WORK ORDER NO.
At the
PREPARED BY:
Architectural: Mechanical:
Civil: Electrical:
Structural:
APPROVED BY:
Specifications:
For Commander, NAVFAC:
Date:
Submitted By: Date:
Interior Design: Diane McCann, CID
THIS PAGE INTENTIONALLY LEFT BLANK
FY24 MCON Project P1069 eProject Work Order No: 1737142 Dam Neck, Virginia Beach, VA
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17, CHG 8: 02/23 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 22 06/24 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION
02 83 00 11/18 LEAD REMEDIATION
02 84 16 05/20 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 72 00 08/23 DECORATIVE METAL SPECIALTIES
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 20 00 08/16, CHG 2: 11/18 FINISH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 14 00 08/23 FLUID-APPLIED WATERPROOFING
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 10 08/20 COMPOSITE FRAMING SUPPORT (CFS) SYSTEM
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 91 00 07/22 PREFORMED JOINT SEALS
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS
08 34 59 08/08, CHG 1: 11/12 VAULT DOORS AND DAY GATES
08 44 00 05/19 CURTAIN WALL AND GLAZED ASSEMBLIES
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 69 13 11/15, CHG 1: 08/18 RIGID GRID ACCESS FLOORING
09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS
09 90 00 02/21 PAINTS AND COATINGS
09 96 00 11/14 HIGH-PERFORMANCE COATINGS
PROJECT TABLE OF CONTENTS Page 2
DIVISION 10 - SPECIALTIES
10 11 00 08/20 VISUAL DISPLAY UNITS
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 22 43 08/16, CHG 1: 08/18 OPERABLE PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 49 20.00 10 10/07 RF SHIELDING
DIVISION 14 - CONVEYING EQUIPMENT
14 42 16 VERTICAL PLATFORM LIFT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 22 00.00 40 05/16 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND
SEISMIC CONTROL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00.00 22 08/20, CHG 1: 03/22 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 64 26 08/09, CHG 6: 11/22 CHILLED, HEAT RECOVERY AND HOT, WATER
PIPING SYSTEMS
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED
UTILITY MONITORING AND CONTROL SYSTEM
PROJECT TABLE OF CONTENTS Page 3
25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED
UTILITY CONTROL SYSTEMS INCLUDING
ADVANCED METERING INFRASTRUCTURE (AMI)
25 05 11.28 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - ELECTRONIC SECURITY
SYSTEM (ESS)
DIVISION 26 - ELECTRICAL
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 13 13 11/21 METAL-CLAD SWITCHGEAR
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 33 53 05/19 STATIC UNINTERRUPTIBLE POWER SUPPLY
(UPS)
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 13.43 05/20 TELEVISION DISTRIBUTION SYSTEM
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 32 50 11/22 AREA OF REFUGE TWO-WAY COMMUNICATION
SYSTEM
27 51 16 05/20, CHG 1: 05/22 PUBLIC ADDRESS SYSTEMS
27 53 19.13 05/20 FIRST RESPONDER DISTRIBUTED ANTENNAE
SYSTEMS (DAS)
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 08/23 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/24 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
31 31 16.13 08/22 CHEMICAL TERMITE CONTROL
31 62 23.13 02/21 CONCRETE-FILLED STEEL PILES
31 63 16 11/20 AUGERED CAST-IN-PLACE PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
PROJECT TABLE OF CONTENTS Page 4
32 11 20 05/22 AGGREGATE BASE COURSE
32 11 26 05/20 HOT-MIX BITUMINOUS BASE COURSE FOR
ROADS AND STREETS
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK AND
ORNAMENTAL) AND GATES
32 31 13.60 10/25 POST AND BEAM ANTI-RAM VEHICLE BARRIER
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 08 55 08/19 FUEL DISTRIBUTION SYSTEM START-UP
(NON-HYDRANT)
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 52 10 11/18, CHG 1: 11/20 FUEL SYSTEMS PIPING (SERVICE STATION)
33 52 23.15 11/18 POL SERVICE PIPING WELDING
33 56 10 05/19, CHG 1: 11/20 FACTORY-FABRICATED FUEL STORAGE TANKS
33 61 13.13 02/16 PREFABRICATED UNDERGROUND HYDRONIC
ENERGY DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
PROJECT TABLE OF CONTENTS Page 6
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11, CHG 1: 08/14
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
NAVFAC SHEET SHEET SHEET
DWG. NO. NO. REF NO. NAME
GENERAL
12917635 1 G-001 COVER SHEET
12917636 2 GI001 SHEET INDEX
12917637 3 GI002 SHEET INDEX, GENERAL PROJECT NOTES & LEGEND
12917638 4 GI003 SCHEMATIC PHASING SITE PLAN
12917639 5 GI004 SCHEMATIC PHASING PLANS
12917640 6 GI005 PLUMBING FIXTURE COUNT REQUIREMENTS
12917641 7 GI006 BUILDING CODE SUMMARY
12917642 8 GI100 CODE COMPLIANCE SITE PLAN
12917643 9 GI101 BLDG 470 - 1ST FLOOR LIFE SAFETY PLAN
12917644 10 GI102 BLDG 470 - 2ND FLOOR LIFE SAFETY PLAN
HAZMAT
12917645 11 HM101 BLDG 470 - 1ST FLOOR PLAN - HAZMAT REMOVAL - OVERALL
CIVIL
12917646 12 B-100 BORING LOCATION PLAN
12917647 13 B-101 FIELD TEST DATA - BORING LOGS
12917648 14 B-102 FIELD TEST DATA - BORING LOGS
12917649 15 B-103 FIELD TEST DATA - CPT
12917650 16 B-104 FIELD TEST DATA - CPT & SCPT
12917651 17 B-105 FIELD TEST DATA - CPT & DATA SUMMARY
12917652 18 C-001 GENERAL NOTES, LEGEND, AND ABBREVIATIONS
12917653 19 VF101 EXISTING CONDITIONS PLAN
12917654 20 VF102 EXISTING CONDITIONS PLAN
12917655 21 CD101 DEMOLITION PLAN - PRE-BUILDING ADDITION
12917656 22 CD102 DEMOLITION PLAN - PARKING LOT
12917657 23 CD103 DEMOLITION PLAN - POST-BUILDING ADDITION
12917658 24 CS101 SITE PLAN
12917659 25 CS102 SITE PLAN
12917660 26 CS501 SITE DETAILS
12917661 27 CS502 SITE DETAILS
12917662 28 CS503 SITE DETAILS
12917663 29 CS504 SITE DETAILS
12917664 30 CS505 SITE DETAILS
12917665 31 CS506 SITE DETAILS
12917666 32 CP101 PAVING PLAN
12917667 33 CP102 PAVING PLAN
12917668 34 CP501 PAVING DETAILS
DOCUMENT 00 01 15 Page 1
12917669 35 CG101 GRADING PLAN AND DRAINAGE PLAN
12917670 36 CG102 GRADING PLAN AND DRAINAGE PLAN
12917671 37 CG201 DRAINAGE PROFILES
12917672 38 CG202 CONSTRUCTED WETLAND PROFILES
12917673 39 CG501 STORMWATER DETAILS
12917674 40 CG502 STORMWATER DETAILS
12917675 41 CG701 GRADING POINTS
12917676 42 CG702 GRADING POINTS
12917677 43 CH101 HORIZONTAL CONTROL PLAN
12917678 44 CH102 HORIZONTAL CONTROL PLAN
12917679 45 CH601 HORIZONTAL CONTROL TABLES
12917680 46 CH602 HORIZONTAL CONTROL TABLES
12917681 47 CU101 UTILITY PLAN
12917682 48 CU102 UTILITY PLAN
12917683 49 CU201 SANITARY PROFILES
12917684 50 CU202 UTILITY PROFILES
12917685 51 CU401 ENLARGED WET UTILITY PLAN
12917686 52 CU501 SITE UTILITY DETAILS
12917687 53 CU502 SITE UTILITY DETAILS
12917688 54 CU503 SITE UTILITY DETAILS
12917689 55 CU504 SITE UTILITY DETAILS
12917690 56 CU505 SITE UTILITY DETAILS
12917691 57 CE001 EROSION AND SEDIMENT CONTROL NOTES
12917692 58 CE101 EROSION AND SEDIMENT CONTROL PLAN - PHASE 1
12917693 59 CE102 EROSION AND SEDIMENT CONTROL PLAN - PHASE 1
12917694 60 CE103 EROSION AND SEDIMENT CONTROL PLAN - PHASE 2
12917695 61 CE104 EROSION AND SEDIMENT CONTROL PLAN - PHASE 2
12917696 62 CE105 EROSION AND SEDIMENT CONTROL PLAN - PHASE 3
12917697 63 CE106 EROSION AND SEDIMENT CONTROL PLAN - PHASE 3
12917698 64 CE501 EROSION AND SEDIMENT CONTROL DETAILS
12917699 65 CE502 EROSION AND SEDIMENT CONTROL DETAILS
12917700 66 CE503 EROSION AND SEDIMENT CONTROL DETAILS
12917701 67 CE504 EROSION AND SEDIMENT CONTROL DETAILS
LANDSCAPE
12917702 68 LP101 LANDSCAPE PLAN
12917703 69 LP102 LANDSCAPE PLAN
12917704 70 L-501 LANDSCAPE SCHEDULE AND DETAILS
STRUCTURAL
12917705 71 S-001 STRUCTURAL NOTES AND ABBREVIATIONS
12917706 72 S-002 STRUCTURAL NOTES AND LEGEND
12917707 73 S-003 STRUCTURAL NOTES
12917708 74 S-004 REINFORCING SCHEDULES
12917709 75 S-005 WIND PRESSURE DIAGRAMS
12917710 76 SB101A BLDG 470 - FOUNDATION PLAN - AREA 'A'
12917711 77 SB101B BLDG 470 - FOUNDATION PLAN - AREA 'B'
12917712 78 SB101C BLDG 470 - FOUNDATION PLAN - AREA 'C'
12917713 79 SB101LD BLDG 470 - FOUNDATION PLAN - LOADING DOCK
12917714 80 SB111A BLDG 470 - 1ST FLOOR SLAB PLAN - AREA 'A'
12917715 81 SB111B BLDG 470 - 1ST FLOOR SLAB PLAN - AREA 'B'
12917716 82 SB301 FOUNDATION SECTIONS
12917717 83 SB302 FOUNDATION SECTIONS
12917718 84 SB303 FOUNDATION SECTIONS
12917719 85 SB501 TYPICAL FOUNDATION DETAILS
12917720 86 SB502 TYPICAL FOUNDATION DETAILS
12917721 87 SB503 TYPICAL FOUNDATION DETAILS
12917722 88 SB504 TYPICAL FOUNDATION DETAILS
12917723 89 SB505 TYPICAL FOUNDATION DETAILS
DOCUMENT 00 01 15 Page 2
12917724 90 SB506 COLUMN BASE PLATE SCHEDULE AND DETAILS
12917725 91 SF101A BLDG 470 - ROOF FRAMING PLAN - AREA 'A'
12917726 92 SF101B BLDG 470 - 2ND FLOOR FRAMING PLAN - AREA 'B'
12917727 93 SF101C BLDG 470 - 2ND FLOOR FRAMING PLAN - AREA 'C'
12917728 94 SF111B BLDG 470 - ROOF FRAMING PLAN - AREA 'B'
12917729 95 SF201 BRACED FRAME ELEVATIONS
12917730 96 SF202 BRACED FRAME DETAILS
12917731 97 SF301 FRAMING SECTIONS
12917732 98 SF401 MECHANICAL UNIT FRAMING PLANS
12917733 99 SF501 TYPICAL FRAMING DETAILS
12917734 100 SF502 TYPICAL FRAMING DETAILS
12917735 101 SF503 TYPICAL FRAMING DETAILS
12917736 102 SF504 TYPICAL FRAMING DETAILS - CANOPY
12917737 103 SF505 TYPICAL FRAMING DETAILS - MECHANICAL UNITS
12917738 104 SF601 TYPICAL MASONRY DETAILS
12917739 105 SF602 TYPICAL MASONRY DETAILS
12917740 106 SF701 ROOF JOIST LOAD DIAGRAMS - AREA 'A'
12917741 107 SF702 ROOF JOIST LOAD DIAGRAMS - AREA 'B'
12917742 108 SF703 ROOF JOIST LOAD DIAGRAMS - AREA 'B'
12917743 109 SF704 ROOF JOIST LOAD DIAGRAMS - AREA 'B'
ARCHITECTURAL
12917744 110 A-001 ARCHITECTURAL LEGEND, NOTES AND ABBREVIATIONS
12917745 111 A-002 BLDG 470 - AIR BARRIER KEY PLANS & BUILDING
SECTIONS
12917746 112 A-003 BLDG 470 - 1ST FLOOR ACCESS CONTROL KEY PLANS
12917747 113 A-004 BLDG 470 - 2ND FLOOR ACCESS CONTROL AREA KEY PLAN
12917748 114 AD101 BLDG 470 - 1ST FLOOR DEMOLITION PLAN - OVERALL
12917749 115 AD101D BLDG 470 - 1ST FLOOR DEMOLITION PLAN - AREA 'D'
12917750 116 AD102 BLDG 470 - 2ND FLOOR DEMOLITION PLAN - OVERALL
12917751 117 AE101 BLDG 470 - 1ST FLOOR PLAN - OVERALL
12917752 118 AE101A BLDG 470 - 1ST FLOOR PLAN - AREA 'A'
12917753 119 AE101B BLDG 470 - 1ST FLOOR PLAN - AREA 'B'
12917754 120 AE101D BLDG 470 - 1ST FLOOR PLAN - AREA 'D'
12917755 121 AE102 BLDG 470 - 2ND FLOOR PLAN - OVERALL
12917756 122 AE102B BLDG 470 - 2ND FLOOR PLAN - AREA 'B'
12917757 123 AE102C BLDG 470 - 2ND FLOOR PLAN - AREA 'C'
12917758 124 AE103 BLDG 470 - ROOF PLAN - OVERALL
12917759 125 AE111 BLDG 470 - 1ST FLOOR REFLECTED CEILING PLAN -
OVERALL
12917760 126 AE111A BLDG 470 - 1ST FLOOR REFLECTED CEILING PLAN -
AREA 'A'
12917761 127 AE111B BLDG 470 - 1ST FLOOR REFLECTED CEILING PLAN -
AREA 'B'
12917762 128 AE111D BLDG 470 - 1ST FLOOR REFLECTED CEILING PLAN -
AREA 'D'
12917763 129 AE112 BLDG 470 - 2ND FLOOR REFLECTED CEILING PLAN -
OVERALL
12917764 130 AE112B BLDG 470 - 2ND FLOOR REFLECTED CEILING PLAN -
AREA 'B'
12917765 131 AE112C BLDG 470 - 2ND FLOOR REFLECTED CEILING PLAN -
AREA 'C'
12917766 132 AE201 BLDG 470 - EXTERIOR ELEVATIONS
12917767 133 AE202 BLDG 470 - EXTERIOR ELEVATIONS
12917768 134 AE203 BLDG 470 - EXTERIOR ELEVATIONS & DETAILS
12917769 135 AE301 BLDG 470 - BUILDING SECTIONS
12917770 136 AE302 BLDG 470 - BUILDING SECTIONS
12917771 137 AE311 BLDG 470 - WALL SECTIONS
12917772 138 AE312 BLDG 470 - WALL SECTIONS
DOCUMENT 00 01 15 Page 3
12917773 139 AE313 BLDG 470 - WALL SECTIONS
12917774 140 AE401 BLDG 470 - CANOPY PLANS
12917775 141 AE402 BLDG 470 - CANOPY ELEVATION, SECTION & DETAILS
12917776 142 AE403 BLDG 470 - CANOPY SECTIONS & DETAILS
12917777 143 AE404 BLDG 470 - CANOPY SECTIONS & DETAILS
12917778 144 AE405 BLDG 470 - ENLARGED STAIR PLANS
12917779 145 AE406 BLDG 470 - ENLARGED STAIR PLANS
12917780 146 AE407 BLDG 470 - ENLARGED STAIR PLANS
12917781 147 AE408 BLDG 470 - ENLARGED STAIR PLANS
12917782 148 AE409 BLDG 470 - STAIR DETAILS
12917783 149 AE410 BLDG 470 - STAIR DETAILS
12917784 150 AE411 BLDG 470 - STAIR & LADDER DETAILS
12917785 151 AE412 BLDG 470 - ENLARGED TOILET PLANS & EMERGENCY
EYEWASH / SHOWER PLANS
12917786 152 AE501 PARTITION TYPES
12917787 153 AE502 PARTITION DETAILS
12917788 154 AE503 PARTITION DETAILS & BUILT-UP FLOOR DETAIL
12917789 155 AE504 BLDG 470 - COLUMN DETAILS
12917790 156 AE505 BLDG 470 - COLUMN DETAILS, PLAN DETAILS, AND
SECTIONS
12917791 157 AE506 CEILING & OPERABLE PARTITION DETAILS
12917792 158 AE507 RF SHIELDING DETAILS
12917793 159 AE508 RF SHIELDING DETAILS
12917794 160 AE509 WALL DETAILS
12917795 161 AE510 WALL DETAILS
12917796 162 AE511 WALL DETAILS & BUILDING EXPANSION JOINT DETAILS
12917797 163 AE512 BUILDING EXPANSION JOINT DETAILS
12917798 164 AE513 BUILDING EXPANSION JOINT DETAILS & ROOF DETAILS
12917799 165 AE514 ROOF DETAILS
12917800 166 AE515 ROOF DETAILS
12917801 167 AE516 ROOF DETAILS
12917802 168 AE517 ROOF DETAILS
12917803 169 AE601 DOOR SCHEDULE & ELEVATIONS
12917804 170 AE701 DOOR DETAILS
12917805 171 AE702 DOOR DETAILS
12917806 172 AE703 DOOR DETAILS
12917807 173 AE704 CURTAIN WALL ELEVATIONS & DETAILS
12917808 174 AE705 LOUVER ELEVATIONS & DETAILS
12917809 175 AE801 BLDG 470 - INTERIOR ELEVATIONS
INTERIORS
12917810 176 IN101A BLDG 470 - 1ST FLOOR FINISH AND SIGNAGE PLAN -
AREA 'A'
12917811 177 IN101B BLDG 470 - 1ST FLOOR FINISH AND SIGNAGE PLAN -
AREA 'B'
12917812 178 IN101D BLDG 470 - 1ST FLOOR FINISH AND SIGNAGE PLAN -
PARTIAL AREA 'D'
12917813 179 IN102B BLDG 470 - 2ND FLOOR FINISH AND SIGNAGE PLAN -
AREA 'B'
12917814 180 IN102C BLDG 470 - 2ND FLOOR FINISH AND SIGNAGE PLAN -
AREA 'C' AND 2ND FLOOR SIGNAGE PLAN - PARTIAL
AREA 'D'
12917815 181 IN401 INTERIOR DETAILS AND ELEVATIONS
12917816 182 IN601 FINISH SCHEDULE AND LEGEND
12917817 183 IG501 SIGNAGE DETAILS
12917818 184 IF101 BLDG 470 - 1ST FLOOR FURNITURE PLAN - OVERALL
12917819 185 IF101B BLDG 470 - 1ST FLOOR FURNITURE PLAN - AREA 'B'
12917820 186 IF101D BLDG 470 - 1ST FLOOR FURNITURE PLAN - PARTIAL
AREA 'D'
DOCUMENT 00 01 15 Page 4
12917821 187 IF102 BLDG 470 - 2ND FLOOR FURNITURE PLAN - OVERALL
12917822 188 IF102B BLDG 470 - 2ND FLOOR FURNITURE PLAN - AREA 'B'
FIRE PROTECTION
12917823 189 FD101C BLDG 470 - 1ST FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'C'
12917824 190 FD101D BLDG 470 - 1ST FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'D'
12917825 191 FD101E BLDG 470 - 1ST FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'E'
12917826 192 FD101F BLDG 469 - 1ST FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'F'
12917827 193 FD102C BLDG 470 - 2ND FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'C'
12917828 194 FD102D BLDG 470 - 2ND FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'D'
12917829 195 FD102E BLDG 470 - 2ND FLOOR FIRE PROTECTION DEMOLITION
PLAN - AREA 'E'
12917830 196 FA001 FIRE ALARM LEGEND
12917831 197 FA002 FIRE ALARM/MNS RISER DIAGRAM
12917832 198 FA003 CLEAN AGENT SYSTEM RISER AND MATRIX
12917833 199 FA101A BLDG 470 - 1ST FLOOR FIRE ALARM PLAN - AREA 'A'
12917834 200 FA101B BLDG 470 - 1ST FLOOR FIRE ALARM PLAN - AREA 'B'
12917835 201 FA101C BLDG 470 - 1ST FLOOR FIRE ALARM PLAN - AREA 'C'
12917836 202 FA101D BLDG 470 - 1ST FLOOR FIRE ALARM PLAN - AREA 'D'
12917837 203 FA101E BLDG 470 - 1ST FLOOR FIRE ALARM PLAN - AREA 'E'
12917838 204 FA101F BLDG 469 - 1ST FLOOR FIRE ALARM PLAN - AREA F
12917839 205 FA102B BLDG 470 - 2ND FLOOR FIRE ALARM PLAN - AREA 'B'
12917840 206 FA102C BLDG 470 - 2ND FLOOR FIRE ALARM PLAN - AREA 'C'
12917841 207 FA102D BLDG 470 - 2ND FLOOR FIRE ALARM PLAN - AREA 'D'
12917842 208 FA102E BLDG 470 - 2ND FLOOR FIRE ALARM PLAN - AREA 'E'
12917843 209 FX001 FIRE SUPPRESSION LEGEND
12917844 210 FX002 FIRE SUPPRESSION FIRST FLOOR PHASING PLAN
12917845 211 FX003 FIRE SUPPRESSION SECOND FLOOR PHASING PLAN
12917846 212 FX101A BLDG 470 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'A'
12917847 213 FX101B BLDG 470 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'B'
12917848 214 FX101C BLDG 470 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'C'
12917849 215 FX101D BLDG 470 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'D'
12917850 216 FX101E BLDG 470 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'E'
12917851 217 FX101F BLDG 469 - 1ST FLOOR FIRE SUPPRESSION PLAN -
AREA 'F'
12917852 218 FX102B BLDG 470 - 2ND FLOOR FIRE SUPPRESSION PLAN -
AREA 'B'
12917853 219 FX102C BLDG 470 - 2ND FLOOR FIRE SUPPRESSION PLAN -
AREA 'C'
12917854 220 FX102D BLDG 470 - 2ND FLOOR FIRE SUPPRESSION PLAN -
AREA 'D'
12917855 221 FX102E BLDG 470 - 2ND FLOOR FIRE SUPPRESSION PLAN -
AREA 'E'
PLUMBING
12917856 222 P-001 PLUMBING LEGEND
12917857 223 PF101A BLDG 470 - FOUNDATION PLAN - AREA 'A'
12917858 224 PF101B BLDG 470 - FOUNDATION PLAN - AREA 'B'
DOCUMENT 00 01 15 Page 5
12917859 225 PL101A BLDG 470 - 1ST FLOOR PLAN - AREA 'A'
12917860 226 PL101B BLDG 470 - 1ST FLOOR PLAN - AREA 'B'
12917861 227 PL102B BLDG 470 - 2ND FLOOR PLAN - AREA 'B'
12917862 228 P-401 ENLARGED
12917863 229 P-501 DETAILS
12917864 230 P-601 SCHEDULES
12917865 231 P-701 PIPING DIAGRAMS
MECHANICAL
12917866 232 M-001 MECHANICAL LEGEND, ABBREVIATIONS, AND GENERAL
NOTES
12917867 233 M-002 MECHANICAL LEGEND, ABBREVIATIONS, AND GENERAL
NOTES
12917868 234 MD101C BLDG 470 - 1ST FLOOR DEMOLITION PLAN - AREA 'C'
12917869 235 MD101D BLDG 470 - 1ST FLOOR DEMOLITION PLAN - AREA 'D'
12917870 236 MD101F BLDG 469 - 1ST FLOOR DEMOLITION PLAN - AREA 'F'
12917871 237 MD102D BLDG 470 - 2ND FLOOR DEMOLITION PLAN - AREA 'D'
12917872 238 MD301 DEMOLITION SECTIONS
12917873 239 MD401 ENLARGED DEMOLITION PLANS
12917874 240 MD402 ENLARGED DEMOLITION PLANS
12917875 241 MD403 ENLARGED DEMOLITION PLANS
12917876 242 MD404 ENLARGED DEMOLITION PLANS
12917877 243 MH101A BLDG 470 - 1ST FLOOR DUCTWORK PLAN - AREA 'A'
12917878 244 MH101B BLDG 470 - 1ST FLOOR DUCTWORK PLAN - AREA 'B'
12917879 245 MH101D BLDG 470 - 1ST FLOOR DUCTWORK PLAN - AREA 'D'
12917880 246 MH102A BLDG 470 - ROOF PLAN - AREA 'A'
12917881 247 MH102B BLDG 470 - 2ND FLOOR DUCTWORK PLAN - AREA 'B'
12917882 248 MH102D BLDG 470 - 2ND FLOOR DUCTWORK PLAN - AREA 'D'
12917883 249 MH103B BLDG 470 - ROOF PLAN - AREA 'B'
12917884 250 MP101A BLDG 470 - 1ST FLOOR PIPING PLAN - AREA 'A'
12917885 251 MP101B BLDG 470 - 1ST FLOOR PIPING PLAN - AREA 'B'
12917886 252 MP101C BLDG 470 - 1ST FLOOR PIPING PLAN - AREA 'C'
12917887 253 MP101D BLDG 470 - 1ST FLOOR PIPING PLAN - AREA 'D'
12917888 254 MP101F BLDG 469 - 1ST FLOOR PIPING PLAN - AREA 'F'
12917889 255 MP102B BLDG 470 - 2ND FLOOR PIPING PLAN - AREA 'B'
12917890 256 MP102D BLDG 470 - 2ND FLOOR PIPING PLAN - AREA 'D'
12917891 257 M-301 SECTIONS
12917892 258 M-302 SECTIONS
12917893 259 M-303 SECTIONS
12917894 260 M-401 ENLARGED PLANS
12917895 261 M-402 ENLARGED PLANS
12917896 262 M-403 ENLARGED PLANS
12917897 263 M-404 ENLARGED PLANS
12917898 264 M-501 DETAILS
12917899 265 M-502 DETAILS
12917900 266 M-503 DETAILS
12917901 267 M-601 SCHEDULES
12917902 268 M-602 SCHEDULES
12917903 269 M-603 SCHEDULES
12917904 270 M-604 SCHEDULES
12917905 271 M-605 SCHEDULES
12917906 272 M-701 FLOW DIAGRAMS
12917907 273 M-702 FLOW DIAGRAMS
12917908 274 M-703 FLOW DIAGRAMS
12917909 275 M-800 CONTROLS
12917910 276 M-801 CONTROLS
12917911 277 M-802 CONTROLS
12917912 278 M-803 CONTROLS
12917913 279 M-804 CONTROLS
DOCUMENT 00 01 15 Page 6
12917914 280 M-805 CONTROLS
12917915 281 M-806 CONTROLS
12917916 282 M-807 CONTROLS
12917917 283 M-808 CONTROLS
ELECTRICAL
12917918 284 E-001 ELECTRICAL LEGEND, NOTES AND ABBREVIATIONS
12917919 285 ED101 ELECTRICAL SITE PLAN - DEMOLITION
12917920 286 ED102 ELECTRICAL SITE PLAN - DEMOLITION
12917921 287 ES101 ELECTRICAL SITE PLAN - NEW WORK
12917922 288 ES102 ELECTRICAL SITE PLAN - NEW WORK
12917923 289 ES401 ENLARGED ELECTRICAL SITE PLAN
12917924 290 ES402 ENLARGED ELECTRICAL SITE PLANS
12917925 291 ES501 ELECTRICAL SITE DETAILS
12917926 292 ES502 ELECTRICAL SITE DETAILS
12917927 293 EG101A BLDG 470 - LIGHTNING PROTECTION PLAN - AREA 'A'
12917928 294 EG101B BLDG 470 - LIGHTNING PROTECTION PLAN - AREA 'B'
12917929 295 EG501 LIGHTNING PROTECTION DETAILS
12917930 296 ED101D BLDG 470 - 1ST FLOOR DEMOLITION PLAN - AREA 'D'
12917931 297 ED102C BLDG 470 - 2ND FLOOR DEMOLITION PLAN - AREA 'C'
12917932 298 EL101A BLDG 470 - 1ST FLOOR LIGHTING PLAN - AREA 'A'
12917933 299 EL101B BLDG 470 - 1ST FLOOR LIGHTING PLAN - AREA 'B'
12917934 300 EL101D BLDG 470 - 1ST FLOOR LIGHTING PLAN - AREA 'D'
12917935 301 EL102B BLDG 470 - 2ND FLOOR LIGHTING PLAN - AREA 'B'
12917936 302 EL501 LIGHTING FIXTURE DETAILS
12917937 303 EL502 LIGHTING FIXTURE DETAILS
12917938 304 EL503 LIGHTING FIXTURE DETAILS
12917939 305 EL601 LIGHTING FIXTURE SCHEDULE
12917940 306 EP101A BLDG 470 - 1ST FLOOR POWER PLAN - AREA 'A'
12917941 307 EP101B BLDG 470 - 1ST FLOOR POWER PLAN - AREA 'B'
12917942 308 EP101D BLDG 470 - 1ST FLOOR POWER PLAN - AREA 'D'
12917943 309 EP101F BLDG 469 - PARTIAL POWER PLAN - AREA 'F'
12917944 310 EP102B BLDG 470 - 2ND FLOOR POWER PLAN - AREA 'B'
12917945 311 EP102D BLDG 470 - 2ND FLOOR POWER PLAN - AREA 'D'
12917946 312 EP401 ENLARGED POWER PLANS
12917947 313 EP402 ENLARGED POWER PLANS
12917948 314 EP403 ENLARGED POWER PLANS
12917949 315 EP404 ENLARGED POWER PLANS
12917950 316 EP501 POWER DETAILS
12917951 317 EP502 POWER DETAILS
12917952 318 EP503 POWER DETAILS
12917953 319 EP601 EQUIPMENT CONNECTION SCHEDULE
12917954 320 EP602 PANELBOARD SCHEDULES
12917955 321 EP603 PANELBOARD SCHEDULES
12917956 322 EP604 PANELBOARD SCHEDULES
12917957 323 EP605 PANELBOARD SCHEDULES
12917958 324 EP606 PANELBOARD SCHEDULES
12917959 325 EP607 PANELBOARD SCHEDULES
12917960 326 EP608 PANELBOARD SCHEDULES
12917961 327 EP609 PANELBOARD SCHEDULES
12917962 328 EP610 PANELBOARD SCHEDULES
12917963 329 EP611 PANELBOARD SCHEDULES
12917964 330 EP612 PANELBOARD SCHEDULES
12917965 331 EP613 PANELBOARD SCHEDULES
12917966 332 EP614 PANELBOARD SCHEDULES
12917967 333 EP701 POWER RISER DIAGRAM
12917968 334 EP702 POWER RISER DIAGRAM
12917969 335 EP703 POWER RISER DIAGRAM
DOCUMENT 00 01 15 Page 7
TELECOM
12917970 336 TN001 TELECOM LEGEND, ABBREVIATIONS & NOTES
12917971 337 TN101A BLDG 470 - 1ST FLOOR TELECOM PLAN - AREA 'A'
12917972 338 TN101B BLDG 470 - 1ST FLOOR TELECOM PLAN - AREA 'B'
12917973 339 TN101C BLDG 470 - 1ST FLOOR TELECOM PLAN - AREA 'C'
12917974 340 TN101D BLDG 470 - 1ST FLOOR TELECOM PLAN - AREA 'D'
12917975 341 TN102B BLDG 470 - 2ND FLOOR TELECOM PLAN - AREA 'B'
12917976 342 TN102C BLDG 470 - 2ND FLOOR TELECOM PLAN - AREA 'C'
12917977 343 TN401 ENLARGED TELECOM PLANS
12917978 344 TN402 ENLARGED TELECOM PLANS
12917979 345 TN403 ENLARGED TELECOM PLANS
12917980 346 TN404 ENLARGED TELECOM PLANS
12917981 347 TN405 ENLARGED TELECOM PLANS
12917982 348 TN501 TELECOM DETAILS
12917983 349 TN502 TELECOM DETAILS
12917984 350 TN503 TELECOM DETAILS
12917985 351 TN504 TELECOM DETAILS
12917986 352 TN505 TELECOM DETAILS
12917987 353 TN701 TELECOM RISER DIAGRAM
12917988 354 TN702 TELECOM RISER DIAGRAM
12917989 355 TY001 SECURITY LEGEND, ABBREVIATIONS & NOTES
12917990 356 TY101A BLDG 470 - 1ST FLOOR SECURITY PLAN - AREA 'A'
12917991 357 TY101B BLDG 470 - 1ST FLOOR SECURITY PLAN - AREA B
12917992 358 TY101D BLDG 470 - 1ST FLOOR SECURITY PLAN - AREA 'D'
12917993 359 TY102B BLDG 470 - 2ND FLOOR SECURITY PLAN - AREA 'B'
12917994 360 TY501 SECURITY DETAILS
12917995 361 TY502 SECURITY DETAILS
12917996 362 TY503 SECURITY DETAILS
12917997 363 TY504 SECURITY DETAILS
12917998 364 TY505 SECURITY DETAILS
12917999 365 TY506 SECURITY DETAILS
12918000 366 TY507 SECURITY DETAILS
12918001 367 TY508 SECURITY DETAILS
AUDIOVISUAL
12918002 368 TA001 AUDIOVISUAL - GENERAL NOTES
12918003 369 TA101 BLDG 470 - 1ST FLOOR PLAN - OVERALL
12918004 370 TA101B BLDG 470 - 1ST FLOOR PLAN - AREA B
12918005 371 TA101D BLDG 470 - 1ST FLOOR PLAN - AREA D
12918006 372 TA102 BLDG 470 - 2ND FLOOR PLAN - OVERALL
12918007 373 TA102B BLDG 470 - 2ND FLOOR PLAN - AREA B
12918008 374 TA111D BLDG 470 - 1ST FLOOR CEILING PLAN - AREA D
12918009 375 TA112B BLDG 470 - 2ND FLOOR CEILING PLAN - AREA B
12918010 376 TA201 BLDG 470 - DISPLAY ELEVATIONS
12918011 377 TA202 BLDG 470 - DISPLAY ELEVATIONS
12918012 378 TA501 BLDG 470 - PLATE AND PANEL DETAILS
12918013 379 TA511 BLDG 470 - AV EQUIPMENT RACK DETAILS
12918014 380 TA512 BLDG 470 - AV EQUIPMENT RACK DETAILS
12918015 381 TA601 BLDG 470 - AUDIOVISUAL RISER DIAGRAMS
12918016 382 TA602 BLDG 470 - AUDIOVISUAL RISER DIAGRAMS
12918017 383 TA701 BLDG 470 - CLASSROOM 133 SCHEMATIC DIAGRAM
12918018 384 TA702 BLDG 470 - CLASSROOM 296 SCHEMATIC DIAGRAM
12918019 385 TA703 BLDG 470 - CONF RM 294 SCHEMATIC DIAGRAM
12918020 386 TA704 BLDG 470 - WATCH FLOOR 292 SCHEMATIC DIAGRAM
12918021 387 TA801 BLDG 470 - CONCEPT ELEVATIONS - WATCH FLOOR 292
12918022 388 TA802 BLDG 470 - CONCEPT SIGHTLINES - WATCH FLOOR 292
ERCES
12918023 389 X-001 BLDG 470 - ERCES BILL OF MATERIALS
DOCUMENT 00 01 15 Page 8
12918024 390 XV101 BLDG 470 - 1ST FLOOR VHF ANTENNA DIAGRAM
12918025 391 XV102 BLDG 470 - 2ND FLOOR VHF ANTENNA DIAGRAM
12918026 392 XV103 BLDG 470 - ROOFTOP VHF ANTENNA DIAGRAM
12918027 393 XV104 BLDG 470 - VHF RISER DIAGRAM
12918028 394 XV111 BLDG 470 - 1ST FLOOR VHF COVERAGE MAP
12918029 395 XV112 BLDG 470 - 2ND FLOOR VHF COVERAGE MAP
12918030 396 XU101 BLDG 470 - 1ST FLOOR UHF ANTENNA DIAGRAM
12918031 397 XU102 BLDG 470 - 2ND FLOOR UHF ANTENNA DIAGRAM
12918032 398 XU103 BLDG 470 - ROOFTOP UHF ANTENNA DIAGRAM
12918033 399 XU104 BLDG 470 - UHF RISER DIAGRAM
12918034 400 XZ101 BLDG 470 - 1ST FLOOR 800MHZ COVERAGE MAP
12918035 401 XZ102 BLDG 470 - 2ND FLOOR 800MHZ COVERAGE MAP
12918036 402 XZ111 BLDG 470 - 1ST FLOOR 400MHZ COVERAGE MAP
12918037 403 XZ112 BLDG 470 - 2ND FLOOR 400MHZ COVERAGE MAP
-- End of Document --
DOCUMENT 00 01 15 Page 9
DOCUMENT 00 01 15 Page 10
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan; G
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The project is located at Oceana Naval Air Station - Dam Neck Annex, Virginia Beach, VA.
Existing Building 470 is provided with a significant 2-story building addition at the West end of recently completed project P603 and select interior renovations. The new addition provides expanded data processing & mission operational spaces, increased operational support spaces, select facility security upgrades, and associated utility & site modifications.
Parking at the complex is also expanded to improve the parking concerns for the approximately 368 personnel across the TUSC LANT complex.
The building addition includes training, operations, administrative, IT logistics support, and watch stander spaces. It consists of open secret storage spaces (OSS), controlled areas, NMCI server room, and telecommunications rooms. Supporting spaces include male and female restrooms, a break room, an uninterruptable power supply (UPS) room, and utility rooms.
The renovation area primarily consists of approximately 4,300 SF of floor space on the first floor of the original portion of existing Building 470.
It includes training and training support spaces. Additionally, the project includes upgrades to portions of the HVAC system and the relocation of existing UPS equipment from the existing building to the new addition. It also includes the replacement of the existing fire protection systems in existing Building 470 and portions of existing utility Building 469.
1.2.2 Location
The work is located at the Oceana Naval Air Station - Dam Neck Annex, Virginia Beach, Virginia, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location
SECTION 01 11 00 Page 1 in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. Special procedures will need to be followed for entry into the existing buildings and these procedures will need to be coordinated with the Contracting Officer.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.6 NAVY AND MARINE CORPS INTRANET(NMCI) COORDINATION REQUIREMENTS
1.6.1 NMCI Contractor Access
Allow the NMCI Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the NMCI Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional
SECTION 01 11 00 Page 2 coordination with the NMCI Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.7 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 5 miles of the construction site.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 1: 02/23
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. All work must be ready for operation as approved by Contracting Officer before work is started in any area of Building 470 or P603 which would interfere with normal operation.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the any work in existing building 470 or P603.
c. Buildings 469, 470 and P603 will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
The following conditions apply:
(1) Existing underground water piping below the proposed P1069 building addition footprint that serves P603 and the Utility Plant is to remain in service until new water service is constructed through the P1069 building addition and new water service is activated. Contractor to protect existing water service lines until new water service is activated and then abandon existing water lines in place. Abandoned lines shall be filled with flowable fill.
(2) Existing underground sanitary line piping below the proposed P1069 building addition footprint that serves P603 and the Utility Plant is to remain in service until new sanitary line is constructed and then existing sanitary line is to be demolished.
SECTION 01 14 00 Page 1
f. In order to minimize impacts to protected, threatened and endangered species, tree clearing/pruning is prohibited from December 15 through February 15 and April 1 through July 31 of any given year.
g. As indicated on the drawings, significant environmentally sensitive areas, including protected wetlands, areas of contamination (including, but not limited to, lead, PAHs, petroleum, PFAS, low level radiological materials, and unexploded ordnance) will be encountered at the site, including areas that may not be disturbed. A Land Disturbance Work Plan with these important features defined, appropriate construction restrictions, material, Soil management and dewatering plans, work protection requirements, and a clear plan for waste disposal excavated from these areas is required to be submitted prior to mobilization for this project. This Work Plan is expected to take 180 days to review and ultimately approved by the appropriate POCs and regulatory agencies. Assume 3 rounds of comments between NAVFAC/regulatory agencies and the construction contractor is required. The contractor will have 10 work days to respond. The review and approval of this work plan must be included in all construction schedules. The submittal register for this Land Disturbance Work Plan is included in specification 01 57 19, Temporary Environmental Controls.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Additional Personnel Requirements
1.3.1.2.1 General Construction and Finish Work
General construction and finish work of the controlled area must be performed by U.S. firms using U.S. citizens. General construction includes construction activities such as building sitework, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work. Finish Work includes construction activities such as insulation, floor, partition, and ceiling systems; cabinet work; conveyor systems; specialties; building furnishings, fixtures, and equipment; and mechanical and electrical services and equipment including those specialized for fire protection, security, communication, control, energy conservation, safety, comfort, convenience, and similar purposes.
SECTION 01 14 00 Page 2
1.3.1.2.2 Electronic Security Systems Equipment
Electronic Security Systems equipment such as processing control units, workstations, field panels, sensors, high security locks, card readers, cable installation, and system programming, testing and training must be performed by U.S. citizens who have been subjected to a trustworthiness determination.
1.3.1.3 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.3.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.3.1.3.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and
SECTION 01 14 00 Page 3
Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.3.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.3.4 One-Day Passes
Participation in the NCACS is not mandatory, and if the contractor chooses not to participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied and Existing Buildings
The Contractor shall be working in and around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in all spaces where active work is occurring during the construction period.
SECTION 01 14 00 Page 4
Relocate movable furniture away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.
The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and communications are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to hours as directed by the Contracting Officer. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4 SECURITY REQUIREMENTS
1.4.1 Naval Air Station, Oceana, Virginia Beach, VA
Contractor personnel are required to obtain personnel identification badges. In accordance with Section 01 30 00 ADMINISTRATIVE REQUIREMENTS, paragraph "Subcontractors and Personnel," the Contractor must submit, in triplicate, a list of his subcontractors and the work each is to perform.
On this listing must appear the names of the key personnel of the Contractor and subcontractors. A copy of the list of key personnel will be forwarded to the Naval Air Station, Oceana, Security Department by the Contracting Officer. The key personnel are responsible for identifying other Contractor and subcontractor personnel for the purpose of obtaining identification badges. Contractors working in restricted work areas are also required to obtain special identification badges for personnel requiring access to the restricted work areas. Immediately after award, the Contractor must submit a letter to the Contracting Officer with the following information for each employee: Company name, employee's name, Social Security number, height, and weight. Also, indicate the names of persons authorized to vouch for additional employees requiring badges.
Requests must be made at least 48-hours in advance but not exceed 5-days in advance of the day escorts are needed. Coordinate the requirement with the command's Site Security Manager (SSM) and the Construction Security
SECTION 01 14 00 Page 5