250029 BASIS OF DESIGN.pdf

PDF 3 MB Posted

Attached to
P1625 MARSOC Storage and Training Facilities
Solicitation number
N4008526R9012
Issued by

About this file

This is a Design Narrative for the MRSG DST Storage Facility at MARSOC, Camp Lejeune, North Carolina, submitted as the final design submittal on February 22, 2024, under Contract No. N40085-22-D-0013, Task Order No. N4008523F6883.

The project involves designing a 6,000 square-foot pre-engineered metal building with a standing seam metal roof, brick veneer on steel stud backup, and a monolithic concrete foundation and floor slab. The facility includes three cage storage areas with storage racks, overhead door access, work benches, and a toilet room with shower. Civil work encompasses site preparation, a heavy-duty concrete apron for vehicular access, trench drainage, protective bollards, grading for drainage, utility service extensions (water, sanitary sewer, electric, and communications), and erosion control measures. Structural design follows 2018 International Building Code and ASCE 7-16 standards with Type IIB construction classification and concrete exposure class F1. Architectural elements include split-face CMU and brick veneer exterior walls with 2.5 inches of rigid insulation, R-19 roof insulation, insulated 10' x 12' metal coiling doors, and sealed concrete interior flooring with rubber base. Plumbing systems include a reduced pressure zone backflow preventer, domestic water distribution, sanitary sewer connection, hot water supply (80-gallon heater with 4.5 kW input), and fixtures specified for water conservation. Mechanical design incorporates split system heat pumps for each storage bay with MERV 8 and 13 filters, ASHRAE 62.1-2016 outdoor air requirements, and a building automation system with BACnet technology for direct digital control. Electrical service consists of three 37.5 kVA pole-mounted transformers providing 208-volt, 3-phase, 100-amp service with LED lighting throughout at 3500K interior and 4000K exterior, occupancy sensors, and dedicated circuits for equipment. Fire protection includes automatic sprinkler systems designed per NFPA 13 for Class IV commodities at 0.30 gpm/sf with 500-gpm hose stream allowance, quick response sprinklers, and fire department connections. Telecommunications infrastructure provides 25-pair copper and 12-strand single-mode fiber optic service with CAT6 cabling, cable trays, and an enclosed telecommunications cabinet. The design achieves 25.7% energy cost savings compared to ASHRAE 90.1-2010 baseline through efficient HVAC systems, LED lighting, and building envelope improvements, meeting UFC requirements for sustainable design and operation.

View the file

Other files

File Type Posted
Amend 0015.pdf PDF
Amend 0015 Pricing Sheet.pdf PDF
Amend 0014.pdf PDF
Amend 0014 Pricing Sheet.pdf PDF
Amend 0013.pdf PDF
Amend 0012.pdf PDF
Amendment 0011.pdf PDF
Amend 0010.pdf PDF
Amend 0009.pdf PDF
22-0047 Prac App Combined Sheets - ASI 01.pdf PDF
Amend 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
250029 Geotechnical Report.pdf PDF
250029_APPXD.pdf PDF
N4008525B0029 Dwgs.pdf PDF
250029 APPXD.pdf PDF
Gen MACC RFP.pdf PDF
N4008525B0029_Dwgs.pdf PDF
N4008525B0029 Specs.pdf PDF
N4008525B0029_Specs.pdf PDF
250029 Facility Geotechnical Report.pdf PDF
Encl 1 Pricing Sheet.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design Narrative

23-0033 MRSG DST STORAGE FACILITY

MARSOC

CAMP LEJEUNE, Jacksonville, NC

CONTRACT NO. N40085-22-D-0013

TASK ORDER NO. N4008523F6883

for

PUBLIC WORKS DIVISION

MARINE CORPS BASE CAMP

CAMP LEJEUNE, NORTH CAROLINA

FINAL SUBMITTAL

02-22-2024

Prepared by:

151 Poole Road; Suite 100

Leland, NC 28451

(910) 383-1044

N.C. License #C-1621

Table of Contents

Introduction

Civil scope

Structural scope

Architectural scope

Plumbing scope

DOMESTIC WATER CALCULATIONS

SANITARY SEWER CALCULATIONS

HOT WATER CALCULATIONS

Mechanical scope

Electrical scope

Fire Protection

Telecommunications scope

Appendix A – Flow Test

Appendix B – Mechanical Design Analysis

Appendix C – Electrical Design Analysis

MRSG DST Storage Facility – MARSOC

Introduction

The project location is an existing developed area at MARSOC The project consists of a 6,000 SF pre-engineered metal building with standing seam metal roof, brick veneer on steel stud backup, monolithic concrete foundation and floor slab, site work and utilities. Room requirements include a general storage area consisting of 3 cage storage areas with storage racks, overhead door access, and work benches (by others), and toilet room.

Civil scope

DESIGN CRITERIA

The following criteria references shall be used in the design of this project where they apply to the required scope of work:

1. Project RFP

2. UFC 3-201-01 - Civil Engineering

3. AASHTO Assoc. of State Highway & Transportation Officials

4. NCDOT North Carolina Department of Transportation

5. NCDEQ Sedimentation and Erosion Control Manual

Existing Site Conditions

The project site is located north of Anchor Road between Rifle Range Rd on the west and Globe Rd on the east. The site fronts on an existing large, paved parking and access area with existing catch basins. The MRSG building is located directly south of three existing warehouse buildings of similar size and is situated inside of a fenced compound. The site is grassed and the surrounding area to the east is mostly open with grass and tree cover, and several storm ponds.

Demolition will include clearing and grubbing the turfed area, and chain-link fence removal and relocation around the MRSG building to include it within the fenced compound.

Proposed Site and Utility Features

A heavy-duty concrete apron will be provided for vehicular access from the existing paved parking and access area to the building. The concrete apron will consist of a rigid pavement section of 6” of

650 psi flexural concrete with WWF mesh and 6” NCDOT aggregate base course over an approved subgrade. Pavement and sidewalk patches will match existing sections and be performed in a neat manner.

To assist drainage at the impervious areas, a trench drain will be provided along the full width of the loading apron, daylighting to graded swale south of the new building. The building site will be graded to fall towards the naturally sloping undeveloped areas east of the building.

Protective bollards will be utilized at building service doors where vehicular damage could occur.

An existing water distribution line runs in the east-west direction to the south of the site and a new water service and fire service line will be installed to serve the new building. An existing sanitary sewer collection line runs to the north of the building site in the east-west direction and a new sanitary sewer service line will connect to this main and terminate with a clean-out approximately

5-feet outside the building. These service lines are tapping existing utility mains and NCDEQ water and sanitary sewer permits are not required.

An existing overhead electric line passing over the building site will be relocated by providing a new power pole southeast of the building site. A pad mounted transformer will be provided on site with underground primary provided from the overhead service at the relocated power pole, with underground secondary from the transformer to the building. An existing communication manhole located south of the site will provide communication lines extended to an existing comm handhole near the northeast corner of the building.

All disturbed areas will be sodded.

Stormwater and Erosion Control

The existing drainage patterns on site will be maintained to the maximum extent possible with building downspouts discharging via concrete splash blocks to grade and sheet flowing across the site.

Erosion and sedimentation control measures will be utilized during construction to prevent sediment from leaving the site.

Disturbance on site is limited to less than the required threshold, therefore no environmental permits are expected to be required for this project.

Structural scope

DESIGN CRITERIA

1. Project RFP

2. 2018 International Building Code

3. ASCE 7-16

4. UFC 3-301-01

5. ACI 318-14

6. AISC

Design Loads

All footings and walls will be designed to meet all provided loading included in the RFP specifications/pricing documents provided to the design team.

Anti-Terrorism / Security

No ATFP requirements in structural scope for this project.

Concrete Exposure Class

Concrete exposure class will be F1 (Concrete exposed to freezing-and-thawing cycles with limited exposure to water) as listed in table 19.3.1.1 in ACI 318-14. F1 Exposure Class has a minimum compressive strength requirement of 3,500 psi and a maximum water/cement ratio of 0.55 per table 19.3.2.1.

Architectural scope

DESIGN CRITERIA

The following criteria references shall be used in the design of this project where they apply to the required scope of work:

1. Project RFP

2. UFC 1-200-01 DoD Building Code, with Change 1

3. UFC 1-200-02 High Performance and Sustainable Building Requirements, with Change 2

4. FC 1-300-09N Navy and Marine Corps Design Procedures, with Change 6

5. UFC 3-101-01 Architecture, with Change 1

6. UFC 3-110-03 Roofing, with Change 5

7. UFC 3-120-01 Design: Sign Standards, with Change 3

8. UFC 3-120-10 Interior Design, with Change 2

9. Architectural Barriers Act Accessibility Standards (ABAAS)

10. 2010 ADA Standards for Accessible Design

11. Marine Corps Base Camp Lejeune Base Exterior Architectural Plan (BEAP)

The architectural scope consists of the design of a new 6,000 sf pre-engineered metal building. The building will include three large open caged areas with storage racks, work benches and a toilet room with shower. There will be 8’ wide x 8’ high sliding chain link gates between the caged bays.

The exterior of the building will be composed of split face CMU and brick veneer with a steel stud back up. The walls will have 2 ½” rigid insulation or closed cell spray foam insulation in the wall cavity to act as the continuous insulation and moisture barrier for the building. The walls will have a minimum thermal resistance of R-13 insulation in accordance with ASHRAE 90.1. The building will have a reinforced concrete slab on grade with turn down edges and rigid insulation extending 24” horizontally from the building’s perimeter. The slab finish will be sealed concrete.

The exterior doors will be insulated electrically operated 10’ wide x 12’ high metal coiling doors, insulated metal personnel doors and frames. The roof will consist of a hydrostatic prefinished metal roofing system provided by the Pre-Engineered Metal Building Manufacturer. The roof will have an R-19 with an R-11 liner system in accordance with ASHRAE 90.1. There will be a metal panel soffit under the roof overhang.

Aluminum framed translucent panel windows will be placed high in the front and rear walls of the building to allow natural light to the caged areas.

The interior of the building will consist of a large open workspace. There will not be ceilings in the workspace and the floor will be sealed concrete floor with rubber base. This area will house storage lockers, and work bench areas along with other support functions. The toilet and shower room will receive tile floors, full height tile walls, and a painted gypsum board ceiling. There will be a steel stud framed ceiling platform above the toilet/shower room with a plywood deck. The interior walls will be painted hi-abuse gypsum board on metal stud framing including the perimeter exterior walls. All the storage racks shown on the drawings are for space planning purposes and sizes and modules should be confirmed with the user.

Plumbing scope

DESIGN CRITERIA

UFC 3-420-01 Plumbing Systems (UFC)

PLUMBING SYSTEMS

The plumbing systems within the facilities will consist of the following plumbing fixtures:

• Water Closet

• Lavatory

• Service Sink

• Bi-level Water Cooler

• Wall Hydrant

• Floor Drains

• Water Meter

A reduced pressure zone backflow preventer will be provided on the domestic water service and will be located in the corner of Bay 1- Room 101. Sanitary sewer piping and vent piping for the building will be connected to the site sanitary system at a point approximately 5’-0” outside of the building.

DOMESTIC WATER CALCULATIONS

14 Water Supply Fixture Units (WSFU)

30 GPM, 1-1/4” Dia. Main

SANITARY SEWER CALCULATIONS

11 Drainage Fixture Units (DFSU)

This equates to a 4” sanitary sewer main @ 1/8” per foot slope

HOT WATER CALCULATIONS

Mixed Water Temperature Equation: P = (Tm – Tc) / (Th-Tc)

Th = Supply hot water temperature

Tc = Inlet cold water temperature

Tm = Desired mixed water temperature

P is the hot water multiplier, which is expressed as a percentage.

P = (122 – 60) / (140 – 60)

P = 62 / 80 = .78

1.75 GPM (shower demand per head) x .78 = 1.37 GPM

1 shower x 1.37 x 60 minutes = 82.2 GPH

Additional fixtures:

(1) Lavatory x 6 GPH = 6 GPH

Subtotal – 6 GPH x .3 (Demand Factor) = 1.8 GPH

Total – 82.2 + 1.8 = 84 GPH Peak Demand (1 hour)

The water heater specified is 80 gallon (64 gallons available total) with 4.5 kW input and recover a total of 21 GPH at 90-degree rise. Therefore, 85 gallons is available to meet the one-hour peak demand.

FIXTURES AND EQUIPMENT

Water closet will be floor mounted, bottom outlet, dual flush valve, elongated bowl with open front seat less cover. Water usage will be 1.6 / 1.1 gallons per flush.

Lavatory will be wall-hung, vitreous china, with single-handle faucet, 1-1/2 inch P-Trap and 3/8 inch angle supplies with stop valves for hot and cold water. Faucets will be 0.5 gpm flow.

Floor drains will be provided in bathroom and for backflow preventer and water heater.

MATERIALS

The above grade sanitary waste, vent, and storm systems will be PVC pipe and fittings with glued joints. The below grade sanitary waste, vent, and storm systems will be PVC pipe and fittings with glued joints.

Domestic water piping will be copper tubing, ASTM B88; Type L with solder joint fittings fabricated with code approved “lead free” solder for above ground piping and type K copper tubing for below grade applications.

Elastomeric foam insulation with vapor barrier will be applied to all domestic cold and hot water piping and all above grade storm and condensate piping.

Valves will be solder type, ball, for use with the copper tubing, Class 125 in accordance with MSS

SP-80.

TESTING

Domestic water piping will be tested in sections at 100 psig for two hours.

DWV piping will be subjected to a final air pressure test of 1.0 inches of water column, or a smoke test. Disinfection will be in accordance with AWWA C651 using a solution containing a minimum of

50 parts per million of available chlorine.

Mechanical scope

The design shall be in accordance with the latest editions of, but not limited to, the following design criteria:

International Mechanical Code – 2015 Edition

UFC 3-401-01 - Mechanical Engineering

UFC 3-410-01 - Heating, Ventilation and Air Conditioning Systems

UFC 4-010-01 - DoD Minimum Antiterrorism Standards for Buildings

ASHRAE 62.1 – 2016 - Ventilation for Acceptable Indoor Air Quality

ASHRAE 90.1 – 2013 - Energy Standard for Buildings except Low Rise Residential Buildings

FC 1-300-09N - Navy and Marine Corps Design Procedures

PROJECT DESCRIPTION

This project consists of one new single story 6,000 sq.ft. facility.

DESIGN CONDITIONS

Outdoor Summer Design temperatures: 91.0°F DB / 77.0°F WB (1% ASHRAE)

Outdoor Winter Design temperature: 27.0°F DB (99% ASHRAE)

Indoor Design Conditions: Occupied: 76°F Summer / 68°F Winter

Unoccupied: 82°F Summer / 55°F Winter

Indoor Design Relative Humidity: 30% to 60%

ASHRAE Climate Zone 3A

MECHANICAL SYSTEM

Each bay storage area will be served by its own split system heat pump. The air handling unit will have MERV

8 and 13 filters on the return/outside air. The amount of outside air will be measured to ensure sufficient quantities are brought into the building to meet ASHRAE 62.1 – 2016 requirements to maintain indoor air quality, and positively pressurize all rooms with exterior openings.

General

Air distribution will be via overhead galvanized sheet metal ductwork designed in accordance with

SMACNA Duct Construction Standards. Duct will be wrapped with 2”, 1-lb. exterior insulation, no duct liner shall be used. Exposed duct shall be double wall 2” insulated spiral lock seam construction. Exterior duct shall be prefabricated and insulated phenolic duct suitable for exterior installations. The ductwork systems are designed to provide a low noise environment. Air distribution shall be duct or ceiling mounted. Duct construction shall be for low pressure VAV usage.

All air systems shall have a full Test and Balance performed to verify performance match’s design.

Exhaust shall be provided in the Toilet room and shall be exhaust directly out the building. Make-up air shall be through a supply grille in the ceiling grid as well as a transfer grille from the storage room.

ATFP

All applicable requirements of UFC 04-010-01 will be followed. All outside air intakes shall be a minimum of 10’ above grade. Low leakage dampers will be installed at all building exterior wall penetrations by the HVAC system. An emergency stop button will be located inside the facility to shut down all air moving systems.

BUILDING AUTOMATION SYSTEM

All control and monitoring points will be connected through a single complete building automation system (BAS) suitable for direct digital control (DDC) of all HVAC system components within the building. The control system within the building shall utilize an open protocol implementation of

BACnet technology and will utilize ANSI/CEA 709.1B as the communication protocol between DDC hardware devices. All utility meters shall employ the BACnet protocol, with the water meter outputting to the building DDC system and the electric meters outputting directly to the basewide electric metering system. The DDC system will have the ability to limit the operating hours of any equipment, as well as perform setback functions when parts of the building are unoccupied. The

DDC system will be compliant with all Cybersecurity requirements. A local display panel for monitoring and scheduling program changes will be provided. The BAS shall be provided with a router to communicate all building points to the basewide EMCS.

CALCULATIONS

• Included in the separate document “MRSG – Mechanical Design Analysis.pdf” are the following:

o Carrier HAP Load Calculations, including all input data, equipment sizing calculations and outside air calculations.

SUSTAINABLE DESIGN

The HVAC systems for this project have been designed in accordance with UFC 1-200-02. An

Energy Model has been used to show that the facility has achieved energy savings above a baseline system. The Energy Model has been run utilizing the Carrier HAP program, version 5.11. The selected system was compared with the ASHRAE 90.1-2010 Appendix G Baseline system, with savings calculated below.

Electrical scope

UFC 3-501-01 Electrical Engineering

UFC 3-520-01 Interior Electrical Systems

UFC 3-530-01 Interior and Exterior Lighting Systems and Controls

UFC 3-550-01 Exterior Electrical Power Distribution

UFC 3-560-01 Electrical Safety, O&M

UFC 3-575-01 Lightning and Static Electricity Protection Systems

NFPA 70 National Electric Code

NFPA 101 Life Safety Code

NFPA 780 Standard for the Installation of Lightning Protection Systems

Applicable UL standards

Applicable NEMA standards

EXTERIOR ELECTRICAL SYSTEMS

A new electrical system will connect the existing 12.47 kV primary on site and (3) new 37.5 kVA pole-mounted transformers will be provided to serve this building. Secondary service conductors shall be fed from these transformers to a service-entrance rated, 208 volt, 3-phase, 100-amp main breaker panel inside the building. A spare conduit will be installed in the service duct bank to allow for future flexibility.

INTERIOR ELECTRICAL SYSTEMS

The electrical building distribution system shall be designed for the type of loads served. All panels shall be fully rated for fault current and designed with a minimum of 20% spare breaker capacity and 15% space in each panel. All panels shall have copper bus, a separate grounding bus, and will utilize bolt-on type breakers. All feeders shall be sized for a maximum voltage drop of 2%, while branch circuits shall not exceed a voltage drop of 3%. Panels that supply non-linear loads will be provided with a 200% rated neutral. All conductors shall be copper, and MC cabling is not allowed.

All conductors shall be installed in conduit with a minimum conduit size of 3/4”. All electrical devices in this facility shall be U.L. listed and labeled.

Interior lighting shall be designed in accordance with the Illuminating Engineering Society (IES) recommendations. Lighting levels shall meet UFC and user requirements. All new light fixtures shall be energy-efficient LED type. Lighting shall consist of fixtures suitable for the environment in which they are being installed. Emergency lighting shall be separate wall pack fixtures per base standards and shall be spaced to comply with NFPA 101. Test switches shall be integral to fixture.

Exit signs shall be LED type, and night lights shall be designed and located according to code requirements. Interior lighting shall be provided at 3500K and exterior lighting at 4000K. Lighting controls, where applicable, will be utilized to meet ASHRAE and UFC requirements, and also to maximize energy savings. This could include dual technology occupancy/vacancy sensors, relay panel, timeclock, and/or photocell.

Receptacles and power for all areas shall follow project and user requirements as it relates to locations, spacing, heights, and type. Connections for all equipment shall be provided for all new equipment per information provided. Dedicated circuits will be run as required for equipment or user needs. Electrical power and infrastructure for mechanical, plumbing, telecommunications, audio/visual (AV), and other low voltage systems will be coordinated and provided to meet project specifications.

Fire Protection

The following building and fire safety codes and standards apply to this project:

· Unified Facilities Criteria, including, but not limited to:

· UFC 1-200-01, DoD Building Code, 12 June 2023;

· UFC 3-520-01, Interior Electrical Systems, 12 April 2021;

· UFC 3-600-01, Fire Protection Engineering for Facilities, 6 May 2021;

· UFC 4-440-01, Warehouses and Storage Facilities, 1 April 2019

· ICC International Building Code – 2021 Edition (IBC);

· National Fire Protection Association (NFPA) Standards, including, but not limited to:

· NFPA 1, Fire Code – 2024 Edition;

· NFPA 13, Installation of Sprinkler Systems – 2022 Edition;

· NFPA 24, Installation of Private Fire Service Mains and Their Appurtenances – 2022 Edition;

· NFPA 70, National Electrical Code – 2023 Edition;

· NFPA 72, National Fire Alarm and Signaling Code – 2022 Edition;

· NFPA 90A, Installation of Air-Conditioning and Ventilating Systems, – 2024 Edition;

· NFPA 101, Life Safety Code – 2024 Edition (LSC); and

· The Architectural Barriers Act (ABA).

UFC 3-600-01 generally requires construction issues to comply with IBC criteria and life safety/egress issues to meet the requirements of LSC. Fire resistance ratings are required to comply with IBC criteria. For occupancy separations and LSC criteria for interior non-bearing walls (other than occupancy separations) [UFC 3-600-01 §3-2 & 3-3].

DESIGN ANALYSIS

Building Description

The MRSG DST Storage Facility consists of a 6,000-sf one-story building. The primary use of the facility includes storage and support spaces (e.g., toilets). The building will be a pre-engineered metal building. The facility will be equipped with automatic sprinkler protection throughout the building. Code allowances for fully-sprinklered buildings will be applied.

Occupancy

1. The primary use of the building will be for storage.

2. For IBC compliance the facility will be classified as a Group S-1, Moderate Hazard Storage [IBC

§311.2] occupancy.

3. For LSC compliance, the facility will be classified as a storage [LSC Chapter 42] occupancy [LSC

§6.1.13.1 & LSC §42.1.5].

4. Special hazard areas including any mechanical, utility, and electrical areas are considered incidental to the main occupancy. These areas are required to be protected in accordance with

LSC Section 8.7.1.

Construction Requirements

1. The minimum construction type of a structure is required to comply with the fire resistance requirements and fire area limitations in UFC 3-600-01 and the IBC. The minimum construction type of a building is typically based on the height, area, occupancy, open street frontage, and automatic sprinkler protection provided in the building.

2. In accordance with IBC Chapter 5, the building will be constructed to be Type IIB construction.

The height and area limitations in Table 3.1 apply to the building for confirming the minimum required construction type.

Table 3.1: Limitations for Type IIB Construction Group S-1

Single-Story

Sprinklered

Allowable Height

[IBC Table 504.3] 75-ft

Allowable Number of

Stories [IBC Table 504.4]*

Allowable Area Per Story

[IBC Table 506.2] 70,000-sf

*: Limited to a single story to allow for the increase in allowable area for a single-story building per IBC

Table 506.2.

3. The building has a total footprint area of approximately 6,000-sf. As the allowable area for

Group S-1 of 70,000-sf is greater than the actual footprint area of the building Type IIB construction is allowable.

4. The required fire resistance ratings of building structural elements as specified in IBC Table 601 are provided in Table 3.2 below for Type IIB construction:

MRSG DST Storage Facility – MARSOC November 30, 2023

Camp Lejeune, North Carolina p. 5

Fire Protection Design Analysis 50% Submittal

Table 3.2: Type IIB Resistance Ratings of Structural Elements Building Element IBC Type IIB

Structural frame, including columns, girders, trusses a 0-hr

Bearing walls, exteriorb 0-hr

Bearing walls, interiorc 0-hr

Non-bearing walls, exteriorb 0-hr

Non-bearing walls, interiorc 0-hr

Floor construction, including supporting beams and joists 0-hr

Roof construction, including supporting beams and joists 0-hr a The structural frame is considered to be the columns and the girders, beams, trusses, and spandrels having direct connections to the columns and bracing members designed to carry gravity loads.

b Based on IBC Table 705.5 for a fire separation distance of 10-feet or more.

c Not less than the fire resistance required by other section of the code.

5. The roof coverings and roof deck assemblies must be in accordance with UFC 3-600-01 Sections

15-1 and 15-2.

Exterior Fire Exposure

1. The requirements for providing fire resistance-rated exterior walls and openings are based on the fire separation distances (FSD) between buildings and the occupancy groups within the buildings.

2. The fire separation distance is defined as the distance measured from the building face to the closest interior lot line, to the centerline of a street or public way, or to an imaginary line between two buildings on the same lot [IBC §602].

3. The fire separation distance is a measure of the separation to a point along a line between buildings, not the actual distance between buildings. The fire separation distance is measured at right angles from the face of the wall.

4. Once the location of the lot line is established, all future provisions must be based on this lot line and applied to both buildings. Where the lot line is not parallel to the exterior wall of a building, the required fire resistance rating may vary along the building side.

5. For building sides not fronted by a street, the fire separation distance is measured to an imaginary line between the buildings assuming the buildings are located on the same property

(i.e., an interior lot line).

6. Where a new building is erected on the same lot as an existing building, the code requires the assumed property line to be located such that the existing building complies with exterior wall and opening protection criteria [IBC §605.3].

7. The fire-resistance rating of exterior walls with a fire separation distance of 10-ft or less shall be rated for exposure to fire from both sides [IBC §705.5].

8. The exterior walls are required to extend the full height of the building and be constructed to remain in place for the duration of time indicated by the required fire-resistance rating

[IBC §705.6].

9. The code requirements for the fire-resistance rating and exterior wall openings are provided in

Table 3.3.

Table 3.3: Fire-Resistance Rating Requirements for Exterior Walls of

Type IIB Buildings Based on Fire Separation Distance [IBC Table 705.5]

Fire Separation Distance

(FSD)

Group S-1

FSD < 5-feet 2-hr

5-feet ≤ FSD < 10-feet 1-hr

FSD ≥ 10-feet r

10. The Storage Facility is at least 40-ft from the adjacent buildings and any other structure on all sides. This provides a FSD of at least 30-ft from the adjacent buildings to an imaginary lot line and at least 10-ft from the imaginary lot line to the Storage Facility. The exterior wall of the building is not required to have a fire-resistance rating and there is no limit on the area of openings [IBC §705.8.1 Exception 2].

11. Openings in the exterior wall are required to be in accordance with IBC Section 705.8.3.

HVAC Systems

1. Air handling, HVAC, and exhaust systems, including fire/smoke dampers, are required to comply with NFPA 90A except as modified by UFC [UFC 3-600-01 §28-1].

2. Fire dampers are required in ductwork or air transfer openings that penetrate fire resistance rated assemblies. NFPA 90A permits the deletion of fire dampers in fully ducted penetrations of

1-hour fire resistance-rated partitions.

3. The installation of duct detectors is required to comply with NFPA 90A. Smoke detectors listed for use in air distribution systems shall be located downstream of the air filters and ahead of any branch connections in air supply systems having a capacity greater than 2,000-cfm [NFPA 90A

§11.4.2.1 (1)].

4. Plenum spaces may be used as part of an air handling system where the plenums comply with

NFPA 90A [UFC 3-600-01 §28-1.2]. Rooms or areas that form a plenum space or that are used as a plenum must not be occupied for any purpose except during repairs and maintenance operations to the air-handling equipment [UFC 3-600-01 §28-1.2].

Interior Finish Materials

1. Interior walls and ceiling finishes are required to comply with UFC 3-600-01 Section 8-1 which requires wall and ceiling finishes, and movable partitions to conform to the requirements of the

LSC. The LSC restricts the use of certain materials as interior finishes on walls and ceilings based on the flame spread rating and smoke development rating of the material. Interior wall and ceiling finishes shall be classified in accordance with ASTM E-84.

2. The interior finish materials shall be grouped in the following classes, based on their flame spread rating and smoke developed rating [LSC §10.2.3.4]:

Class A – Flame spread 0-25, smoke developed 0-450

Class B – Flame spread 26-75, smoke developed 0-450

Class C – Flame spread 76-200, smoke developed 0-450

3. Table 3.5 summarizes the interior finish requirements for the Storage Facility [LSC Table A.10.2.2 note (6)].

Table 3.5: Minimum Interior Finish Requirements

Note: Automatic sprinkler protection allowances have been applied.

4. The codes also specify requirements for interior floor finish and floor covering materials. Floor coverings other than carpet shall have a minimum critical radiant flux of 0.1 W/cm2 [LSC

§10.2.7.2]. Interior floor finish materials shall be classified in accordance with NFPA 253, Standard Method of Test for Critical Radiant Flux for Floor Covering Systems Using a Radiant

Heat Energy Source as follows [LSC §10.2.7.4]:

Class I – Critical radiant heat flux ≥ 0.45 W/cm2

Class II – Critical radiant heat flux ≥ 0.22 W/cm2

5. There are no additional requirements for floor finish in all areas for storage occupancies [LSC

Table A-10.2.2, Note 6].

Means of Egress

Means of egress are required to comply with the LSC except as modified by the UFC [UFC 3-600-01

§10-

1.1]. Where egress elements serve multiple occupancies, the most restrictive requirements apply.

Occupant Load

1. The calculated occupant loads are required to be determined in accordance with LSC Section

7.3.1.2. The occupant load is determined based on the use and area of the space, and the

Occupancy Exits Exit Access Corridors Other Spaces

Storage Minimum Class C Minimum Class C Minimum Class C occupant load factors specified by the LSC. Table 3.6 summarizes the applicable occupant load factors for the Storage Facility.

Table 3.6: Applicable Occupant Load Factors

Use Occupant Load Factor (sf/person)

Storage Maximum Probable Business 150

2. Table 3.7 summaries the occupant load calculations for the building per the LSC.

Table 3.7: Calculated Occupant Loads per LSC

Area Occupancy / Use Approx. Area

(sf)

Occupant Load

Factor (sf/person)

Occupant Load

(persons)

Toilet Business 93 150 1

Bay 1 Storage 1,708 Max. Probable 4

Bay 2 Storage 1,887 Max. Probable 4

Bay 3 Storage 1,825 Max. Probable 4

Total 5,513 - 13

Number & Capacity of Means of Egress

1. A minimum of two means of egress is required from areas with an occupant load of 500 persons or less, a minimum of three means of egress is required for areas with an occupant load of 500 to 1,000 persons, and a minimum of four means of egress is required for areas with an occupant load of more than 1,000 persons [LSC §7.4.1.2, §42.2.4.1].

2. A single means of egress is permitted when the travel distance is less than the common path of travel limitation [LSC §42.2.4.1(2)].

3. The LSC specifies an exit capacity factor 0.2 inches of exit width per person for level exit components (e.g., doors, corridors, ramps) [LSC Table 7.3.3.1].

4. Table 3.8 summarizes the number and capacity of exits provided for the renovation areas per the LSC.

Table 3.8: Number of Exits and Capacity

Floor Level Required

Exit

Capacity

Available Exit

Capacity

Number of Exits

Required

Number of Exits

Provided

Storage

Facility 13 680 1 4

5. Based on the proposed floor plan, the number and capacity of the exits serving the Storage

Facility are adequate.

Arrangement of Means of Egress

1. Where two or more means of egress (exits or exit access) are required, the means of egress are required to be located remote from one another, so that the distance between them is at least one-half the maximum diagonal distance of the area served [LSC §7.5.1.3.2].

2. Travel distance to an exit, dead-ends, and common paths of travel are limited based on occupancy [LSC Table A.7.6]. Table 3.9 summarizes the exit access travel distance, dead-end, and common path of travel limitations for the facility.

Table 3.9: General Arrangement of Means of Egress Criteria

Note: (1) Automatic sprinkler protection allowances have been applied.

3. Travel distance, common path of travel, and dead ends will be provided in accordance with LSC

Table A.7.6.

Accessible Means of Egress

1. Accessible means of egress shall comply with LSC [UFC 3-600-01 §10-1.2]. Areas accessible to people with severe mobility impairment are required to be provided with not less than two accessible means of egress unless exit access travel along the accessible means of egress is less than the permitted common path of travel [LSC §7.5.4.1 & §7.5.4.1.4].

2. Where two accessible means of egress are required, the exits serving such means of egress will be located at a distance from one another not less than one-half the length of the maximum overall diagonal of the building/area unless the building is fully sprinklered [LSC §7.5.4.2 &

§7.5.4.2.2].

3. Accessible means of egress will be continuous from each accessible occupied area to a public way or area of refuge [LSC §7.5.4.3].

Occupancy Exit Access Travel

Distance (ft)

Common Path of

Travel Limit (ft)

Dead-end Corridor

Limit (ft)

Storage 400 100 100

4. The Storage Facility is classified as a one-story Storage Occupancy; therefore, the accessible means of egress will consist of the following component:

a. First Floor

i. Fully sprinklered floor

ii. Access to the public way

Exit Discharge

1. All exits will discharge directly to the outside [LSC §7.7.1].

Egress Doors

1. Doors serving as part of the means of egress are required to comply with LSC Section 7.2.1. Door openings in means of egress are required to be not less than 32-in clear width [LSC §7.2.1.2.3].

Where a pair of doors is provided, not less than one of the doors is required to provide at least a

32-in clear width.

2. Doors in the means of egress are generally required to be of the side-hinged or pivoted-swinging type [LSC §7.2.1.4].

3. Where serving a room or area with an occupant load of 50 or more, doors are required to swing in the direction of egress travel [LSC §7.2.1.4.2].

4. Doors shall be arranged to be opened readily from the egress side whenever the building is occupied. Locks, if provided, shall not require the use of a key, a tool, or special knowledge or effort for operation from the egress side [LSC §7.2.1.5].

5. Access-controlled egress doors (e.g., equipped with card readers) must comply with LSC Section

7.2.1.6.2. The LSC requirements do not practically permit egress in two directions through doors equipped with access-control hardware.

Automatic Suppression Systems

1. Section 4-48.2.1 of UFC-3-600-01 requires automatic sprinkler protection in warehouses and storage facilities, regardless of floor area or construction type. As such, sprinkler protection is required throughout the facility. The sprinkler system must meet the requirements of UFC 3-

600-01, UFC 4-440-01, and NFPA 13.

2. All sprinkler system piping must be installed in compliance with UFC 3-600-01 Section 9-7.6. Pipe

2-in and less in diameter must be minimum Schedule 40. Pipe larger than 2-in in diameter must be minimum Schedule 10 [UFC 3-600-01 §9-7.6.2]

3. The incoming sprinkler service will be provided with a reduced pressure backflow prevention assembly.

4. Quick response sprinklers will be provided throughout. Upright sprinklers will be provided in rooms without finished ceilings. Recessed sprinklers will be provided in rooms with finished ceilings. All sprinklers will have ordinary temperature ratings unless more stringent requirements apply.

5. Fire department connections shall follow the requirements in NFPA 13 Section 16.12.3. Fire department connections shall consist of one 5-in Storz connection. Fire department connections for sprinkler systems will be provided within 150-ft of fire hydrants.

6. Per UFC 3-600-01 Section 4-48.2.3 sprinkler systems for warehouses shall be provided per NFPA

13. Design requirements for these configurations are contained in Table 3.10. The remaining areas of the building will be classified as either Light or Ordinary Hazard.

Table 3.10: Sprinkler System Storage Design Criteria

Room

Description

NFPA 13 Code

Reference Storage Description Design Criteria

Warehouse

(ST)

Table

21.4.1.2.1.1(a)

Class IV Commodities

High Temp. Sprinklers

Single- & Double-Row Racks up to 14’

0.30-gpm/sf over 2,000-sf

500-gpm hose stream

120-min

7. Preliminary hydraulic calculations are based on the most hydraulic demanding area – single- & double-row rack storage of Class IV Commodities with a storage height of 14-ft.

Water Supply

The fire protection water supply, including fire hydrants, serving the buildings is required to comply with

UFC 3-600-01 Section 9-6.4. The water supply data from flow tests performed on August 23, 2023, is shown in Table 3.11.

Table 3.11: Summary of Water Supply Tests Measurement

Static Pressure 78-psi

Residual Pressure 70-psi

Flow 1,325-gpm

Fire Department (Emergency) Vehicle Access

1. Fire department vehicle access is required to comply with UFC 3-600-01 Section 9-1.1. All buildings greater than 5,000-sf, or more than two stories in height, are required to have at least one means of all-weather ground access to allow emergency vehicles unimpeded access to the building. The all-weather ground access is required to be paved, start from the road, and terminate no farther than 33-ft from a door from the building. Where approved by the AHJ, an engineered all-weather surface that is not paved may be provided.

2. Facilities with fire department connections for sprinkler systems must be provided with suitable all-weather ground access surface for pumper apparatus within 150-ft of such fire department connections.

3. The fire department access shall meet the dimensions for fire lanes and turnarounds contained in NFPA 1. All force protection equipment, such as bollards or gates, must not require more than one person to remove or open. Access may require fire apparatus to drive over a curb.

Any locking device controlling vehicle access must be under control of the Fire Department or

24-hr security personnel located at the facility.

Fire Hydrants

1. Fire hydrants must be provided to protect the facility. All parts of the Storage Facility must be within 350 ft of a hydrant with consideration given to accessibility and obstructions [UFC 3-600-

01 §9-3.5.8.2]. Hydrants protecting warehouses must be spaced at 300 ft intervals [UFC 3-600-

01 §9-3.5.8.4.b]. Hydrants must be installed adjacent to paved areas, accessible to fire department apparatus [UFC 3-600-01 §9-3.5.7.b].

Fire Alarm System

1. A complete, electrically supervised, addressable intelligent, manual, automatic, annunciated fire alarm system shall be provided throughout the building. This system will be installed in accordance with UFC 3-600-01 and NFPA 72.

2. The Fire Alarm Control Panel (FACP) shall be located in Bay 1.

3. Audible notification is required to be provided within all occupied spaces.

4. Clear strobes marked with the word “ALERT” will be provided. Visible notification is required as follows:

a. In normally occupied, public and common use areas (e.g. break rooms, corridors, or conference rooms).

b. In all normally unoccupied areas (such as mechanical rooms, electrical rooms, janitor rooms, storage areas, communications closets, and other similar spaces) greater than 900-sf.

c. In any normally unoccupied area where the ambient noise is loud enough to require hearing protection.

d. In all offices that are designed for, or may contain, more than four persons at any one time.

5. The fire alarm system design and installation will include initiation of the fire alarm system by actuation of any sprinkler system water-flow devices, smoke detectors, carbon monoxide detectors, or manual pull stations.

6. Smoke detection is required in HVAC ducts in accordance with NFPA 90A.

7. Carbon monoxide detection shall be required in all rooms with fuel-burning equipment [UFC 3-

600-01 §5-9.1] and in each HVAC zone served by a separate air handler [UFC 3-600-01 §5-9.2].

8. Manual fire alarm pull stations will be provided at each building exit.

9. The fire alarm system is required to interface with the lighting control system to energize all means of egress lighting controlled by occupancy sensors upon activation of the building fire alarm.

10. The system is required to be connected to a central alarm location, fire department, or alarm monitoring location [UFC 3-600-01 §5-2.1.1]. The fire reporting portion of the system shall report to the central fire alarm reporting station via a Digital Alarm Communicator Transmitter

(DACT).

11. Class B notification appliances, signaling line circuits, and initiating device circuits will be provided and installed in conduit.

12. If more than one fire protection circuit is required, a panelboard dedicated to fire protection and life safety systems will be provided [UFC 3-520-01 §3-2.7.a].

Fire Extinguishers

1. Fire extinguishers shall be provided in accordance with LSC [UFC 3-600-01 §9-17.1]. Fire extinguishers are not required in Storage occupancies [NFPA 101 §42.3.5].

Emergency Lighting & Exit Signage

1. All means of egress are required to be illuminated in accordance with LSC Section 7.8 [LSC

§42.2.8.1].

a. Exit access will include only designated aisles, corridors, and passageways leading to an exit [LSC §7.8.1.1]. Exit discharge will include only designated aisles, corridors, walkways, and passageways leading to a public way [LSC §7.8.1.1].

b. Artificial lighting is required at locations and times necessary to maintain adequate illumination [LSC §7.8.1.2.1].

c. When automatic controls are used to temporarily turn off the illumination within the means of egress, the system must comply with the criteria provided in LSC Section 7.8.1.2.2. The fire alarm system is required to interface with the lighting control system to energize all means of egress lighting controlled by occupancy sensors upon activation of the building fire alarm.

2. Emergency lighting facilities are required for the means of egress [LSC §42.2.9]. The emergency lighting system is required to provide continued illumination for a duration of not less than 90 minutes in case of emergency or primary power loss [LSC §7.9.2.1].

3. Exit signage is required for exits and exit access routes in accordance with LSC Section 7.10 and

UFC-3-600-01 Section 10-2 [LSC §42.2.10]. Signs must have lettering on an opaque background.

Internally illuminated signs must be light emitting diode (LED) type, electroluminescence (LEC), or cold cathode type. Incandescent fixtures are not permitted. Radioluminous exit signs are not permitted [UFC 3-600-01 §10-2.2].

CONCLUSION

The MRSG DST Storage Facility will comply with UFC-3-600-01 and National Fire Codes.

APPENDIX A – HYDRAULIC CALCULATIONS

Hydraulic Analysis Worksheet

MCB CL MRSG DST Storage Facility – Double-Row Rack Storage (Class IV)

1. Water Quantity:

a. Density*Design Area*1.2 = 720.0 gpm

Includes 20% overage

b. Outside Hose Stream Allowance = 500.0 gpm

c. Other = 0.0 gpm

d. Domestic Demand = 0.0 gpm

Total Water Demand (a+b+c+d) = 1220.0 gpm

2. Water Pressure:

a. End-head-pressure = 14.1 psi

[density*(area/head)/k-factor]^2

b. Elevation Loss = height *0.433 = 9.5 psi

c. Outside Friction Loss = 3.0 psi

d. Backflow Preventer = 12.0 psi

RPZ Backflow Preventer

e. Inside Friction Loss = 20.0 psi

Total Pressure (a+b+c+d+e) + 10% SF = 64.4 psi

3. Available Pressure:

Pa = Ps – (Ps-Pr)x(Qa/Qt)1.85 = 71.1 psi

Available Pressure Greater than Required Total

Telecommunications scope

UFC 3-580-01 Telecommunications Building System Design

Camp Lejeune Base Specification 27 10 00

Camp Lejeune Base Specification 33 82 00

Applicable EIA and TIA standards

Applicable UL standards

NFPA 70 National Electric Code

EXTERIOR TELECOMMUNICATIONS SYSTEMS

This facility shall be provided with new OSP infrastructure and service to include OSP copper and single mode OSP fiber. The planned cable counts are 25 pair copper and 12 strand SM FOC.

OSP cabling point of connection is existing manhole MHRR110-3-5 and the duct bank point of connection is existing manhole MHRR110-3-6. Both existing manholes are nearby on the other side of C Street. All new duct bank shall be concrete-encased.

INTERIOR TELECOMMUNICATIONS SYSTEMS

The new telecommunications service for each building shall include, but not be limited to, vertical, horizontal, and backbone distribution, copper and fiber optic backbone and distribution cabling, termination equipment, workstation outlets, racks, cable trays, cable management, patch panels, conduits, backboards, and grounding. Cable trays will be used for cable distribution throughout the building, and ladder racks will be utilized at the telecommunications cabinet. Voice and data connectivity will be provided for all workstations, floor boxes, printers, and projectors per project and user requirements. Cabling shall be CAT6 and rated for its application. All telecommunications requirements shall adhere to the applicable design criteria and base standards.

A telecommunications room is not required in this building, and an enclosed telecommunications cabinet will suffice. This facility also does not have a requirement for SIPRnet.

Appendix B – FIRE FLOW TEST

Appendix C – MECHANICAL DESIGN ANALYSIS

CAMP LEJEUNE – MRSG DST STORAGE

FACILITY

MECHANCICAL DESIGN ANALYSIS

50% SUBMITTAL

adamsb Text Box 100%

Camp Lejeune MRSG DST Storage Facility

TABLE OF CONTENTS

I. Proposed Building HVAC Loads - Inputs

a. Spaces

b. Wall

c. Window

d. Roof

e. Air Systems

f. Building

II. Baseline Building HVAC Loads – Inputs

a. Spaces

b. Wall

c. Window

d. Roof

e. Air Systems

f. Building

III. Proposed Building HVAC Loads - Outputs

a. Equipment Sizing

b. Outside Air Calculations

IV. Baseline Building HVAC Loads - Outputs

a. Equipment Sizing

b. Outside Air Calculations

V. Energy Model Inputs

a. Weather Reports

b. Electric Rate Input

c. Fuel Rate Input

VI. Proposed vs Baseline Energy Model Outputs

a. Building Simulation Report

I. Proposed Building HVAC Loads – Inputs

Space Input Data Camp Lejeune - MRSG DST Storage 11-29-2023

CRENSHAW CONSULTING ENGINEERS, INC. 04:01PM

Restroom

1. General Details:

Floor Area 82.0 ft² Avg. Ceiling Height 9.0 ft Building Weight 70.0 lb/ft²

1.1. OA Ventilation Requirements:

Space Usage User-Defined OA Requirement 1 0.0 CFM/person OA Requirement 2 0.00 CFM/ft² Space Usage Defaults ASHRAE Std 62.1-2010

2. Internals:

2.1. Overhead Lighting:

Fixture Type Recessed (Unvented) Wattage 60.0 Watts Ballast Multiplier 1.00 Schedule 90.1 Warehouse Lights/Elec

2.4. People:

Occupancy 0.0 Person Activity Level Office Work Sensible 245.0 BTU/hr/person Latent 205.0 BTU/hr/person Schedule None

2.2. Task Lighting:

Wattage 0.00 W/ft² Schedule None

2.5. Miscellaneous Loads:

Sensible 0 BTU/hr Schedule None Latent 0 BTU/hr Schedule None

2.3. Electrical Equipment:

Wattage 0.00 W/ft² Schedule None

3. Walls, Windows, Doors:

Exp. Wall Gross Area (ft²) Window 1 Qty. Window 2 Qty. Door 1 Qty.

W 90.0 0 0 0

S 90.0 0 0 1

3.1. Construction Types for Exposure W

Wall Type MRSG Wall

3.2. Construction Types for Exposure S

Wall Type MRSG Wall Door Type 2013 Zone 3 Opaque Nonswinging

4. Roofs, Skylights:

(No Roof or Skylight data).

5. Infiltration:

Design Cooling 0.00 CFM Design Heating 0.00 CFM Energy Analysis 0.00 CFM Infiltration occurs only when the fan is off.

6. Floors:

Type Floor Above Conditioned Space (No additional input required for this floor type).

7. Partitions:

(No partition data).

Hourly Analysis Program v5.11 Page 1 of 2

CRENSHAW CONSULTING ENGINEERS, INC. 04:01PM

Storage

1. General Details:

Floor Area 5440.0 ft² Avg. Ceiling Height 10.0 ft Building Weight 70.0 lb/ft²

1.1. OA Ventilation Requirements:

Space Usage MISCELLANEOUS: Warehouse OA Requirement 1 10.0 CFM/person OA Requirement 2 0.06 CFM/ft² Space Usage Defaults ASHRAE Std 62.1-2010

2. Internals:

2.1. Overhead Lighting:

Fixture Type Recessed (Unvented) Wattage 1152.0 Watts Ballast Multiplier 1.00 Schedule 90.1 Warehouse Lights/Elec

2.4. People:

Occupancy 4.0 People Activity Level Medium Work Sensible 295.0 BTU/hr/person Latent 455.0 BTU/hr/person Schedule 90.1 Warehouse Occupants

2.2. Task Lighting:

Wattage 0.00 W/ft² Schedule None

2.5. Miscellaneous Loads:

Sensible 0 BTU/hr Schedule None Latent 0 BTU/hr Schedule None

2.3. Electrical Equipment:

Wattage 0.25 W/ft² Schedule 90.1 Warehouse Lights/Elec

3. Walls, Windows, Doors:

Exp. Wall Gross Area (ft²) Window 1 Qty. Window 2 Qty. Door 1 Qty.

N 1584.0 0 0 0

S 1584.0 0 0 4

W 726.0 0 0 0

E 907.0 0 0 0

3.1. Construction Types for Exposure N

Wall Type MRSG Wall

3.2. Construction Types for Exposure S

Wall Type MRSG Wall Door Type 2013 Zone 3 Opaque Nonswinging

3.3. Construction Types for Exposure W

Wall Type MRSG Wall

3.4. Construction Types for Exposure E

Wall Type MRSG Wall

4. Roofs, Skylights:

(No Roof or Skylight data).

5. Infiltration:

Design Cooling 0.00 CFM Design Heating 0.00 CFM Energy Analysis 0.00 CFM Infiltration occurs only when the fan is off.

6. Floors:

Type Floor Above Conditioned Space (No additional input required for this floor type).

7. Partitions:

Hourly Analysis Program v5.11 Page 2 of 2

Wall Constructions

CRENSHAW CONSULTING ENGINEERS, INC. 04:01PM

MRSG Wall

Wall Details Outside Surface Color Medium Absorptivity 0.675 Overall U-Value 0.046 BTU/(hr·ft²·°F)

Wall Layers Details (Inside to Outside)

Thickness Density Specific Ht. R-Value Weight

Layers in lb/ft³ BTU / (lb·°F) (hr·ft²·°F)/BTU lb/ft²

Inside surface resistance 0.000 0.0 0.00 0.68500 0.0

6" STEEL STUDS 6.000 490.0 0.12 1.75000 245.0

3" Rigid Insulation 3.000 2.0 0.22 18.60000 0.5

4-in face brick 4.000 125.0 0.22 0.43290 41.7

Outside surface resistance 0.000 0.0 0.00 0.33300 0.0

Totals 13.000 - 21.80090 287.2

Hourly Analysis Program v5.11 Page 1 of 1

Window Constructions Camp Lejeune - BEQ HP505 11-06-2023

CRENSHAW CONSULTING ENGINEERS, INC. 04:45PM

HP514 - 4'

Window Details:

Detailed Input No

Height 4.00 ft Width 1.00 ft Overall U-Value 0.400 BTU/(hr·ft²·°F) Overall Shade Coefficient 0.400

Roof Constructions

CRENSHAW CONSULTING ENGINEERS, INC. 04:02PM

2013 Zone 2-3 Insulation Entirely Above Deck

Roof Details Outside Surface Color Medium Absorptivity 0.675 Overall U-Value 0.039 BTU/(hr·ft²·°F)

Roof Layers Details (Inside to Outside)

Thickness Density Specific Ht. R-Value Weight

Layers in lb/ft³ BTU / (lb·°F) (hr·ft²·°F)/BTU lb/ft²

Inside surface resistance 0.000 0.0 0.00 0.61000 0.0

22 gage steel deck 0.034 489.0 0.12 0.00011 1.4

Board Insulation 2.900 2.0 0.22 25.00000 0.5

Outside surface resistance 0.000 0.0 0.00 0.17000 0.0

Totals 2.934 - 25.78011 1.9

[P] AHU Input Data Project Name: Camp Lejeune - MRSG DST Storage 11-29-2023 Prepared by: CRENSHAW CONSULTING ENGINEERS, INC. 04:02PM

1. General Details:

Air System Name [P] AHU Equipment Type Split AHU Air System Type Single Zone CAV Number of zones 1

2. Ventilation System Components:

Ventilation Air Data:

Airflow Control Constant Ventilation Airflow Ventilation Sizing Method ASHRAE Std 62.1-2010 Unocc. Damper Position Closed Damper Leak Rate 0 % Outdoor Air CO2 Level 400 ppm

Central Cooling Data:

Supply Air Temperature 58.0 °F Coil Bypass Factor 0.100 Cooling…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .