P678 Dry Dock 8 SW System Amendment 0009.docx
DOCX document 58 KB Posted
- Attached to
- P-678 Dry Dock 8 Saltwater System for CVN-78, Norfolk Naval Shipyard, Portsmouth, Virginia
- Solicitation number
- N40085-22-R-2598
About this file
This amendment to a federal contract modifies the specifications and drawings for a solicitation seeking a contractor to provide a saltwater system for Dry Dock 8 at Norfolk Naval Shipyard in Portsmouth, Virginia. The scope of work includes replacing the main dewatering pumps and drainage pumps, installing temporary pumpwell suction culvert plugs, and coordinating work with concurrent projects to retrofit Caisson 8 and repair Berths 40 and 41. Key dates include a ship docked at Dry Dock 8 until end of November 2022, work starting no earlier than January 2023, culvert plug work by July 2024, main pump testing between July and September 2024, and an overall completion date of August 2024. The Navy is the contracting agency, with the Naval Facilities Engineering Command as party to the solicitation.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P678 Dry Dock 8 Saltwater System Amendment 0009
P678 DRY DOCK 8 AMENDMENT CONTINUATION SHEET
CONTRACT SPECIFICATIONS
SECTION 01 14 00.00 22 WORK RESTRICTIONS
1.4 SPECIAL SCHEDULING REQUIREMENTS
Revise 1.4.d (3) to the following:
“1.4.d (3) NNSY will install temporary construction office trailers on the southside of the dry dock approximately three to four months prior to construction completion to prepare for a ship docking. Coordinate construction operations near these areas with the Contracting Officer.”
Under paragraph 1.4.d (3), add the following item:
“1.4.d (4) Contractor must not stage or utilize Berths 40 & 41 for any work involved with this project. Due to laydown requirements of concurrent projects (see RELATED PROJECTS below), the Contractor must utilize the P678 Dry Dock 8 Saltwater System laydown areas as indicated or as designated by the Contracting Officer.”
After subparagraph 1.4.e add the following items:
“f. A ship will be drydocked at Dry Dock 8 until the end of November 2022. The Contractor is not authorized to start onsite demolition or construction work before 16 January 2023.
g. The Contractor must coordinate the work of this project with the projects listed under paragraph RELATED PROJECTS below.
h. Coordinate construction of the temporary Pumpwell 8 suction culvert plugs to occur prior to Caisson 8 (See RELATED PROJECTS below - Special Project RM 19-0182 NNSY Caisson 8 Install Flood Through Valves) being removed from Government property for renovations. Anticipated Caisson 8 removal is November 2023. Anticipated Caisson 8 return is July 2024.
i. The Government will flood the dry dock to flip the Caisson for retrofit work on “Side B” no earlier than 1 May 2023 and no later than 5 June 2023. The dock will be dry until this time, and temporary suction culvert plug work may proceed prior to “Side B” retrofit.
j. After the Caisson is flipped to “Side “B”, the Caisson 8 Contractor will dewater Dry Dock 8 so Caisson in-dock work can proceed, no later than 1 July 2023.
k. The Government will flood the dock for the Caisson to be removed and transported to a shipyard for remaining modifications, no later than 13 November 2023. The dock will be flooded until the Caisson returns, no later than 17 July 2024. The Pumpwell 8 Main Dewatering Pump work and Drainage pumps DP-1, DP-2 and DP-3 work shall complete by 17 July 2024.
k. Once the Caisson is returned and seated in the dry dock, the P678 Contractor will be required to dewater the dock utilizing temporary pumps in order to remove the temporary suction plugs.
l. The reconstruction of the Berth 41 dewatering flume by Project RM22-0455 Repair Berths 40 and 41 (See RELATED PROJECTS below) will complete by 30 June 2024 such that the dewatering flume can be utilized for testing of the Main Dewatering pumps of this project and the Caisson 8 Flood Through Valves. The Beneficial Occupancy date (BOD) for Project RM22-0455 Repair Berths 40 and 41 BOD is anticipated no later than 23 August 2024.
m. Once the suction culvert plugs are removed, the Government will flood the dock for the Main Dewatering Pumps to be tested. Once these tests are completed, approved by the Contracting Officer and the pumps are accepted by the Government, the Government will operate the Main Dewatering Pumps so that certification testing of the Caisson 8 Flood Through Valves can begin. There will be two complete dewaterings required for the Caisson 8 certification testing.
n. Coordinate the North and South Flooding flume work with the project, RM22-0455 Repair Berths 40 and 41(See RELATED PROJECTS below). The North and South flooding flume work shall not commence until Beneficial Occupancy of Berth 40 and Berth 41 are achieved.
1.5 RELATED PROJECTS
Replace paragraph 1.5 in its entirety with the following:
“Three additional construction projects will take place concurrently with this project at Dry Dock 8.
(1) Special Project RM 19-0182 NNSY Caisson 8 Install Flood Through Valves: Award - September 2022; Beneficial Occupancy – October 2024.
(2) RM 18-0623 (WON 1632158) Replace Dry Dock 8 Main Dewatering Pump #2: Award – April 2021; Beneficial Occupancy November 2024.
(3) RM22-0455 Repair Berths 40 and 41: Award – July 2022; Beneficial Occupancy August 2024.”
Additionally, a NNSY project to replace Dry Dock 8 Main Dewatering Pump 3 including Pumpwell 8 Miscellaneous Repairs is anticipated to be awarded in June 2023 with a completion date of February 2025.”
SECTION 02 6113 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
Replace paragraph 3.6.2 Sampling Liquid with the following:
Liquid / groundwater collected from excavations shall be sampled at a frequency of once for every 500 gal of liquid collected, or once a tank is considered full. Samples must be tested in accordance with SECTION 01 57 19.00 22 TEMPORARY ENVIRONMENTAL CONTROLS.
Liquid with contaminant levels that exceed action levels shall be treated offsite. Analyses for contaminated liquid to be taken to an offsite treatment facility shall conform to local, state, and federal criteria as well as to the requirements of the treatment facility. Documentation of all analyses performed shall be furnished to the Contracting Officer. Additional sampling and analysis to the extent required by the approved offsite treatment, storage or disposal (TSD) facility receiving the material shall be the responsibility of the Contractor and subject to approval by the Contracting Officer.
CONTRACT DRAWINGS
Phase 1 Drawings
(1) NAVFAC Dwg. No. 12857519 (1-GC101) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(2) NAVFAC Dwg. No. 12857521 Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(3) NAVFAC Dwg. No. 12857554 (1-CD112) To the end of Keynote 19 add the following: “PRESERVE AND PROTECT FOUNDATION FOR RE-USE. ASSUME 10'x 10' x 2' DEEP FOUNDATION.”
(4) NAVFAC Dwg. No. 12857555 (1-CD113) To the end of Keynote 19 add the following: “PRESERVE AND PROTECT FOUNDATION FOR RE-USE. ASSUME 10'x 10' x 2' DEEP FOUNDATION.”
(5) NAVFAC Dwg. No. 12857556 (1-CD114) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
Replace Keynote 10 with the following: “PERMANENTLY ABANDON, DISCONNECT AND REMOVE PORTION OF STORM DRAIN PIPE AS NEEDED TO ALLOW FOR CONSTRUCTION ACTIVITIES. REMOVE ASSOCIATED STORM DRAIN STRUCTURES.”
Add Keynote 19 to the sheet: “DISCONNECT AND REMOVE LIGHT POLE. STORE FOR RE-INSTALLATION. PRESERVE AND PROTECT FOUNDATION FOR RE-USE. ASSUME 10'x 10' x 2' DEEP FOUNDATION.” Apply to existing lightpole located in A4 south of Misc Office Trailer 1.
To the end of Keynote 24 add the following: “REPLACE WITH ASPHALT PAVEMENT. SEE DETAIL A3/1-CS501.”
(6) NAVFAC Dwg. No. 12857557 (1-CD115) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
To the end of Keynote 24 add the following: “REPLACE WITH ASPHALT PAVEMENT. SEE DETAIL A3/1-CS501.”
(7) NAVFAC Dwg. No. 12857564 (1-CS112) Replace Keynote 16 with the following: “RE-INSTALL LIGHT POLE ON EXISTING FOUNDATION. RE-CONNECT ELECTRIC SERVICE.”
(8) NAVFAC Dwg. No. 12857565 (1-CS113) Replace Keynote 16 with the following: “RE-INSTALL LIGHT POLE ON EXISTING FOUNDATION. RE-CONNECT ELECTRIC SERVICE.”
(9) NAVFAC Dwg. No. 12857566 (1-CS114) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(10) NAVFAC Dwg. No. 12857567 (1-CS115) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
Add Keynote 16 as follows: “RE-INSTALL LIGHT POLE ON EXISTING FOUNDATION. RE-CONNECT ELECTRIC SERVICE.” Apply to existing light pole indicated by Keynote 19 on 1-CD114.
(11) NAVFAC Dwg. No. 12857578 (1-CU114) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(12) NAVFAC Dwg. No. 12857579 (1-CU115) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(13) NAVFAC Dwg. No. 12857589 (1-CU211) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(14) NAVFAC Dwg. No. 12857590 (1-CU212) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(15) NAVFAC Dwg. No. 12857596 (1-CU314) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(16) NAVFAC Dwg. No. 12857597 (1-CU321) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(17) NAVFAC Dwg. No. 12857599 (1-CG114) Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(18) NAVFAC Dwg. No. 12857661 (1-MD102) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(19) NAVFAC Dwg. No. 12857662 (1-MD103) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(20) NAVFAC Dwg. No. 12857663 (1-MD104) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(21) NAVFAC Dwg. No. 12857664 (1-MD105) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(22) NAVFAC Dwg. No. 12857665 (1-MD115) Delete Keynote X1 and associated cloud located at DD8 Pumpwell 8. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(23) NAVFAC Dwg. No. 12857670 (1-MP102), NAVFAC Dwg. No. 12857608 (1-SD100), NAVFAC Dwg. No. 12857610 (1-SD103), NAVFAC Dwg. No. 12857611 (1-SD104), NAVFAC Dwg. No. 12857613 (1-SD201), NAVFAC Dwg. No. 12857614 (1-SD202), NAVFAC Dwg. No. 12857616 (1-S-100), NAVFAC Dwg. No. 12857618 (1-S-103), NAVFAC Dwg. No. 12857619 (1-S-104), NAVFAC Dwg. No. 12857620 (1-S-201), NAVFAC Dwg. No. 12857621 (1-S-202), Delete Keynote X1 (CLIN002) and associated clouds. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(24) NAVFAC Dwg. No. 12857671 (1-MP103) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(25) NAVFAC Dwg. No. 12857672 (1-MP104) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(26) NAVFAC Dwg. No. 12857673 (1-MP105) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(27) NAVFAC Dwg. No. 12857674 (1-MP115) Delete Keynote X1 and associated cloud at PW8-DP-1,2,3 and PW8-SP-1,2,3,4 discharge piping exiting DD8 Pumpwell 8. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(28) NAVFAC Dwg. No. 12857680 (1-MP402) Delete Keynote X1 and associated cloud. Work identified no longer precluded from phase 1 due to consolidation of project schedule. Coordinate P678 construction schedule to accommodate Main Dewatering Pump and Caisson testing in accordance with Section 01 14 00 WORK RESTRICTIONS. Testing is anticipated to occur between July and September 2024.
(29) NAVFAC Dwg. No. 12857688 (1-M-601) Pump Schedule: Delete Note #2 from pumps PW8-SP-1, 2, 3, & 4.
Pump Schedule: Add New Note #4 to pumps PW8-SP-1, 2, 3, & 4.
Pump Schedule: Schedule notes add the following: “4. PROVIDE SAFETY SWITCH/STARTER COMBINATION; REFER TO ELECTRICAL.”.
(30) NAVFAC Dwg. No. 12857721 (1-EP601) PW8-MCC-DP: Update elevation and schedule to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
PW8-MCC-MDP: Update elevation and schedule to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(31) NAVFAC Dwg. No. 12857723 (1-EP701) PW8-MCC: Update one line diagram to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
PW8-MCC-MDP: Update one line diagram to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(32) NAVFAC Dwg. No. 12857636 (1-SS501) Replace Note 9 with the following: “OUTER CRANE RAILS TO BE REMOVED AND REPLACED TO SERVE AS “DUMMY CRANE RAILS” GROUTED IN PLACE.”
Phase 2 Drawings
(1) NAVFAC Dwg. No. 12857799 (2-CD115) To the end of Keynote 45 add the following: “PRESERVE AND PROTECT FOUNDATION FOR RE-USE. ASSUME 10'x 10' x 2' DEEP FOUNDATION.”
(2) NAVFAC Dwg. No. 12857809 (2-CS115) Replace Keynote 16 with the following: “RE-INSTALL LIGHT POLE ON EXISTING FOUNDATION. RE-CONNECT ELECTRIC SERVICE.”
(3) NAVFAC Dwg. No. 12858048 (2-EP651) PS6-MCC-DP: Update elevation and schedule to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(4) NAVFAC Dwg. No. 12858050 (2-EP661) PS8-MCC-DP: Update elevation and schedule to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(5) NAVFAC Dwg. No. 12858052 (2-EP751) PS6-MCC-DP: Update one line diagram to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(6) NAVFAC Dwg. No. 12858054 (2-EP761) PS6-MCC-DP: Update one line diagram to reflect fusing/disconnect switching/vacuum contactor arrangement in lieu of circuit breakers.
(7) NAVFAC Dwg. No. 12857893 (2-SS501) Replace Note 9 with the following: “OUTER CRANE RAILS TO BE REMOVED AND REPLACED TO SERVE AS “DUMMY CRANE RAILS” GROUTED IN PLACE.”
Additional reference drawings for Pumpwell 8 accompany this Amendment as a separate file.
-- End of Amendment --