N4008525R2513 AMD 0004.pdf

PDF 146 KB Posted

Attached to
PI2045M Parris Island 3rd Battalion Pond Causeway Repair
Solicitation number
N4008525R2513
Issued by

About this file

This document is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for the Repair of 3rd Battalion Pond Causeway at Marine Corps Recruit Depot, Parris Island, SC. Amendment 0004, dated 19-Mar-2025, provides responses to pre-proposal inquiries covering technical details such as king pile tip elevations, handling of gabion and rip rap stone materials, utility relocation procedures, and contact information for utility companies. Key clarifications include specifying king pile tip elevations at -46 and -47 feet, guidance on reusing or recycling stone materials, contractor responsibilities for coordinating power outages, and providing utility company contact details. The solicitation response date remains unchanged at 31 March 2025 NLT 2:00PM EDT, and the amendment maintains the original solicitation requirements for corporate experience, emphasizing that only prime contractor experience will be considered.

View the file

Other files

File Type Posted
N4008525R2513 AMD 0014.pdf PDF
Attachment C - Price Proposal Form REV2.docx DOCX document
N4008525R2513 AMD 0013.pdf PDF
N4008525R2513 AMD 0012.pdf PDF
N4008525R2513 AMD 0011.pdf PDF
N4008525R2513 AMD 0010.pdf PDF
N4008525R2513 AMD 0009.pdf PDF
Attachment C - Price Proposal Form REVISED.docx DOCX document
Attachment C - Price Proposal Form REVISED.docx DOCX document
N4008525R2513 AMD 0009.pdf PDF
N4008525R2513 AMD 008.pdf PDF
N4008525R2513 AMD 0007.pdf PDF
N4008525R2513 AMD 0006.pdf PDF
N4008525R2513 AMD 0005.pdf PDF
N4008525R2513 AMD 0003.pdf PDF
PI2045M SITE VISIT SIGN IN SHEET.PDF PDF
Attachment D - Construction Experience Data Sheet.docx DOCX document
Attachment F - Historical Small Business Utilization.docx DOCX document
Attachment G - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
N4008525R2513 AMD 0002.pdf PDF
N4008525R2513 AMD 0001.pdf PDF
1669917spc_attachments (4 of 4).pdf PDF
1669917spc_attachments (3 of 4).pdf PDF
1669917spc_attachments (1 of 4).pdf PDF
1669917spc_attachments (2 of 4).pdf PDF
Attachment G - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment E - Past Performance Questionnaire (PPQ).docx DOCX document
1669917dwg01of01_COMBINED_REDUCED SCDES Stamped.pdf PDF
N4008525R2513.pdf PDF
Attachment C - Price Proposal Form.docx DOCX document
Attachment D - Construction Experience Data Sheet.docx DOCX document
Attachment H - Small Business Subcontracting Plan.docx DOCX document
1669917spc01of01.pdf PDF
Attachment F - Historical Small Business Utilization.docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation No.: N4008525R2513 - PI2045M Repair of 3rd Battalion Pond Causew ay, MCRD, Parris Island, SC

Solicitation Response Date: 31 March 2025 NLT 2:00PM EDT remains unchanged

See Continuation Page(s)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Mar-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008525R2513

X 9B. DATED (SEE ITEM 11)

14-Feb-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Mar-2025

CODE

NAVFACSYSCOM MID-ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008525R2513

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0004

The purpose of this amendment is to

1. Provide responses to pre-proposal inquiries Reference

Question Response Page Section Para

Drawin g S-015

The tables North & South Bridge Bent Notes provides load requirements for the king pile but does not provide a tip elevation for the pile. Please provide a tip elevation for the king pile. If no tip elevation is provided, please provide a unit price item for king pile by the LF.

Per paragraph 3.3.1.2 in Section 31 41 16 (Steel Combination Pile Bulkheads) of the Specifications, tip elevation for the king piles at the North and South bridge is equal to -46 feet and -47 feet, respectively.

02 61 13

This section discusses the procedure for handling the excavation of contaminated material, The drawings show gabions is to be removed and disposed. How should the gabions be handled? Since gabions consist of medium sized stone contained in wire cages, what testing and disposal method is required?

Gabion stone material does not require testing for offsite disposal. If possible, please reuse to the extent practicable vs offsite disposal. If offsite disposal is required, please recycle the gabion stone material for reuse.

02 61 13

This section discusses the procedure for handling the excavation of contaminated material, The drawings show rip rap is to be removed and disposed. Since the rip rap consist of large stones, how should the rip rap be handled? What testing and disposal method is required?

Rip Rap stone material does not require testing for offsite disposal. If possible, please reuse to the extent practicable vs offsite disposal. If offsite disposal is required, please recycle the rip rap for reuse.

VU101

Temporar y Utility Narrative

3 - Utility

Relocati on and

Restorat ion

Are Utility agreements executed with the 5 utility owners that require relocation? Could you please provide timeline/duration for each utility relocation?

After discussing with previous DM (Chas Crawley), intent is for the KTRs to reach out to the utility companies for durations, as they may have changed since last discussion.

VU101

Temporar y Utility Narrative

3 - Utility

Relocati on and

Restorat ion

Can the Contractor reachout directly to utility owners? If so, please provide contact information for each Utility

Yes, contact information is as follows.

Brightspeed: William McCollam; T:

980-376-1388; M: 843-521-7424;

william.mccollam@brightspeed.com Hargray: David Stiles; T: 843-694- 1780; david.stiles@htc.hargray.com DESC: George M. Cox; O: 843-953- 0238; George.Cox@des.sc.gov Parris Island Power/Comm: LT Gal, Andrea; O: 843.228.3497; Cell:

843.996.9107;

N4008525R2513 andrea.h.gal.mil@us.navy.mil | andrea.h.gal.mil@usmc.mil

VU101

Temporar y Utility Narrative

3 - Utility

Relocati on and

Restorat ion

The temporary relocation plan for the Dominion OH power line is not practicle.

With the OH Power line on the Marsh side, the plan requires the contractor to use a crane and place the HDPE conduit in the marsh over the active OH Power line. Will there be a coordinated power outage for the installation of the HDPE conduit, caisons, and pipe pile?

Contractor to coordinate power outage.

Please provide expected duration from Award to NTP.

NTP will be provided as soon as Bonds are authenticated.

Attach ment C

Option No. 2 Unit Price for transfer fresh saltwater from Ribbon Creek to the pond… Please clarify the intent of this Option Pice?

Is it to Pump water from May to October If work is not completed by the Closure window of April 30th?

Yes, that is the intent.

General General General

With the scope of work being so unique on this project, please allow for general contractor to use teaming subcontractors past performance to meet the RFP requirements.

Per the RFP, Factor 1, Corporate Experience - "Experience shall be that of the offeror, performed as the Prime Contractor. Experience of proposed subcontractors will not be considered.

Furthermore, experience of the offeror while working as a subcontractor will not be considered." Please bid per the

RFP.

Are the sheetpile coated or black steel? Per paragraph 3.3.1.2 in Section 31 41 16 (Steel Combination Pile Bulkheads) of the Specifications, tip elevation for the king piles at the North and South bridge is equal to -46 feet and -47 feet, respectively.

(End of Summary of Changes)