON 1383711:

Add appendices to the Pre-Draft Water Areas Explosives Safety Submission Repair of Lima Mike November Wharves, Apra Harbor (Pre-Draft Water Areas ESS). Appendices are provided herein as Enclosure (1).

B. Notice 10 is provided in response to requests for information and is provided herein as Enclosure (2). Notice 10 is provided for INFORMATION ONLY. The solicitation remains unchanged unless it is amended in writing.

C. The date for receipt of proposals is extended from August 31, 2020 to September 9, 2020 at 4:30pm local time.

D. Offerors shall acknowledge this amendment in Block 19 of the Standard Form 1442 with their proposals.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 31-Aug-2020 04:30 PM to 09-Sep-2020 04:30 PM.

(End of Summary of Changes)

Water Areas Explosives Safety Submission Repair of Lima Mike November Wharves, Apra Harbor Naval Base Guam, Joint Region Marianas CTO N6274220F0108 Appendix A

A-1

APPENDIX A. 1

Signature Page 2

This appendix contains the Signature Page for this Explosives Safety Submission. 3

This space intentionally left blank 4

A-2

This page intentionally left blank 2

A-3

Table A-1. Signature Page 1

NOSSAINST 8020.15D 2

NAVFAC Project BRAC PMO Project

Project name: Project name:

Explosives Safety Officer or

UXO Contractor Safety Officer*

Explosives Safety Officer or

UXO Contractor Safety Officer**

Signature Signature

Printed name Date Printed name Date

PWO BRAC Environmental Coordinator

Navy Project Manager Navy Project Manager

* This must be signed by the cognizant ESO when the munitions response actions are being 3 executed on active Navy facilities. 4

** This may be signed by either the Navy Regional ESO or a technically qualified explosives safety 5 official designated by the BRAC PMO. 6

A-4

This page is intentionally left blank. 2

CTO N6274220F0108 Appendix B

B-1

APPENDIX B. 1

Supporting Explosive Safety Data 2

This appendix contains the supporting data for this Explosives Safety Submission. 3

This space intentionally left blank 4

CTO N6274220F0108 Appendix B

B-2

Munition Information and Fragmentation Characteristics

Theoretical Calculated Fragment Distances

Minimum Thickness to Prevent Perforation (in)

Overpressure Distances

Sandbag and Water Mitigation Options

Fragmentation Data Review Form

Category: Air-Launched HE Rounds

Munition: 1000 lb AN-M65A1 Bomb (Composition B filled)

Case Material: Steel, Mild

Secondary Database Category: Bomb

Munition Case Classification: Robust

DODIC:

Individual Last Updated Record: SDH

Explosive Type: Composition B

Explosive Weight (lb): 595

Diameter (in): 18.8000

Maximum Fragment Weight (Intentional) (lb):

0.7020

Critical Fragment Velocity (fps): 9385

HFD [Hazardous Fragment Distance: distance to no more than 1 hazardous fragment per 600 square feet] (ft):

MFD-V [Maximum Fragment Distance, Vertical] (ft): 2673

MFD-H [Maximum Fragment Distance, Horizontal] (ft): 3355

1.2 psi, K40 Distance (ft): 353

3.5 psi, K18 Distance (ft): 159

0.0655 psi, K328 Distance (ft): 2899

4000 psi Concrete (Prevent Spall): 46.31

Mild Steel: 6.73

Hard Steel: 5.52

Aluminum: 12.93

LEXAN: 17.03

Plexi-glass: 17.41

Bullet Resist Glass: 16.43

Kinetic Energy 10⁶ (lb-ft²/s²): 30.9134

Required Wall & Roof Thickness (in) Not Permitted

Expected Max. Throw Distance (ft): Not Permitted

Minimum Separation Distance (ft): Not Permitted

Water Containment System: Not Permitted

Minimum Separation Distance (ft): Not Permitted

Date Record Created: 10/5/2009

Last Date Record Updated: 9/14/2011

Date Record Retired:

Database Revision Date 6/5/2020

Intentional Unintentional

Design Fragment Weight (95%) (Unintentional) (lb):

0.0627

16.66

5.27

2.59

2.12

9.45

6.89

7.97

Distribution Statement D. Distribution authorized to the Department of Defense and U.S. DoD contractors only for Administrative- Operational Use (7 January 2020). Other requests shall be referred to the Department of Defense Explosives Safety Board, 4800 Mark

Center Drive, Suite 16E12, Alexandria, VA 22350.

Fragmentation Method: Naturally Fragmenting

Record Created By: SDH

2.3 psi; K24 Distance (ft): 212

TNT Equivalent (Pressure): 1.16

TNT Equivalent Weight - Pressure (lbs): 690.200

Item Notes

TNT Equivalent (Impulse): 1.14

TNT Equivalent Weight - Impulse (lbs): 678.300

Cylindrical Case Weight (lb): 314.38573

Required Wall & Roof Thickness (in) Not Permitted

Expected Max. Throw Distance (ft): Not Permitted

Minimum Separation Distance (ft): Not Permitted

Single Sandbag Mitigation

Double Sandbag Mitigation

"NOTE: Values shown within this section only address overpressure hazards and do not account for applicable distance values for fragments and debris as required per DoD 6055.09-M."

Water Mitigation

Note: Use Sandbag and Water Mitigation in accordance with all applicable documents and guidance. If a donor charge larger than 32 grams is utilized, the above mitigation options are no longer applicable. Subject matter experts may be contacted to develop site specific mitigation options.

B-3

This page is intentionally left blank.

B-4

Theoretical Calculated Fragment Distances

Minimum Thickness to Prevent Perforation (in)

Overpressure Distances

Sandbag and Water Mitigation Options

Fragmentation Data Review Form

Category: Surface-Launched HE Rounds

Munition: 5 in Mk 41 Mod 0

Case Material: Steel, Mild

Secondary Database Category: Projectile

Munition Case Classification: Robust

DODIC: D320

Individual Last Updated Record: SDH

Explosive Type: Explosive D

Explosive Weight (lb): 7.38

Diameter (in): 4.8890

Maximum Fragment Weight (Intentional) (lb):

0.6726

Critical Fragment Velocity (fps): 2538

HFD [Hazardous Fragment Distance: distance to no more than 1 hazardous fragment per 600 square feet] (ft):

MFD-V [Maximum Fragment Distance, Vertical] (ft): 1748

MFD-H [Maximum Fragment Distance, Horizontal] (ft): 2377

1.2 psi, K40 Distance (ft): 74

3.5 psi, K18 Distance (ft): 33

0.0655 psi, K328 Distance (ft): 605

4000 psi Concrete (Prevent Spall): 9.17

Mild Steel: 1.77

Hard Steel: 1.45

Aluminum: 3.43

LEXAN: 8.58

Plexi-glass: 7.05

Bullet Resist Glass: 6.32

Kinetic Energy 10⁶ (lb-ft²/s²): 2.4521

Required Wall & Roof Thickness (in) 36

Expected Max. Throw Distance (ft): 220

Minimum Separation Distance (ft): 220

Water Containment System: 1100 gal tank

Minimum Separation Distance (ft): 275

Date Record Created: 9/21/2004

Last Date Record Updated: 9/14/2011

Date Record Retired:

Database Revision Date 6/5/2020

Intentional Unintentional

Design Fragment Weight (95%) (Unintentional) (lb):

0.1367

4.80

1.86

0.92

0.75

5.73

3.49

4.13

Distribution Statement D. Distribution authorized to the Department of Defense and U.S. DoD contractors only for Administrative- Operational Use (7 January 2020). Other requests shall be referred to the Department of Defense Explosives Safety Board, 4800 Mark

Center Drive, Suite 16E12, Alexandria, VA 22350.

Fragmentation Method: Naturally Fragmenting

Record Created By: MMC

2.3 psi; K24 Distance (ft): 44

TNT Equivalent (Pressure): 0.85

TNT Equivalent Weight - Pressure (lbs): 6.273

Item Notes

TNT Equivalent (Impulse): 0.81

TNT Equivalent Weight - Impulse (lbs): 5.978

Cylindrical Case Weight (lb): 51.30473

Required Wall & Roof Thickness (in) Not Permitted

Expected Max. Throw Distance (ft): Not Permitted

Minimum Separation Distance (ft): Not Permitted

Single Sandbag Mitigation

Double Sandbag Mitigation

"NOTE: Values shown within this section only address overpressure hazards and do not account for applicable distance values for fragments and debris as required per DoD 6055.09-M."

Water Mitigation

Note: Use Sandbag and Water Mitigation in accordance with all applicable documents and guidance. If a donor charge larger than 32 grams is utilized, the above mitigation options are no longer applicable. Subject matter experts may be contacted to develop site

B-5

B-6

Theoretical Calculated Fragment Distances

Minimum Thickness to Prevent Perforation (in)

Overpressure Distances

Sandbag and Water Mitigation Options

Fragmentation Data Review Form

Category: Surface-Launched HE Rounds

Munition: 3 in / 50 AP Mk29

Case Material: Steel, Mild

Secondary Database Category: Projectile

Munition Case Classification: Extremely Heavy Cased

DODIC: C143

Individual Last Updated Record: SDH

Explosive Type: Explosive D

Explosive Weight (lb): 0.14

Diameter (in): 2.9800

Maximum Fragment Weight (Intentional) (lb):

0.3707

Critical Fragment Velocity (fps): 1969

HFD [Hazardous Fragment Distance: distance to no more than 1 hazardous fragment per 600 square feet] (ft):

MFD-V [Maximum Fragment Distance, Vertical] (ft): 1087

MFD-H [Maximum Fragment Distance, Horizontal] (ft): 1523

1.2 psi, K40 Distance (ft): 20

3.5 psi, K18 Distance (ft): 9

0.0655 psi, K328 Distance (ft): 161

4000 psi Concrete (Prevent Spall): 4.55

Mild Steel: 0.75

Hard Steel: 0.61

Aluminum: 1.48

LEXAN: 5.37

Plexi-glass: 3.80

Bullet Resist Glass: 3.25

Kinetic Energy 10⁶ (lb-ft²/s²): 0.4090

Required Wall & Roof Thickness (in) 20

Expected Max. Throw Distance (ft): 125

Minimum Separation Distance (ft): 125

Water Containment System: 5 gal carboys/ inflatable pool

Minimum Separation Distance (ft): 264/200

Date Record Created: 9/21/2004

Last Date Record Updated: 5/3/2018

Date Record Retired:

Database Revision Date 6/5/2020

Intentional Unintentional

Design Fragment Weight (95%) (Unintentional) (lb):

0.2321

3.57

1.03

0.51

0.42

4.25

2.31

2.79

Distribution Statement D. Distribution authorized to the Department of Defense and U.S. DoD contractors only for Administrative- Operational Use (7 January 2020). Other requests shall be referred to the Department of Defense Explosives Safety Board, 4800 Mark

Center Drive, Suite 16E12, Alexandria, VA 22350.

Fragmentation Method: Naturally Fragmenting

Record Created By: MMC

2.3 psi; K24 Distance (ft): 12

TNT Equivalent (Pressure): 0.85

TNT Equivalent Weight - Pressure (lbs): 0.119

Item Notes

TNT Equivalent (Impulse): 0.81

TNT Equivalent Weight - Impulse (lbs): 0.113

Cylindrical Case Weight (lb): 4.54141

Required Wall & Roof Thickness (in) 48

Expected Max. Throw Distance (ft): 10

Minimum Separation Distance (ft): 12.5

Single Sandbag Mitigation

Double Sandbag Mitigation

"NOTE: Values shown within this section only address overpressure hazards and do not account for applicable distance values for fragments and debris as required per DoD 6055.09-M."

Water Mitigation

Note: Use Sandbag and Water Mitigation in accordance with all applicable documents and guidance. If a donor charge larger than 32 grams is utilized, the above mitigation options are no longer applicable. Subject matter experts may be contacted to develop site

B-7

B-8

CTO N6274220F0108 Appendix C

C-1

APPENDIX C. 1

ESQD Maps 2

This appendix contains the following ESQD Maps for this Explosives Safety Submission. 3

• Figure C-1: Project Area ESQD Arcs 4

• Figure C-2: Primary 1 MGFD HFD Arcs for Dredging Operations 5

• Figure C-3: Contingency MGFD HFD Arcs for Dredging Operations 6

• Figure C-4: Primary 2 MGFD HFD Arcs for USSA Operations. 7

This space intentionally left blank 8

CTO N6274220F0108 Appendix C

C-2

USSA #2

USSA #1

Figure C-1 Project Area ESQD Arcs

Data is projected to the UTM Coordinate System:

WGS 1984 UTM Zone 55N

Revision Date:Submitted By:

Checked By: Date Drawn: 7/30/2020

1 inch = 100 metersCLHDrawn By: Scale:

Rev No.

Path: S:\Guam\Apra Harbor\MXD\ESS\Fig C-1 Project Area ESQD Arcs and EZ Access Points.mxd

0 330 660165 ft

0 100 20050 m

ÈN

Water Areas Explosives Safety Submission Repairs of Lima Mike November Wharves Apra Harbor

Naval Base Guam, Joint Region Marianas

Legend Upland Staging and Screening Area

(USSA)

Lima Wharf Laydown Area Lima Wharf Dredge Area Mike Wharf Laydown Area Mike Wharf Dredge Area November Wharf Laydown Area November Wharf Dredge Area

ESQD Arcs Primary 1 HFD for 5 in Mk 41 Mod 0 - 359ft Primary 2 HFD for 3 in/50 AP Mk 29 - 116ft Contingency HFD for 1000 lb AN-M65A1 Bomb (Composition B filled) - 810 ft

MS

C-3

C-4

USSA #2

USSA #1

Figure C-2

Primary 1 MGFD HFD Arcs for Dredging

Operations

Data is projected to the UTM Coordinate System:

WGS 1984 UTM Zone 55N

Revision Date:Submitted By:

Checked By: Date Drawn: 7/30/2020

1 inch = 70 metersCLHDrawn By: Scale:

Rev No.

Path: S:\Guam\Apra Harbor\MXD\ESS\Fig C-2 Primary 1 MGFD HFD Arcs for Dredging Operations.mxd

0 230 460115 ft

0 70 14035 m

ÈN

Water Areas Explosives Safety Submission Repairs of Lima Mike November Wharves Apra Harbor

Naval Base Guam, Joint Region Marianas

Legend Entry Control Points

") Waterway Spotter Locations Upland Staging and Screening Area

(USSA)

Lima Wharf Laydown Area Lima Wharf Dredge Area Mike Wharf Laydown Area Mike Wharf Dredge Area November Wharf Laydown Area November Wharf Dredge Area

ESQD Arcs Primary 1 HFD for 5 in Mk 41 Mod 0 - 359ft

C-5

C-6

USSA #2

USSA #1

Figure C-3 Contingency MGFD

HFD Arcs for Dredging Operations

Data is projected to the UTM Coordinate System:

WGS 1984 UTM Zone 55N

Revision Date:Submitted By:

Checked By: Date Drawn: 7/30/2020

1 inch = 100 metersCLHDrawn By: Scale:

Rev No.

Path: S:\Guam\Apra Harbor\MXD\ESS\Fig C-3 Contingency MGFD HFD Arcs for Dredging Operations.mxd

0 330 660165 ft

0 100 20050 m

ÈN

Water Areas Explosives Safety Submission Repairs of Lima Mike November Wharves Apra Harbor

Naval Base Guam, Joint Region Marianas

Legend Entry Control Points

") Waterway Spotter Locations Upland Staging and Screening Area

(USSA)

Lima Wharf Laydown Area Lima Wharf Dredge Area Mike Wharf Laydown Area Mike Wharf Dredge Area November Wharf Laydown Area November Wharf Dredge Area

ESQD Arcs Contingency HFD for 1000 lb AN-M65A1 Bomb (Composition B filled) - 810 ft

C-7

C-8

USSA #2

USSA #1 Figure C-4 Primary 2 MGFD

HFD Arcs for USSA Operations

Data is projected to the UTM Coordinate System:

WGS 1984 UTM Zone 55N

Revision Date:Submitted By:

Checked By: Date Drawn: 7/30/2020

1 inch = 50 metersCLHDrawn By: Scale:

Rev No.

Path: S:\Guam\Apra Harbor\MXD\ESS\Fig C-4 Primary 2 MGFD HFD Arcs for USSA Operations.mxd

0 160 32080 ft

0 50 10025 m

ÈN

Water Areas Explosives Safety Submission Repairs of Lima Mike November Wharves Apra Harbor

Naval Base Guam, Joint Region Marianas

Legend Entry Control Points

") Waterway Spotter Locations Upland Staging and Screening Area

(USSA)

Lima Wharf Laydown Area Lima Wharf Dredge Area Mike Wharf Laydown Area Mike Wharf Dredge Area November Wharf Laydown Area November Wharf Dredge Area

ESQD Arcs Primary 2 HFD for 3 in/50 AP Mk 29 - 116ft

C-9

C-10

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING COMMAND MARIANAS

PSC 455, BOX 195

FPO AP 96540-2937

N4019220R1300 Notice 10

21 August 2020

NOTICE 10

REQUESTS FOR INFORMATION AND RESPONSES

SOLICITATION N4019220R1300 FY21 SPECIAL PROJECT RM 14-1420

REPAIR LIMA WHARF, NAVAL BASE GUAM

QUESTION (Q) 136: Air Barrier – Reference RFP Part B, Specification Section 07 05 23 Pressure Testing an Air Barrier System for Air Tightness and Section 07 05 23 Building Air Barrier System:

Please verify that air barrier submittal review, commissioning, air blower testing is not required on the transformer building. An air barrier is not shown.

Answer (A) 136: Air barrier testing is required in the air conditioned spaces (DDC/AMI room, Battery room, Elect/Equipment room and Elect room at BOWTS). Air barrier testing of the Switchgear Room is not required.

Q137: Angled Connection of PVC Piping – Reference RFP Part C, Drawing No. S-512 (Bulkhead Cap Details - 3), Detail A4:

Please explain the angled connection of the 6" PVC piping around the tie rod as it enters the existing bulkhead. What is this material, and can the PVC continue at the same elevation throughout the overall distance of the rod from the concrete dead man to the king pile?

A137: The PVC piping must be constructed as detailed/specified. The angled connection is a flexible PVC joint as indicated in Drawing S-507, Detail B3. The tie rod must be centered within the PVC from the bulkhead cap through the existing bulkhead wall. From the existing bulkhead wall to the tie back anchor, the tie shall be located at the bottom of the PVC sleeve as indicated to allow for settlement.

Q138: Finishes – Reference RFP Part C, Drawing No. A-601 (Room Finish Schedule, Door & Window Schedule and Types):

What are the finishes for the BOWTS building? Do the CMU walls need paint? Is there an oil resistant coating on the floor area? Please provide information.

A138: (1) BOWTS:

• BOWTS walls must be tooled joint and painted (PT1), refer to A-201. Exposed cast in place concrete wall must be painted (PT1).

• Concrete floor slab must be coated with a slip resistant epoxy coating.

(2) BOWTS Electrical Building:

• CMU wall shall be cement plastered and paint finish (exterior and interior surfaces), refer to A-402.

• Floor Finish - Electrical Room 109 floor finish shall be “F1”, refer to sheet A-601 “Room Finish Schedule.

• Door Type – Door 109 at Electrical Room shall be Type B aluminum door and frame, refer to sheet A- 601 Door Schedule.

Q142: Bollard/Mooring Bolt Pull Testing – Reference RFP Part B, Specification Section 05 12 00 Structural Steel, Paragraph 3.8.4.1 Anchor Bolts:

Paragraph 3.8.4.1 states, “All anchor bolts shall be load tested to 130 kips for 300 ton bollards and 44 kips for 100 ton bollards in tension…”

Do the mooring cleats on the North Wharf also need anchor bolt testing? If yes, please provide the load testing criteria.

A142: Yes, provide anchor bolt testing with 10 kips of tension loading for mooring cleats. Change will be included in a future amendment.

Q144: Cathodic Protection – Reference RFP Part C, Drawing No. CP301 (Cathodic Protection Layout), Detail B4:

Detail B4 on drawing CP301 states the following, “Provide a minimum 6” long weld at each sheet pile interlock prior to concrete cap installation to provide electrical continuity.”

Does this weld just need to take place where the sheet piles interlock? Or is a continuity weld also needed where the sheet piles interlock with the king piles?

Based on past projects a 6” weld for continuity at each interlock seems excessive. This continuity weld will take place below water and will have to be performed by divers so any additional welding can have significant cost impacts.

A144: Provide weld at each interlock (sheet pile/ sheet pile and sheet pile/king pile) to ensure electrical continuity. The weld is not required to be performed underwater.

Q145: Waterstops – Reference RFP Part B, Specification Section 03 31 29 Marine Concrete with Service Life Modeling and Section 03 31 30 Marine Concrete:

Both the Marine Concrete with Service Life Modeling and the Marine Concrete specification sections mention waterstops. Please confirm if waterstops are required for the new concrete bulkhead and anchor wall.

A145: Waterstops are required for the substation building, BOWTS structures, manholes, vaults, etc.

Waterstops are not required at the bulkhead wall cap or anchor pile cap.

Q146: Mudline Elevation – Reference RFP Part C, Drawing Nos. SD301 (Typical Demolition Section -

1) and CN301 (Dredging Sections):

Drawing SD301 shows a lower mudline elevation compared to CN301. Please confirm which mudline elevation is correct.

A146: Refer to CN301 for existing mudline elevation.

Q148: Crane Rail Fastening System – Reference RFP Part C, Drawing No. S-533 (Miscellaneous Details), Detail C1 - Crane Rail Foundation:

Please provide the following clarifications:

(a) There is no grade for the Steel Base Plates or embedded Anchor Bolts for the Crane Rail System specified. Please confirm if ASTM A36 would be acceptable for the plate and ASTM A307 for the Anchor Bolt. Does this material need to be HDG?

(b) What is the spacing of the 3/4" Bearing Plates? The Detail shows the Anchor Bolts spaced every 6', is that accurate? Industry Standard is 2' o/c.

(c) What is the purpose of the 1/4" and 1/8" shims on top of the bearing plates? Since this is a new installation, the contractor would set the 3/4" bearing plate at the elevation required, prior to grouting.

Would this be acceptable?

A148: (a) See response to Question 134.

(b) Bearing plate must be provided at each anchor bolt.

(c) Provide shims as required to maintian the top of rail flush with top of AC pavement.

Q149: 110# Crane Rail – Reference RFP Part B, Specification Section 01 57 19.02 (formerly 01 57

19.01 20) Supplemental Temporary Environmental Controls, Paragraph 3.6.1 Crane Rails:

SECTION 01 57 19.02 (formerly 01 57 19.01 20, refer to RFP Amendment 0006), Page 12, PARAGRAPH 3.6.1 CRANE RAIL States "Sections of rail that have incurred greater than 20% section loss due to corrossion must be replaced in-kind to match existing profile and material where possible."

The 110lb/yd Rail has not been made since well before 1977 (Reference ArcelorMITTAL Steelton, previously Bethlehem Steel). There is no exact match profile that is currently produced. ArcelorMITTAL produces the 115lb/yd RE Rail which appears to be the closest match.

(a) Is it the intention of NAVFAC to operate on this rail after it is reinstalled? If so, what are the installation tolerances for the rail profiles?

(b) Would NAVFAC please indicate which profile is an appropriate replacement to the 110 lb/yd Rail, since this profile is no longer produced, as Section 3.3.2.1 (SECTION 02 41 00 Page 10) indicates that the contractor should assume 200LF of new rail in the base bid?

A149: (a) The crane rail will not be operational after re-installation.

(b) See response to Question 134.

Q150: Coating to Sheet Pile Interlock Surfaces – Reference RFP Part B, Specification Section 09 97

13.26 Coating of Steel Waterfront Structures, Zero VOC, (SZC) Splash Zone Coating:

Please clarify if sheet pile interlock surfaces will be coated. Detail B5/S-501 states to "exclude coating to sheet pile interlock surfaces” while specification 09 97 13.26 paragraph 3.2 implies to coat all surfaces including the joints.

A150: As noted in Detail B5/S-501, provide coating on waterside face of king piles and sheet piles.

Exclude coating at interlock surfaces unless noted otherwise.

Q151: Bollards and Cleats – Reference RFP Part B, Specification Section 05 12 00 Structural Steel, Paragraph 2.2.4 Mooring Fittings:

Please verify that Bollards and Cleats are required to be cast using MIL-C-24707/1 and not ASTM A27 Grade 65-35.

A151: Deferred

Q152: BOWTS – Reference RFP Part B, Specification Section 40 42 60.20 Bilge and Oily Waste Treatment System:

Specification section 40 42 60.20 references UFC 4-832-01N (2010) Design: Industrial and Oily Waste Control. From the Unified Facilities Criteria website UFC 4-832-01N 2010 is not available. 2004 is, however, it is watermarked “CANCELLED”. Please clarify if the 2010 standard reference is correct and if so please provide that standard.

A152: Deferred

Q153: SubCLIN 0001B Revised Quantity and Unit – Reference Amendment 0003, Price Proposal Schedule, SubCLIN 0001B Base Bid Item B Stone Columns:

Amendment 0003 included a revised PRICE PROPOSAL SCHEDULE. For CLIN 0001, SubCLIN 0001B – BASE BID ITEM 0001B Stone Columns, the quantity and unit were revised from 34,270 CY to 44,070 MT. The equivalent unit weight using the original volume measurement of 34,720 CY and the revised weight measurement of 44,070 MT is 104 pounds per cubic foot (pcf). The stone material available on Guam is limestone based and has a loose unit weight of 82 pcf to 85 pcf. From experience, placing and densifying the stone with vibroflotation equipment reduces the loose stone volume by approximately 8%. This will result in an installed unit weight of between 89.1 pcf to 92.4 pcf. When this installed unit weight range is applied to the original SubCLIN 0001B volume of 34,720 CY, the equivalent total weight is between 37,897 MT and 39,301 MT which is substantially less than the revised bid quantity of 44,070 MT.

Based on the unit weight of the stone available on Guam, the revised quantity of 44,070 MT is overstated by over 4,700 MT. Please revise the bid quantity for SubCLIN 0001B to be based on the unit weight of stone available on Guam.

A153: Deferred

Q154: Marine Resources Monitoring – Reference Amendment 0006, Section 01 57 19.02 Supplemental Temporary Environmental Controls, Paragraphs 3.1.2 Marine Resources Monitoring and 3.1.3 Marine Resources Monitoring for In-water Construction Activities:

Is marine resources monitoring required for all construction activities or just the pile driving and dredging? Paragraph 3.1.2 states that it will be performed for all construction activities while paragraph

3.1.3 just references pile driving and dredging. Please clarify.

A154: Deferred

Q155: Marine Resources Monitoring – Reference Amendment 0006, Section 01 57 19.02 Supplemental Temporary Environmental Controls, Paragraph 3.3 Water Quality Monitoring (WQM) Plan, Item e:

Is continuous water quality monitoring required for all in-water work or just for in-water work that generates turbidity such as pile driving and dredging?

A155: Deferred

Q156: Small Business Subcontracting Plan:

No Small Business Subcontracting Plan was mentioned or provided within the RFP. Please confirm that a Small Business Subcontracting Plan is not required.

A156: Deferred

Q157: MEC/MPPEH – Reference Amendment 0005, Pre-Draft Water Area ESS, Paragraph 6.1.1 MEC Support Activities of Water Construction Areas:

Comment: The requirement to pre-screen the MEC/MPPEH with a 3” screen for all recovered dredge material when it first reaches the surface and is placed in/on the dredge scow/barge may not be possible for the following reasons:

(1) The barge and dredging equipment to be used for this purpose will be of STEEL construction. To identify MEC/MPPEH, UXO personnel must use detection equipment (EES 5.1 Detection Equipment, Method, and Standards ……electromagnetic (EM)-based detectors such as the Whites DFX 300, MineLab Explorer II, or equivalent). These various types of detection equipment will NOT be able to detect MEC/MPPEH placed in the dredging bucket and barge as the steel mass of the bucket and barge will overwhelm the ability of the detection equipment to identify the significantly smaller mass of a MEC/MPPEH item. MEC/MPPEH will not be identified if the contractor follows this procedure.

(2) Any MEC/MPPEH removed during dredging will be unrecognizable via visual means as they will be encased in mud/debris and comingled with various non-MEC/MPPEH debris.

Recommendation: MEC/MPPEH screening of dredge spoils should only be performed following placement at the drying area.

A157: (1) The MPPEH/MPPEH removal operation can be conducted on the Barge and/or at the upland Laydown Area as cited in the ESS. The sensitivity of the detection equipment can be adjusted by UXO-qualified technicians to account for the surrounding environment, including nearby metallic objects or the barge. The objective of the prescreening method is to reduce the HFD (from 5-inch projectile to 3-inch projectile) so the dredge material can be mechanically screened at the Upland Staging/Screening Areas (USSA #1 and USSA #2) to remove smaller MEC/MPPEH items down to 20mm projectile. The final draft of the ESS will be revised to state that the grizzly will be properly sized to screen-out the 5-inch projectile (Primary I MGFD) and larger.

(2) UXO-qualified technicians also know how to distinguish between munitions and non-munitions related items even with some dirt/mud covering. The dredge materials that do not pass through the grizzly will potentially contain the Primary I MGFD (5-inch projectile) and cannot be processed at USSA #1 or USSA #2 sited areas. The HFD arc for the USSA #1 and USSA #2 is for MEC management of Primary II MGFD (3-inch projectile) and under items only. However, the upland Laydown Area adjacent to the LMN Wharves is provided for MEC/MPPEH handling operations of the materials that may contain Primary I MGFD (5-inch projectile) or greater. Refer to Figures C-1, C-2, C-3, and C-4 in the appendices issued with RFP Amendment 0010.

Q158: Summary Subcontractor Participation for Bid Options 1 through 6 – Reference RFP Part A, SF1442, Factor 3 Small Business Utilization, Exhibit C Small Business Participation and Commitment Strategy:

Factor 3 – Small Business Utilization Exhibit C, Small Business Participation and Commitment Strategy requires the Offerors to complete the Contract Level Performance Summary table. The summary table provided in the Exhibit C document includes columns for dollar values for the Base, Option 1 and Option

2. The Price Proposal Schedule includes the Base Bid and Options 1 through 6. Please advise if Offerors should expand the summary table to include columns for the dollar values of Options 1 through 6 in addition to the Base.

A158: Contract Level Performance Summary Form can be expanded for additional options. See response to Question 131.

Q159: Wall Finishes – Reference RFP Part C, Drawing Nos. A-201 and A-202 (Substation - Building Elevations):

Reference Sheets A-201 and A-202. Substation Exterior Elevations call for PT1, PT2, and PT3 for wall finishes. Elevations on Sheet A-301 and A-501 call for “SKIM COATED CONC WALL, PAINTED.”

Please clarify the intent.

A159: Deferred

Q160: General Permit – Reference RFP Part B, Specification Section 01 57 19 Temporary Environmental Controls, Paragraph 3.2.1 Construction General Permit:

Please verify that the “General Permit” has been applied and paid for the NAVFAC and the Contractor is only responsible to provide a “Notice of Intent”.

A160: Deferred

Q161: Quantities of Vessel Ingress & Egress – Reference RFP Part B, Specification Section 35 20 23 Dredging, Paragraph 3.14.2 Navigation Channel, Item b:

Please fill in the "X" quantities below:

"U.S. Navy use of the channel is expected to occur regularly on average X vessel ingress and X vessel egress per week. A vessel ingress/egress requires approximately 1 hour each way. During this vessel ingress/egress, completely remove the dredge and all related equipment to such an extent to afford passage. A schedule of vessel transits can be obtained from the Contracting Officer."

A161: Deferred

Q162: Dredging – Reference RFP Part B, Specification Section 01 57 19.01 20 Supplemental Temporary Environmental Controls Lima Mike November Wharves Apra Harbor, Naval Base Guam, Water Areas Explosives Safety Submission (ESS), Paragraph 3.5.2 MEC Support to In-Water Operations:

Can dredging be performed from a crane directly on the dock and the material placed in a 3" grizzly that would also be located directly on the dock?

The trans-load pad would be outfitted with the proper environmental controls for turbidity as well as the 3" grid/grizzly for MEC screening and could even be built to have walls for additional shielding from potential MEC discharges.

A162: Deferred

Q163: FAR 52.215-1(c) – Reference RFP Part A, SF1442 Section 00 70 00 Conditions of Contract (Contract Clauses), FAR Clause 52.215-1 Instructions to Offerors--Competitive Acquisition (Jan 2017) - Alternate I, Paragraph (c):

With the current restrictions on travel and possible road blocks would it be possible to submit the proposal by email? FAR 52.215-1(c) allows for submission by email if stated in the RFP. Please provide an amendment stating that this is allowed and provide the email address to use.

Excerpt from the Governors press release:

"This is why, effective noon tomorrow, August 21, through an Executive Order, all businesses will be closed with the exception of grocery stores, healthcare operations, including pharmacies, gas stations, convenience stores, hardware stores, and those operations critical to health, shelter, and the preservation of life. It is my hope that this escalation will last only a week—just long enough to flatten our rising curve. To assuage any fears you may have because of this order, I will be establishing a hotline that will answer your questions, which we will announce tomorrow."

A163: No, electronic submission of proposals is not authorized for this solicitation. To ensure minimization of the spread of COVID-19, Offerors are asked to maintain social distancing, that is no less than six (6) feet between persons, and wear proper face coverings when hand-delivering proposals to the address specified in RFP Part A SF1442 Section 00 21 16 Paragraph 3.3. Proposal Submission. Please contact the Point of Contact (POC), Janeen Bais, at (671) 339-2572 to submit hand-delivered proposals.

Q164: Diving Certification Requirements – Reference RFP Part B, Specification Section 01 45 00.00 20 Quality Control, Paragraph 1.5.11 Underwater QC Team:

Underwater diving QC team requires a certified diving company to be a member of the ADCI. Searching the ADCI member directory there are no current members in Guam. Please remove this requirement and allow the Contractor to use the local dive companies with all of the other requirements of this section.

A164: Deferred

Q165: Water Security Fence:

(a) What is the plan for the opening and closing of the in-water security fencing?

(b) What is the time frame from requesting it opened to the time that it is opened?

(c) Does opening and closing the fencing cost the Contractor?

(d) Where is the fence connected to the existing wharf?

(e) Is there any upgrade or modification that needs to happen?

A165: Deferred

Q166: Mechanical Piping Schedule – Reference RFP Part B, Specification Section 40 05 13 Pipelines, Liquid Process Piping:

Specification Section 40 05 13 – Pipelines, Liquid Process Piping contains numerous types of piping systems including ductile iron, stainless steel, copper, PVC, CPVC, HDPE and Double Containment.

Please provide a pipe schedule that lists what piping system is associated with each type of fluid carried in piping such as for Drain, Sludge, BOW inside the BOWT facility, Air, Slop Oil, Treated Effluent, etc.

A166: Deferred

Q167: Horizontal Cold Joint in Bulkhead – Reference RFP Part C, Drawing No. S510 (Bulkhead Cap Details - 1), Detail A4:

Due to the requirement of a different concrete mix design for the bulkhead concrete (Non Segregating Admixture), placing of concrete in the water and mass concrete requirements is it acceptable to place the bulkhead with two horizontal construction joints?

A167: Deferred

Q168: Existing Storm Bollards – Reference RFP Part B, Specification Section 02 41 00 Demolition and Deconstruction:

Please confirm that the existing storm bollards cannot be salvaged for re-use on the new wharf structure.

A168: Deferred

N4019220R1300_Amendment 0010_SF30
N4019220R1300_Amendment 0010_Encl (1)_Appendices to Pre-Draft Water Areas Explosives Safety Submission
APPENDIX A. Signature Page
Table A-1. Signature Page
APPENDIX B. Supporting Explosive Safety Data
1000-lb AN-M65A1
Primary 1_MGFD_5-in Mk41 Mod 0
Primary 2_MGFD_3-in 50AP Mk29
APPENDIX C. ESQD Maps
Figure C-1: Project Area ESQD Arcs
Figure C-2: Primary 1 MGFD HFD Arcs for Dredging Operations
Figure C-3: Contingency MGFD HFD Arcs for Dredging Operations
Figure C-4: Primary 2 MGFD HFD Arcs for USSA Operations

N4019220R1300_Amendment 0010_Encl (2)_RFI Notice 10

File details come from the government source that posted it. Updated .