Amend 0013.pdf
PDF 145 KB Posted
- Attached to
- P1625 MARSOC Storage and Training Facilities
- Solicitation number
- N4008526R9012
About this file
This is an Amendment to a federal construction solicitation (Amendment 0013) for the MARSOC Storage and Training Facilities project at MCB Camp Lejeune, North Carolina. The solicitation number is N40085-26-R-9012, Project No. 25-0029, issued by NAVFAC Mid-Atlantic. The amendment, effective April 6, 2026, addresses two previously submitted Requests for Information (RFIs) and provides clarification on pricing and payment requirements.
The amendment clarifies that contractors must submit pricing for ELIN 0003, which covers all work associated with plantings at the 4,000 square foot practical application classroom training facility. The pricing sheet specifies an estimated quantity of 250 square feet and requires unit pricing with all applicable costs, overhead, and profit included. Regarding progress payments, the Government confirms that materials on site can be considered for progress payments if properly identified on the schedule of prices and stored appropriately, reversing a previous restriction on materials such as conduit, gypsum board, glass, and insulation. Contractors must acknowledge receipt of this amendment when submitting their proposal, as failure to do so may result in rejection. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0015 Pricing Sheet.pdf | ||
| Amend 0015.pdf | ||
| Amend 0014.pdf | ||
| Amend 0014 Pricing Sheet.pdf | ||
| Amend 0012.pdf | ||
| Amendment 0011.pdf | ||
| Amend 0010.pdf | ||
| Amend 0009.pdf | ||
| 22-0047 Prac App Combined Sheets - ASI 01.pdf | ||
| Amend 0008.pdf | ||
| Amendment 0007.pdf | ||
| Amendment 0006.pdf | ||
| Amend 0005.pdf | ||
| Amend 0004.pdf | ||
| Amend 0003.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| 250029 Geotechnical Report.pdf | ||
| 250029 BASIS OF DESIGN.pdf | ||
| 250029_APPXD.pdf | ||
| N4008525B0029 Dwgs.pdf | ||
| 250029 APPXD.pdf | ||
| Gen MACC RFP.pdf | ||
| N4008525B0029_Specs.pdf | ||
| 250029 Facility Geotechnical Report.pdf | ||
| Encl 1 Pricing Sheet.pdf | ||
| N4008525B0029_Dwgs.pdf | ||
| N4008525B0029 Specs.pdf |
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 3
AMENDMENT NO. 0011 04/06/26 25-0029
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-26-R-9012
02/05/26
25-0029 - P1625 MARSOC Storage and Training Facilities Amendment 0011, Answer to RFIs
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
N40085-26-R-9012 Amendment 0013
CONTINUATION SHEET
1. QUESTION: Sheet G001 Practical Application Training Facility indicates a CLIN is required for per plant pricing. This requirement is also referenced on Sheet GC100, Notes 2, 3, and 4. Please confirm whether a separate CLIN is required for per plant pricing. If so, please identify where this should be included in the pricing sheet or provide an updated pricing structure.
ANSWER: See Pricing Sheet attached.
2. QUESTION: In reference to Amendment 8, Question 3, the Government’s response indicates that materials such as conduit, gypsum board, glass, and insulation are not acceptable for progress payments. Several subcontractors have indicated they are unwilling to bid the project under these conditions. Please confirm whether the Government intends to maintain this position.
ANSWER: Refer to Amendment 0009: Yes, materials on site can be considered for progress payments if properly identified on the schedule of prices and stored appropriately.
3. All other terms and conditions remain unchanged.
P1625 MARSOC Storage and Training Facilities Solicitation No. N40085-26-R-9012 MCB Camp Lejeune Project No. 25-0029
Amendment 0013
PRICING SHEET
Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:
ELIN 0003
Price includes completing all work associated with plantings at the 4,000 sqft practical application classroom training facility in accordance with the provided drawings and specifications, but excluding work described in ELIN’s 0001 & 0002. The price for this line item should include all applicable costs, overhead and profit for this work.
Estimated Qty Unit Type Unit Price Total
250 SF
Notes A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.
B. ELINs shall include all markups (overhead, labor burden, and profit).
C. Evaluation of Options (NOV 2025). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0003. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).
| Amend 0013 Draft |
| Continuation Sheet |
| Amend 0013 Pricing Sheet |
File details come from the government source that posted it. Updated .