About this file
This is Amendment 0009 to Solicitation N40085-26-R-9012 for MARSOC Storage and Training Facilities, issued by NAVFAC Mid-Atlantic. The amendment's effective date is March 25, 2026, and it modifies the original solicitation dated February 5, 2026. The primary change extends the proposal receipt deadline to March 30, 2026 at 3:00 PM. Offerors must acknowledge receipt of this amendment prior to proposal submission to avoid potential rejection. The amendment also provides a continuation sheet addressing Question 3 from Amendment 0008, clarifying that materials on site can be considered for progress payments if they are properly identified on the schedule of prices and stored appropriately.
All other terms and conditions of the original solicitation remain unchanged and in full force and effect. Contracting administration is handled by NAVFAC Mid-Atlantic's Resident Officer in Charge of Construction located at 1107A Birch Street, Camp Lejeune, NC 28547-2521. Offerors may acknowledge the amendment by completing and returning copies, acknowledging receipt on each proposal copy, or submitting a separate letter or telegram referencing the solicitation and amendment numbers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0015.pdf | ||
| Amend 0015 Pricing Sheet.pdf | ||
| Amend 0014 Pricing Sheet.pdf | ||
| Amend 0014.pdf | ||
| Amend 0013.pdf | ||
| Amend 0012.pdf | ||
| Amendment 0011.pdf | ||
| Amend 0010.pdf | ||
| 22-0047 Prac App Combined Sheets - ASI 01.pdf | ||
| Amend 0008.pdf | ||
| Amendment 0007.pdf | ||
| Amendment 0006.pdf | ||
| Amend 0005.pdf | ||
| Amend 0004.pdf | ||
| Amend 0003.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| N4008525B0029_Dwgs.pdf | ||
| 250029 Geotechnical Report.pdf | ||
| 250029 BASIS OF DESIGN.pdf | ||
| 250029_APPXD.pdf | ||
| N4008525B0029 Dwgs.pdf | ||
| 250029 APPXD.pdf | ||
| Gen MACC RFP.pdf | ||
| N4008525B0029 Specs.pdf | ||
| N4008525B0029_Specs.pdf | ||
| 250029 Facility Geotechnical Report.pdf | ||
| Encl 1 Pricing Sheet.pdf |
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 2
AMENDMENT NO. 0009 03/25/26 25-0029
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-26-R-9012
02/05/26
25-0029 - P1625 MARSOC Storage and Training Facilities Amendment 0009
The time and date for receipt of proposals has changed to March 30, 2026 at 3:00PM
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
N40085-26-R-9012 Amendment 0009
CONTINUATION SHEET
1. Replace the answer to Question 3 from Amendment 0008 with the following response:
Yes, materials on site can be considered for progress payments if properly identified on the schedule of prices and stored appropriately.
2. All other terms and conditions remain unchanged.