The file is a Price Schedule Form for the Naval Facilities Engineering Command's PI2045M Parris Island 3rd Battalion Pond Causeway Repair project. The document provides a detailed pricing structure with multiple line items covering base work and optional services, including base price for the entire project (Line Item 0001), and seven additional optional line items. The base work involves repairing a 4,500-foot causeway at Marine Corps Recruit Depot Parris Island, which includes roadway rehabilitation, power line and communication line relocations, material excavation and disposal, and natural resource monitoring.
Optional line items include deploying temporary pumps and generators, handling and disposing of potentially contaminated or hazardous materials, undercut and repair of unsuitable pavement subgrade, periodic water seepage sampling, and handling/disposal of construction dewatering effluent. The pricing is structured with unit prices for specific quantities, with provisions for potential adjustments if actual quantities vary significantly from estimated amounts. The contract will be a Fixed Price Construction Contract using a Design-Bid-Build approach, with unit prices valid for 365 days from the notice to proceed. The government will evaluate offers by adding option prices to the base price, though option exercise is not guaranteed.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRICE SCHEDULE
Provide line item prices, where indicated by blank underlines, for the following items:
| Line Item |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Sub-Total |
| Total Price |
| Line Item 0001 |
| BASE PRICE: Total Price for the entire work for REPAIR 3RD BATTALION POND CAUSEWAY, MCRD PARRIS ISLAND, SC, complete, in accordance with the drawings and specifications (sum of Items 1A, 1B, 1C, 1D, 1E, 1F, 1G, 1H, and 1I). |
| 1 |
| EA |
| Line Item 001A |
| Subtotal of Base Price for the entire project work in accordance with the drawings and specifications, complete, but excluding work in Line Items 1B, 1C, 1D, 1E, 1F, 1G, 1H, and 1I. |
| 1 |
| EA |
| Line Item 001B |
| Price and subtotal of Base Price for coordination, design, materials, labor and equipment associated with temporary relocation and permanent overhead restoration of overhead power transmission lines owned by Dominion Energy South Carolina, complete, in accordance with the drawings and specifications. |
| 1 |
| LS |
| Line Item 001C |
| Price and subtotal of Base Price for coordination, design, materials, labor and equipment associated with temporary relocation and permanent overhead restoration of overhead power lines owned by MCRD Parris Island, complete, in accordance with the drawings and specifications. |
| 1 |
| LS |
| Line Item 001D |
| Price and subtotal of Base Price for coordination, design, materials, labor and equipment associated with temporary relocation and permanent restoration of two underground communication lines owned by MCRD Parris Island, complete, in accordance with the drawings and specifications. |
| 1 |
| LS |
| Line Item 001E |
| Price and subtotal of Base Price for coordination, design, materials, labor and equipment associated with temporary relocation and permanent restoration of the underground communication line owned by Hargray Communications, complete, in accordance with the drawings and specifications. |
| 1 |
| LS |
| Line Item 001F |
| Price and subtotal of Base Price for coordination, design, materials, labor and equipment associated with temporary relocation and permanent restoration of the underground communication line owned by Brightspeed, complete, in accordance with the drawings and specifications. |
| 1 |
| LS |
| Line Item 001G |
| Unit Price and subtotal of Base Price for the entire work of excavation, handling, temporary storage in covered roll-off dumpsters, sampling, analysis, hauling, and disposal of surplus material removed from planned excavations, complete, in accordance with the drawings and specifications. Unit Price assumes material is contaminated, non-hazardous, and disposed at a licensed and permitted RCRA Subtitle D disposal facility. |
| 10,000 |
| TONS(1) |
| Line Item 001H |
| Price and Subtotal of Base Price for the entire work of natural resource monitoring, including monitoring, sampling, analysis and reporting of dissolved oxygen and other constituents within the water in the 3rd Battalion Pond during period of construction when flow of water to the pond is cut off in both culverts, complete, in accordance with the drawings and specifications. |
| 1 |
| EA |
| Line Item 001I |
| Unit Price and subtotal of Base Price for the entire work of additional demolition, excavation, hauling and disposal of buried concrete and debris greater than 1 cubic yard in size encountered within planned excavation limits and not identified in the drawings, complete, in accordance with the drawings and specifications. Pieces of buried concrete and debris encountered within planned excavation limits and smaller than 1 cubic yard in size are considered to be incidental to the work and are excluded. |
| 250 |
| TONS(1) |
| $_____ |
| $______ |
| Line Item 0002 |
| OPTION No. 2 Unit Price for providing all work in connection with deployment and operation of temporary pumps and generators to transfer fresh saltwater from Ribbon Creek to the pond in order to maintain dissolved oxygen requirements or the pond surface elevation minimum requirement, complete, in accordance with drawings and specifications. |
| 5 |
| MO |
| $_______ |
| Line Item 0003 |
| OPTION No. 3 Unit Price for the entire work of excavation, handling, temporary storage in covered roll-off dumpsters, sampling, analysis, hauling, and disposal of material removed from planned excavations that is characterized as hazardous waste. Unit Price is for all work in connection with disposing of material at a licensed and permitted RCRA Subtitle C disposal facility. |
| 950 |
| TONS(1) |
| $_____ |
| Line Item 0004 |
| OPTION No. 4 Unit Price for undercut of geotechnically unsuitable pavement subgrade not identified in the drawings, and repairing the areas using geogrid and imported graded aggregate base course in accordance with the drawings and specifications. |
| 1,500 |
| CY |
| $______ |
Line Item 0004 Criteria For Bidding: Undercut and replacement of geotechnically unsuitable subgrade: Unit Price includes excavation, handling, hauling, temporary storage, sampling, analysis and disposal of excavated material and assumes material is contaminated, non-hazardous, and disposed at a licensed and permitted RCRA Subtitle D disposal facility. Unsuitable subgrade determinations will be confirmed by the Government Geotechnical Engineer. Unsuitable soil determinations will be confirmed by the Government Geotechnical Engineer and approved by the Contracting Officer. The price shall include removal of geotechnically unsuitable soils encountered at planned subgrade elevations within planned excavation limits after proper completion of work specified, and backfilling the excavation with compacted imported select material. Soils disturbed by Contractor's construction activities, or that are excessively wet or soft due to lack of proper site maintenance, lack of proper site drainage, or lack of proper dewatering, will not be considered unsuitable. The volume of material removed and imported backfill required shall be determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable soil, and approved by the Contracting Officer.
| Line Item 0005 |
| OPTION No. 5 Unit for periodic sampling and analysis of water seepage that occurs within the confines of the cofferdam areas during construction. |
| 24 |
| EA |
| $______ |
| Line Item 0006 |
| OPTION No. 6 Unit price for handling, containerizing, hauling and offsite treatment and disposal of contaminated non-hazardous construction dewatering effluent. |
| 300,000 |
| GAL(2) |
| $_____ |
Line Item 0006 Criteria For Bidding: Unit price includes all sampling and testing required per Specification Section 01 57 19 and must include any other sampling and analytical testing required by the Contractor’s selected treatment/disposal facility. The determination of any non-hazardous construction dewatering effluent will be made by the KO in conjunction with NAVFAC Environmental representatives. The volume of liquid removed must be based on approved certified pump measurement(s) at the disposal facility and written pump measurement documentation and waste manifests must be provided to the Government in accordance with the requirements of the Contract Documents.
| Line Item 0007 |
| OPTION No. 7 Unit price for handling, containerizing, hauling and offsite treatment and disposal of contaminated hazardous construction dewatering effluent. |
| 10,000 |
| GAL(2) |
| $______ |
Line Item 0007 Criteria For Bidding: Unit price includes all sampling and testing required per Specification Section 01 57 19 and must include any other sampling and analytical testing required by the Contractor’s selected treatment/disposal facility. The determination of any contaminated hazardous construction dewatering effluent will be made by the KO in conjunction with NAVFAC Environmental representatives. The volume of liquid removed must be based on approved certified pump measurement(s) at the disposal facility and written pump measurement documentation and waste manifests must be provided to the Government in accordance with the requirements of the Contract Documents.
PRICE SCHEDULE NOTES:
1. The volume of material removed will be determined based on certified truck scale measurement (tons) of material disposed at the receiving facility. Written truck scale measurement documentation and waste manifests must be provided to the Government in accordance with the requirements of the Contract Documents.
2. Unit Price includes all sampling and analytical testing required by the Contractor’s selected disposal facility and must include TPH DRO/GRO and full TCLP Suite as a minimum. The volume of construction dewatering effluent disposed of must be based on approved certified pump measurement(s) at the disposal facility and written pump measurement documentation and waste manifests must be provided to the Government in accordance with the requirements of the Contract Documents.
3. Unit prices for Line Items 0002-0007 shall be good for 365 days from notice to proceed.
GENERAL BID NOTES
a. Award will be made on the price proposed for Base Work and all Options. For line items 1G-1I and 0002-0007 enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
b. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) 0002-0007 to the total price for Line Item 1A. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).
c. In accordance with FAR 52.217-7; Option for Increased Quantity-Separately Priced Line Item (Mar 1989), the Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
d. In accordance with FAR 52.211-18; If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
e. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
f. Failure to enter a price for any line item number will result in a proposal being rejected.
File details come from the government source that posted it. Updated .