1697735_Amend_0002_dated 251030.pdf

PDF 119 KB Posted

Attached to
P-1069, MARITIME SURVEILLANCE SYSTEM FACILITY
Solicitation number
N4008525R2512
Issued by

About this file

This document is a specification for work restrictions from the Naval Facilities Engineering Systems Command (NAVFAC) MID-ATLANTIC, detailing complex construction phasing requirements. The project involves multiple construction phases with a total duration of 1,996 calendar days, including a preconstruction phase of 161 days, Phase 1 of 170 days, Phase 2 spanning 970 days with Subphases 2A and 2B, and Phase 3 encompassing nine Fire Protection subphases over 687 calendar days. Additional project components include 42 calendar days for final site work and 84 calendar days for project closeout. The Beneficial Occupancy Dates (BOD) are carefully sequenced, with specific timelines for each phase and subphase calculated from the notice to proceed, requiring precise coordination and scheduling across multiple construction stages.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS:

REVISE the following sections:

Section 01 14 00 WORK RESTRICTIONS

1.2.e SPECIAL SCHEDULING REQUIREMENTS

ADD the following sections:

(3) The following construction phases must be accounted for on the construction schedule. Refer to drawing sheet GI003 for general phasing and sheets FX002 and FX003 for Fire Protection sub-phasing.

(a) Preconstruction is 161 calendar days.

(b) Phase 1 is 170 calendar days.

(c) Phase 2 includes Subphases 2A, 2B and is 970 calendar days.

(d) Phase 3 includes Subphases 1, 2, 3, 4, 5, 6, 7, 8, 9 and is 687 calendar days.

(e) Final site work is 42 calendar days.

(f) Project closeout is 84 calendar days.

(4) Beneficial Occupancy Date (BOD). Coordinating phasing can be found on sheet GI003 for general phasing and sheets FX002 and FX003 for Fire Protection sub-phasing.

(a) Preconstruction is 161 calendar days from notice to proceed from the contracting officer.

(a) Phase 1 BOD is 212 calendar days from notice to proceed.

(b) Phase 2 BOD is 970 calendar days from Phase 1 BOD.

i. Subphase 2 is 690 calendar days from Phase 1 BOD.

ii. Subphase 2A BOD is 138 calendar days from Subphase 2 BOD.

iii. Subphase 2B BOD is 142 calendar days from Subphase 2A BOD.

(c) Phase 3 BOD is 687 calendar days from Phase 2A BOD.

i. Subphase 1 Fire Protection BOD is 99 calendar days from Subphase 2A BOD.

ii. Subphase 2 Fire Protection BOD is 72 calendar days from Subphase 1 Fire Protection.

iii. Subphase 3 Fire Protection BOD is 72 calendar days from Subphase 2 Fire Protection.

iv. Subphase 4 Fire Protection BOD is 77 calendar days from Subphase 3 Fire Protection.

v. Subphase 5 Fire Protection BOD is 74 calendar days from Subphase 4 Fire Protection.

vi. Subphase 6 Fire Protection BOD is 71 calendar days from Subphase 5 Fire Protection.

vii. Subphase 7 Fire Protection BOD is 72 calendar days from Subphase 6 Fire Protection.

viii. Subphase 8 Fire Protection BOD is 74 calendar days from Subphase 7 Fire Protection.

ix. Subphase 9 Fire Protection BOD is 76 calendar days from Subphase 8 Fire Protection.

(e) Final site work is 42 calendar days from Subphase 9 Fire Protection.

(d) The project closeout period is 84 calendar days from site work. Refer to specification Division 01, section 1.10.1.5.6 for more Turnover and Closeout Activities.

(e) Total construction duration is 1,996 calendar days.