About this file

This document is an Amendment (Amendment 0007) to Solicitation N4008525R2513 for the Repair of 3rd Battalion Pond Causeway at Marine Corps Recruit Depot (MCRD) Parris Island, South Carolina. The amendment extends the solicitation response date from 14 April 2025 to 21 April 2025, both at 2:00 PM EDT, and provides responses to pre-proposal inquiries from potential offerors.

Key changes include revising solicitation provisions and clauses per updated Federal Acquisition Regulation (FAR) guidelines, addressing technical questions about utility relocation, environmental assessments, dewatering procedures, concrete testing, and various site-specific construction details. The amendment provides contact information for utility owners like Dominion Energy, clarifies permit responsibilities, and offers additional context on site conditions such as potential soil contamination, groundwater sampling, and specific construction requirements for roadway rehabilitation, culvert replacement, and utility infrastructure work.

View the file

Other files

File Type Posted
N4008525R2513 AMD 0014.pdf PDF
Attachment C - Price Proposal Form REV2.docx DOCX document
N4008525R2513 AMD 0013.pdf PDF
N4008525R2513 AMD 0012.pdf PDF
N4008525R2513 AMD 0011.pdf PDF
N4008525R2513 AMD 0010.pdf PDF
N4008525R2513 AMD 0009.pdf PDF
Attachment C - Price Proposal Form REVISED.docx DOCX document
Attachment C - Price Proposal Form REVISED.docx DOCX document
N4008525R2513 AMD 0009.pdf PDF
N4008525R2513 AMD 008.pdf PDF
N4008525R2513 AMD 0006.pdf PDF
N4008525R2513 AMD 0005.pdf PDF
N4008525R2513 AMD 0004.pdf PDF
N4008525R2513 AMD 0003.pdf PDF
PI2045M SITE VISIT SIGN IN SHEET.PDF PDF
Attachment D - Construction Experience Data Sheet.docx DOCX document
Attachment F - Historical Small Business Utilization.docx DOCX document
Attachment G - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
N4008525R2513 AMD 0002.pdf PDF
N4008525R2513 AMD 0001.pdf PDF
1669917spc_attachments (4 of 4).pdf PDF
1669917spc_attachments (3 of 4).pdf PDF
1669917spc_attachments (1 of 4).pdf PDF
1669917spc_attachments (2 of 4).pdf PDF
Attachment G - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment E - Past Performance Questionnaire (PPQ).docx DOCX document
1669917dwg01of01_COMBINED_REDUCED SCDES Stamped.pdf PDF
N4008525R2513.pdf PDF
Attachment C - Price Proposal Form.docx DOCX document
Attachment D - Construction Experience Data Sheet.docx DOCX document
Attachment H - Small Business Subcontracting Plan.docx DOCX document
1669917spc01of01.pdf PDF
Attachment F - Historical Small Business Utilization.docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation No.: N4008525R2513 - PI2045M Repair of 3rd Battalion Pond Causew ay, MCRD, Parris Island, SC

The Solicitation Reponse Date has been extended from 14 April 2025 @ 2:00PM EDT to 21 April 2025 @ 2:00PM EDT

See Continuation Page(s)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 11

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Apr-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008525R2513

X 9B. DATED (SEE ITEM 11)

14-Feb-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Apr-2025

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008525R2513

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0007

The purpose of this amendment is to:

1. Extend the proposal due date from 14 April 2025 @ 2:00PM EDT to 21 April 2025 @ 2:00PM EDT

2. Revise solicitation provisions and clauses per updated FAR guidelines

3. Provide responses to pre-proposal inquiries

Reference Question Response

Page Section Para VU101 3.1.3 - Utility

Relocation and Restoration

Note 3.1.1-3 Notes "Secure new above ground steel poles to the foundation" Please confirm the steel poles are to be provided by DESC. If not please provide additional information on the steel poles.

Please see drawings and specs for scope of work to be performed by Utility Owners. Contractor is responsible for costs to Utility Owners for relocation.

Utility Owners can be contacted directly for costs associated with relocation.”

Final Design Submittal

On Page 6 of the Final Design Submittal Specifications, attachments are listed. Please provide the Interim Remedial Action Work Plan Site 3 Solid Waste Managment Unit 3 (SWMU 3) Causeway Landfill MCRD Parris Island SC Dated 8/1/2000 and the Interim Remedial Action Corrective Action Report Site 3 Solid Waste Managment Unit 3 (SWMU 3) Causeway Landfill MCRD Parris Island SC Dated 6/1/2002.

The requested reports are included as Attachments to the specification package.

Enviornmental Assessment

The environmental assessment indicates soil contaminations and provides PAH and metals as the soil constituents of concern. Is the soil above residential or commercial regional screening levels?

Yes, however the extent of this question differs based on the exposure scenarios you are intending to compare agains. The major concern is the waste that remains in place at the site beneath the clean cap installed across over the old landfill area.

The soil concentrations are provided in the Attachments to the specifications (see response to the PPI above).

Enviornmental Assessment

The Environmental Assessment indicates existing monitoring wells onsite. Could you please provide the data on what the current ground water concentrains are?

The ERP samples the groundwater every five years in support of the Remedial Action. The most recent report I can locate is dated 12/2021 (publically available document) with limited analysis conducted on the groundwater.

26 Bid Guarantee B Should the Offeror FedEx the Bid Bond to the Contracting Office prior to bid opening date? Or, only include the Bid Bond as a PDF in the bid proposal package?

Include with bid proposal package

1 13 A Please consider at least a 2-week extension to the proposal due date due to the complexity of the project.

Extended per AMD 0007

Please indicate the location of the vertical and horizontal concrete test sections.

Per 03 31 30 section 1.8.6.7, near the job site (bridge location) but not as part of the structure.

Please provide the dimensions of the vertical concrete test section.

Testing is not needed.

S-008 Reference S-008 Elevation North Bridge Wall 1. Note states that the riprap on the marsh side is 13'-00" thick while the same note for Elevation North Wall 2 states that the riprap on the marsh side is 3'-00 thick. We believe the 13'-00" reference is incorrect and should read 3'-00". Please confirm and/or correct.

S-008 Elevation - North Bridge Wall 1 callout states: "MARSH SIDE RIPRAP (3'-0" THICK)". Please enlarge your view of the .pdf file to see the "(" is not a "1".

S-008 and S-

Reference S-008 and S-014. It is our interpretation that the concrete fascia wall for the bridge wing walls should be 4"0 below the bottom of the rip-rap as called out on S-027. Please confirm and/or clarify.

As shown on S-027 "Combi-wall Typical Section", the concrete fascia should extend 3'-0" minimum below bottom of channel slab or bottom of riprap.

S-028, Section D

Reference S-028 Section D. Section D shows the bottom of the fascia wall to be 3'0 below the bottom of the riprap while the note under Section D Weir Reinforcing indicates the bottom of the fascia wall to be 4'0 below riprap. It is our interpretation that the 3'0 call out is correct. Please confirm and/or clarify.

3'-0" minimum depth below riprap or below channel slab for the weir concrete fascia is correct. The note under Section D Weir Reinforcing should be change from 4'-0" to 3'-0"

Work Plan Pg. 15-16

5.3.1 1 Will dewatering effluent be permitted to be discharged into the adjacent creek? If not, what are the disposal requirements? Corresponding spec sections seem to apply only to solid waste.

See Section 4.4 of Waste Management Plan, which was included as Appendix A of the Final Construction Work Plan (dated May 30, 2024). Sampling of water within the cofferdam at each culvert is required, in accordance with Contractor's sequence of work, to determine appropriate handing of dewatering effluent.

Please note - depending on the sequence of construction (and means and methods of construction), the groundwater is considered solid waste and must be treated as such.

N/A What permits are required and who is responsible for obtaining them?

The official lists of permits and approvals is based on means and methods selected by the construction contractor. A list of anticipated permits (although this is subject to change depending on means and methods) and several permits/approvals that have been secured by the A/E and Marine Corps are included as Attachments to the specifications. It is the construction contractors responsbility to identify all required permits required in accordance with the means and methods selected by the contractor and obtain final approvals of these permits, Work Plan approvals, and G submittals.

In terms of the dewatering disposal, is there an anticipated flow rate for treatment? Please provide treatment requirements for contaminated (non-hazardous) and hazardous effluent.

Flow rate is dependent on means and methods and the quality of construction.

NAVFAC cannot anticipate a flow rate.

Please provide the latest analysis of raw water from the ponds and Ribbon Creek.

NAVFAC does not have access to raw water data within the ponds and Ribbon Creek. You may be able to pull publically available information from a State or Federal entity.

VU101 3.1.3 - Utility Relocation and Restoration

Please clearly define the scope of work that is to be performed by utility owners - Dominion Energy, MCRD Parris Island, Brightspeed, Hargray, and MCRD Parris Island G6. Please confirm the Contractor will not

See specification 33 71 00, paragraph 1.2.

Please see drawings and specs for scope of work to be performed by Utility be responsible for any cost provided to the Utility Owners for relocation.

Owners. Contractor is responsible for costs to Utility Owners for relocation.

Utility Owners can be contacted directly for costs associated with relocation.

VU101 3.1.3 - Utility Relocation and Restoration

Please provide a Dominion Energy Contact, previously provided contact information is not correct.

Larki Robinson larki.robinson@dominionenergy.com

(O) 803-217-9220 : (M) 803-351-5004

Paul S. Matthews Office: 757-857-2851 Cell: 757-681-5826 paul.matthews@dominionenergy.com

Jordan Wood, C.E.M.

jordan.a.wood@dominionenergy.com O: 757-857-2950 C: 757-738-4681

Attachment C

Please confirm how the undercut of unsuitable pavement subgrade (option #4) quantity will be determined for payment.

THE QUANTITY WILL BE

DETERMINED BASED ON FIELD

MEASUREMENT BY THE

GOVERNMENT GEOTECHNICAL

ENGINEER AS INDICATED IN THE

PRICE SCHEDULE.

Cross Section Drawings

Due to the existing environmental conditions and potential contaminants further down in the sub-base layers, specifications indicate that there is no excavation below 12" without the written consent of the contracting officer. Does that include the areas where the proposed 12" cement stabilized base is lower than the existing pavement depth?

DESC – Key Acct Manager

Environmetal Assessment

Please provide the most recent analysis for RCRA characterization to determine disposal methods.

Specifically looking for the TCLP metals, total volatiles and total semi-volatiles.

All existing data that is available has been provided in other PPIs.

CP101-104 What size electric line is to be installed? larki.robinson@dominionenergy.com;

(O) 803-217-9220 : (M) 803-351-5004

CP101-104 Is the electric high voltage or low voltage? See specification 33 71 00, paragraph 1.2.

CP101-104 What size communications fiber needs to be installed? See specification 33 71 00, paragraph 1.2.

11 01 14 00 1.3.4 Section 01 14 00 Work Restrictions 1.3.4 lists "waterflow may be cutoff between October 1 through April 30". Section 01 57 19 Flow Ways 3.1.1 states "culvert locations may be closed between October 1 and May 30. Which is the correct closure date range?

Section 01 14 00 Work Restrictions 1.3.4 should be revised to match Section 01 57 19 Floways 3.1.1.

CS 201-CS

Roadway Profiles and Cross Sections show areas where proposed road elevations are lower than current elevations. No excavation is allowed below the 12" pulverized cement-stabilized base course and the 2' soil cap is to remain undisturbed. Multiple cross sections show excavation areas to achieve the Full Depth Reclamation Detail of 12" recycled base plus 4" hot mix asphalt. In these excavation areas will the contractor be expected to over excavate these areas, dispose of trash, and then reinstall cap to maintain the 2' of cap material?

Or would this be done using the Potential Subgrade Repair detail A2 using geogrid and 12" aggregate base?

For these areas the expectation is for the contractor to use Detail A2 - Potential Subgrade Repair Detail.

Work Plan,

pg. 15-16

Dewatering effluent may be contaminated and may require hauling off if testing shows contamination. Can the Government provide a contaminated effluent quantity for bid purposes?

Flow rate is dependent on means and methods and the quality of construction.

NAVFAC cannot anticipate a volume.

Work Plan,

pg. 15-16

If dewatering effluent tests within allowable contamination limits, will it be permitted to be discharged into the adjacent marsh/creek? If not, what are the disposal requirements? Corresponding spec sections seem to apply only to solid waste.

Solid waste can be a liquid under RCRA.

Bid per the specification requirements.

N/A Will asphalt paving material pricing be adjusted per SCDOT index?

No.

N/A What permits are required and who will obtain them? Is the contractor required to obtain any permits?

The official lists of permits and approvals is based on means and methods selected by the construction contractor. A list of anticipated permits (although this is subject to change depending on means and methods) and several permits/approvals that have been secured by the A/E and Marine Corps are included as Attachments to the specifications. It is the construction contractors responsbility to identify all required permits required in accordance with the means and methods selected by the contractor and obtain final approvals of these permits, Work Plan approvals, and G submittals.

Work Plan,

pg. 11

3.3 Work Plan lists applicable permits. Have all of these

permits already been obtained?

The official lists of permits and approvals is based on means and methods selected by the construction contractor. A list of anticipated permits (although this is subject to change depending on means and methods) and several permits/approvals that have been secured by the A/E and Marine Corps are included as Attachments to the specifications. It is the construction contractors responsbility to identify all required permits required in accordance with the means and methods selected by the contractor and obtain final approvals of these permits, Work Plan approvals, and G submittals.

N/A Is the Construction Work Plan part of the Contract Documents or for reference only?

Yes the Construciton Work Plan is part of the Contract Documents.

S005 If mucking of existing earthen material below the concrete weir is required, how will this be measured and paid?

For sheet S-003 and S-009: base bids on undercutting existing subgrade soils for the entire headwall footing subgrade area to a depth of 3 feet and backfilling with #3 crushed stone. The base bid volume of undercut excavation must be 2(40'X10'X3')/27=90 cubic yards.

Disposal cost will be covered in CLIN 1G.

743 31 41 16 1.3.2 If the king piles or sheet piles are required to be driven to tip elevations below the plan dimensions, how will this be measured and paid?

Bid As Specified.

Please provide a list of permits that are the responsibility of the contractor.

The official lists of permits and approvals is based on means and methods selected by the construction contractor. A list of anticipated permits (although this is subject to change depending on means and methods) and several permits/approvals that have been secured by the A/E and Marine Corps are included as Attachments to the specifications. It is the construction contractors responsbility to identify all required permits required in accordance with the means and methods selected by the contractor and obtain final approvals of these permits, Work Plan approvals, and G submittals.

Please provide a list of permits that are the responsibility of the government.

The official lists of permits and approvals is based on means and methods selected by the construction contractor. A list of anticipated permits (although this is subject to change depending on means and methods) and several permits/approvals that have been secured by the A/E and Marine Corps are included as Attachments to the specifications. It is the construction contractors responsbility to identify all required permits required in accordance with the means and methods selected by the contractor and obtain final approvals of these permits, Work Plan approvals, and G submittals.

Caissons for Dominion Steel Poles – Who provides/performs this work?

See specification 33 71 00 paragraph 1.2.

Dominion Energy is responsible for all design and constrution owned and operated by Dominion Energy.

Steel Poles – What height/dimensions? Who provides/installs?

See specification 33 71 00 paragraph 1.2.

Dominion Energy is responsible for all design and constrution owned and operated by Dominion Energy.

Anchor bolts would be needed in caissons for the steel poles. How is this coordinated if work divided up?

See specification 33 71 00 paragraph 1.2.

Dominion Energy is responsible for all design and constrution owned and operated by Dominion Energy.

High voltage cable (46kV/69kV) is not readily available in these temporary quantities. Will Dominion provide this cable?

See specification 33 71 00 paragraph 1.2.

Dominion Energy is responsible for all design and constrution owned and operated by Dominion Energy.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 14-Apr-2025 02:00 PM to 21-Apr-2025 02:00 PM.

SECTION 00 21 00 - INSTRUCTIONS

The following have been deleted:

52.222-23 Notice of Requirement for Affirmative Action to Ensure

Equal Employment Opportunity for Construction

FEB 1999

SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS

52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEVIATION 2025-O0003/ DEVIATION

2025-O0004) (MAR 2025)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237310.

(2) The small business size standard is $45,000,000.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition--

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph

(d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] Paragraph (d) applies.

[ ] Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) (1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services--Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.

(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(xiv) [Reserved]

(xv) [Reserved]

(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of biobased products in USDA-designated product categories; or include the clause at 52.223-2, Reporting of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA- designated items.

(xix) [Reserved]

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate. (Basic, Alternates II and III.)

This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $50,000, the basic provision applies.

(B) If the acquisition value is $50,000 or more but is less than $100,000, the provision with its Alternate II applies.

(C) If the acquisition value is $100,000 or more but is less than $102,280, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran—Representation and Certification. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

X (i) 52.204-17, Ownership or Control of Offeror.

X (ii) 52.204-20, Predecessor of Offeror.

(iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

(iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.

(v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Certification.

(vi) 52.227-6, Royalty Information.

(A) Basic.

(B) Alternate I.

(vii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https://www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [ offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of provision)

52.204-8 Annual Representations and Certifications JAN 2025 52.222-22 Previous Contracts And Compliance Reports FEB 1999 52.222-25 Affirmative Action Compliance APR 1984

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been added by reference:

52.222-9 (Dev) Apprentices and Trainees (DEVIATION 2025-O0003) MAR 2025 52.223-23 (Dev) Sustainable Products and Services (DEVIATION 2025-

O0004)

MAR 2025

52.244-6 (Dev) Subcontracts for Commercial Products and Commercial Services (DEVIATION 2025-O0003)

MAR 2025

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least (15%) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of clause)

52.222-9 Apprentices and Trainees JUL 2005 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.223-23 Sustainable Products and Services. MAY 2024 52.244-6 Subcontracts for Commercial Products and Commercial

Services

NOV 2024

(End of Summary of Changes)

File details come from the government source that posted it. Updated .