Amend 0012.pdf

PDF 138 KB Posted

Attached to
P1625 MARSOC Storage and Training Facilities
Solicitation number
N4008526R9012
Issued by

About this file

This is Amendment 0012 to Solicitation N40085-26-R-9012, issued by NAVFAC Mid-Atlantic on April 6, 2026, for the P1625 MARSOC Storage and Training Facilities project (Requisition 25-0029) at Camp Lejeune, North Carolina. The amendment provides government responses to four Requests for Information (RFIs) submitted by offerors and clarifies key technical and contractual requirements for the construction project.

The amendment addresses critical design and specification issues: (1) Specification sections previously removed by Amendment 8 Question 8 regarding air barrier requirements (Spec Sections 07 27 10 and 07 27 19) must remain in the project with no alternatives or removals permitted; (2) Pricing for the 4,000 square foot Practical Application Training Facility plantings should be included in the line item price, excluding work in ELIN 0001-0002, with a quantity of 250 units; (3) The design intent includes 4-inch branch piping lines, fire pump exclusion is confirmed, and PEMB bidders must account for collateral piping loads noted in Division 13 specifications with no additional guidance required; and (4) A question regarding progress payment acceptability for materials such as conduit, gypsum board, glass, and insulation is marked as "Not Applicable," indicating the government did not provide clarification on this contentious issue. All other terms and conditions of the solicitation remain unchanged. Offerors must acknowledge receipt of this amendment when submitting their proposals, or face potential rejection.

View the file

Other files

File Type Posted
Amend 0015.pdf PDF
Amend 0015 Pricing Sheet.pdf PDF
Amend 0014 Pricing Sheet.pdf PDF
Amend 0014.pdf PDF
Amend 0013.pdf PDF
Amendment 0011.pdf PDF
Amend 0010.pdf PDF
Amend 0009.pdf PDF
22-0047 Prac App Combined Sheets - ASI 01.pdf PDF
Amend 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
N4008525B0029_Dwgs.pdf PDF
250029 Geotechnical Report.pdf PDF
250029 BASIS OF DESIGN.pdf PDF
250029_APPXD.pdf PDF
N4008525B0029 Dwgs.pdf PDF
250029 APPXD.pdf PDF
Gen MACC RFP.pdf PDF
N4008525B0029 Specs.pdf PDF
N4008525B0029_Specs.pdf PDF
250029 Facility Geotechnical Report.pdf PDF
Encl 1 Pricing Sheet.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 3

AMENDMENT NO. 0011 04/06/26 25-0029

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-26-R-9012

02/05/26

25-0029 - P1625 MARSOC Storage and Training Facilities Amendment 0011, Answer to RFIs

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

N40085-26-R-9012 Amendment 0012

CONTINUATION SHEET

1. QUESTION: Following the Government’s response in Amendment 8 question 8 that the air barrier requirements may be removed, can the Government confirm what, if any, alternative requirements will be provided in place of Spec Section 07 27 10 and 07 27 19, or if these requirements will be removed in their entirety with no replacement?

ANSWER: Specification sections previously removed by Amendment 8 Question 8 must remain in the project.

2. QUESTION: Sheet G001 Practical Application Training Facility indicates a CLIN is required for per plant pricing. This requirement is also referenced on Sheet GC100, Notes 2, 3, and 4. Please confirm whether a separate CLIN is required for per plant pricing. If so, please identify where this should be included in the pricing sheet or provide an updated pricing structure.

ANSWER: Price includes completing all work associated with plantings at the 4,000 SF practical application classroom training facility in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001-0002. The price for this line item should include all applicable costs, overhead and profit for this work.

QTY: 250

3. QUESTION: In reference to Amendment 8, Question 1, the Government’s response indicates that the engineer assumed significantly large pipe sizes, including 4-inch branch lines, in order to rule out the need for a fire pump. From our perspective, pipe sizes of this scale would typically require a fire pump and may also create concerns with system weight and coordination, especially within a PEMB structure. It is unclear if the current documents provide enough information for the building supplier to account for this condition. (1) Please confirm whether the design intent includes 4-inch branch lines. (2) Confirm whether a fire pump is to be excluded. (3) Provide any additional guidance needed for accurate pricing and coordination.

ANSWER:

(1) Please confirm whether the design intent includes 4-inch branch lines. Yes. PEMB bidders should be aware of collateral loads which include piping, specifically noted in Div 13 spec.

(2) Confirm whether a fire pump is to be excluded. Fire pump is to be excluded.

N40085-26-R-9012 Amendment 0012

(3) Provide any additional guidance needed for accurate pricing and coordination. There is no additional guidance needed.

4. QUESTION: In reference to Amendment 8, Question 3, the Government’s response indicates that materials such as conduit, gypsum board, glass, and insulation are not acceptable for progress payments. Several subcontractors have indicated they are unwilling to bid the project under these conditions. Please confirm whether the Government intends to maintain this position.

ANSWER: Not Applicable

5. All other terms and conditions remain unchanged.