This document is a schedule of special inspections for a structural steel project. It outlines inspection requirements and tasks for welding, bolting, non-destructive testing, and driven deep foundations. Inspections include verifying qualifications, materials, procedures, installation, and completed work. Welding inspections cover preparation, process monitoring, and post-weld testing. Bolting inspections involve manufacture certifications, storage, installation, and final acceptance. Non-destructive testing specifies ultrasonic and dye penetrant examination for fatigue-prone welds. Driven foundations require continuous monitoring of elements, driving, placement, testing, and additional steel or concrete oversight. The related federal contract opportunity is a solicitation to relocate an underwater electromagnetic measurement system at a naval submarine base, referencing the PIEE Solicitation Module link for full details.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
SCHEDULE OF SPECIAL INSPECTIONS
Reference UFGS 01 45 35 for all requirements not noted as part of this schedule.
INSPECTION DEFINITIONS:
PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.
OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
The Seismic Design Category for this project is: ☐ A, ☐ B, ☒ C, ☐ D, ☐ E, ☐ F (check appropriate box)
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – WELDING SECTION
ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☒
STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-1
TASK INSPECTION TYPE1 DESCRIPTION
1. Verify that the welding procedures specification (WPS) is available
PERFORM
2. Verify manufacturer certifications for welding consumables are available
PERFORM
3. Verify material identification PERFORM Type and grade.
4. Welder Identification
System PERFORM The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low-stress type.
5. Fit-up of groove welds (including joint geometry)
OBSERVE Joint preparation Dimensions (alignment, root opening, root face, bevel) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location) Backing type and fit (if applicable)
6. Configuration and finish of access holes
OBSERVE
7. Fit-up of fillet welds OBSERVE Dimensions (alignment, gaps at root) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location)
STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-2
TASK INSPECTION TYPE DESCRIPTION
8. Use of qualified welders PERFORM Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.
9. Control and handling of welding consumables OBSERVE Packaging
Electrode atmospheric exposure control
10. No welding over cracked tack welds
OBSERVE
11. Environmental conditions OBSERVE Wind speed within limits Precipitation and temperature
12. Welding Procedures Specification followed
OBSERVE Settings on welding equipment Travel speed Selected welding materials Shielding gas type/flow rate Preheat applied Interpass temperature maintained (min./max.)
Proper position (F, V, H, OH) Intermix of filler metals avoided
13. Welding techniques OBSERVE Interpass and final cleaning Each pass within profile limitations Each pass meets quality requirements
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – WELDING SECTION (CONTINUED)
STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-3
TASK INSPECTION TYPE 1 DESCRIPTION
14. Welds cleaned OBSERVE
15. Size, length, and location of all welds PERFORM Size, length, and location of all welds conform to the requirements of the detail drawings.
16. Welds meet visual acceptance criteria
PERFORM AND
DOCUMENT
Crack prohibition Weld/base-metal fusion Crater cross section Weld profiles Weld size Undercut Porosity
17. Arc strikes PERFORM
18. k-area PERFORM When welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, visually inspect the web k-area for cracks.
19. Backing removed, weld tabs removed and finished, and fillet welds added where required
PERFORM
20. Repair activities PERFORM AND
DOCUMENT
21. Document acceptance or rejection of welded joint or member
PERFORM
END SECTION
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – BOLTING SECTION
STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.6-1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacture’s certifications available for fastener materials
PERFORM
2. Fasteners marked in accordance with ASTM requirements
OBSERVE
3. Proper fasteners selected for joint detail (grade, type, bolt length if threads are to be excluded from shear plane)
OBSERVE
4. Proper bolting procedure selected for joint detail
OBSERVE
5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
OBSERVE
6. Proper storage provided for bolts, nuts, washers, and other fastener components
OBSERVE
STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.6-2
TASK INSPECTION TYPE 1 DESCRIPTION
7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required
OBSERVE
8. Joint brought to the snug-tight condition prior to pretensioning operation
OBSERVE
9. Fastener component not turned by the wrench prevented from rotating
OBSERVE
10. Bolts are pretensioned in accordance with RCSC Specification, progressing systematically from the most rigid point toward the free edges
OBSERVE
STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360-10: Table C-N5.6-3
TASK INSPECTION TYPE 1 DESCRIPTION
11. Document acceptance or rejection of all bolted connections
DOCUMENT
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL - NON DESTRUCTIVE TESTING SECTION
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Section N5.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified nondestructive testing personnel
PERFORM Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS D1.8 clause 7.2
2. Welded joints subject to fatigue
OBSERVE Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.
3. Weld tab removal sites OBSERVE At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam-to-column joints receiving UT
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL - OTHER INSPECTIONS
OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 341-16: Tables J8.1 & J10.1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Anchor rods and other embedments supporting structural steel
PERFORM Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.
2. Fabricated steel or erected steel frame
OBSERVE Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
3. Reduced beam sections (RBS) where/if occurs
DOCUMENT Contour and finish Dimensional tolerances
4. Protected zones DOCUMENT No holes or unapproved attachments made by fabricator or erector
5. H-piles where/if occurs DOCUMENT No holes or unapproved attachments made by the responsible contractor
GEOTECHNICAL - DRIVEN DEEP FOUNDATION ELEMENTS SECTION
DEEP DRIVEN FOUNDATION CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.7
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify element materials, sizes and lengths comply with requirements
CONTINUOUS
2. Inspect driving operations and maintain complete and accurate records for each element
CONTINUOUS
3. Verify placement locations and plumbness, confirm type and size of hammer, record number of blows per foot of penetration, determine required penetrations to achiever design capacity, record tip and butt elevations and document any damage to foundation element
CONTINUOUS
4. Determine capacities of test elements and conduct additional load tests if required.
CONTINUOUS
5. For steel or concrete elements, perform additional special inspections in accordance with the Steel and Concrete sections in this schedule
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.