22R2598 Amendment 0009.pdf
PDF 157 KB Posted
- Attached to
- P-678 Dry Dock 8 Saltwater System for CVN-78, Norfolk Naval Shipyard, Portsmouth, Virginia
- Solicitation number
- N40085-22-R-2598
About this file
This document provides responses to questions on Amendment 0009 to solicitation N40085-22-R-2598 for the P-678 Dry Dock 8 Saltwater System project at the Norfolk Naval Shipyard in Portsmouth, Virginia. The Navy seeks to replace the saltwater piping system that services Dry Dock 8 and Building 1498. The amendment extends the proposal due date to June 15th, 2022 and provides responses to contractor questions on drawings, specifications and the price proposal form. Key project details include replacing approximately 1,800 linear feet of saltwater piping, demolishing and replacing concrete foundations, installing new guardrails and drainage structures, and upgrading pump control panels and motor control centers. The Navy clarifies its requirements around excavation, disposal of materials, electrical equipment, and treatment of groundwater from excavations.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
AMENDMENT TO SOLICITATION NO. N40085-22-R-2598 P-678 DRY DOCK 8 SALTWATER SYSTEM FOR CVN-78, NORFOLK NAVAL
SHIPYARD, PORTSMOUTH, VA
The purpose of this Amendment is to provide PPI responses and the corresponding attachments.
The current proposal due date is 15 June 2022 at 2:00 PM local time.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Jun-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008522R2598
X 9B. DATED (SEE ITEM 11)
29-Mar-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Jun-2022
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008522R2598
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0009
The purpose of this Amendment is to provide the following:
1. PPI responses
2. P678 Dry Dock 8 SW System Amendment 0009
3. TIF files
4. Price Proposal Form_revision 2
REFERENCE QUESTION GOVERNMENT RESPONSE
Page Section Para.
Was steel sheet pile used during the construction of Pump Well 8? If so was any sheeting left in place and what was the tip elevation of the sheet?
See response to PPI below
Can an additional drawings for construction methods used for Pump Well 8 be provided?
Original construction drawings for PW- 8 will be provided for reference as part of the Amendment. The drawing file will be large and will be transmitted separately.
1-CS113 Note 16 states "Light Pole reinstalled on new footing in-kind" Please provide details on existing foundation.
Information on existing foundation size will be provided.
Will NNSY accept MV fusing in the place of breakers for PW8-MCC-DP, PW8-MCC-MPD, PS6-MCC, &PS8-
MCC?
MCC specification callout is correct.
Intention was for MCCs to be equipped with current limiting fuses/disconnect switches/vacuum contactors typical of a UL347 MCC design. Drawings will be updated to reflect specificationss.
Solicitatio n
Due to the complexity of the work, questions arising from our review of the douments, and from that of our subcontractors', we respectfully request a two-week extension of the proposal due date to June 8th, 2022. This will allow us to addres responses received and better coordinate with subcontractors to provide a quality proposal to NAVFAC.
Please see Amendment 0007.
How will the disposal of suitable materials not needed for onsite backfill be paid for?
A CLIN is not offered for the disposal of excavated suitable materials.
1-B-001, 1-C-002, CD107 -
CD115
Site Demolition Note 10 on sheet 1-C- 002 states the "The Contractor must assume that all asphalt pavement has reinforced concrete base beneath it that must be demolished during pavement demolition." CD107 to CD115 note 1 directs the contractor to sawcut and remove asphalt pavement. Assume 8" thick asphalt overlay on 8" thick reinforced concrete. However the borings shown on sheet 1-B-001 do not align with the site demolition notes. Is it the intent for the contractor to base their bids on the plan notes or shall the boring logs be taken into account?
It is the intent for the contractor to base bids on the plan notes. Boring logs depict conditions only at the specific boring locations. Paving depths throughout the site may differ from what is shown in the logs.
1-CD114,
1-CD115,
1-CS114,
1-CS115
Sheet CD114 & CD115 note 24 directs the contractor to sawcut and remove concrete pavement 12 inches thick.
Will these areas recieve new Bituminous Pavement? There isn't any new work shown on the CS drawings in these areas.
Provide new asphalt pavement where existing 12" thick concrete is removed.
Price Proposal
Form
CLIN0003
AG
Please provide the KVA rating and oil capacity of the three transformers to be drained and disposed of.
We beieve there are no PCB containing transformers to dispose of in the project. In the Price Proposal Form, under CLIN 0003AG, replace number of units "3" with "0".
1-CS501 Note 9 on sheet 1-CS501 directs the contractor to abandon and replace outside rails with bituminous pavement.
Will Crane Rail that does not get reinstalled be disposed of by the contractor? Will sections of rail outside and Crane Rail Foundation replacement be left in place?
Wrong drawing refrenced; comment applies to 1-SS501/2-SS502. Based on NAVFAC discussions, the outer crane rails cannot be paved over for historical reasons (as designed). The outer rails that are removed for crane rail foundation reconstruction need be replaced as "dummy rails," grouted into place for aesthetical purposes only.
"Dummy rails" are not to be connected back to the foundation, but rather shimmed and grouted in the existing pocket.
1-CG114,
1-CD114
Will existing drainage structures that are no longer part of the proposed drainage system be removed or abandoned in place?
Remove existing drainage structures that are no longer part of the proposed drainage system.
1-M-601 The Pump Schedule indicates to provide Soft-starts for the 4 each Sump Pumps PW8-SP-1, 2, 3, 4, and to refer to Electrical Drawings. Drawing 1- EP101 indicates combination 100 amp Safety Switch/Starter's to be provided.
Please confirm which is correct.
Provide Safety Switch/Starter combination as indicated on electrical drawing 1-EP101. Pump scheduled on 1-M-601 to be corrected.
2-EP751
& 2-
EP761
Spec 26 20 00 2.23.2
The specification indicates current limiting fuses with a disconnect switch and vacuum contactor arrangement, typical of a UL347 MCC design. The contract drawings seem to indicate a "fixed" breaker and not the fuse, switch, and contactor arrangement.
Please confirm the construction requirements for the disconnect device feeding the soft-starts in the MV MCC's for the project.
MCC specification is correct. MCCs will be equipped with current limiting fuses/disconnect switches/vacuum contactors typical of a UL347 MCC design. Drawings will be updated to reflect specifications.
Price Proposal
Form
On the price proposal form, CLIN 001AF, lists the ACM Exterior Sealant item by the square foot, but CLIN 003AH lists the ACM Exterior Sealant by the linear foot. Please clarify if the item is by the square foot or linear foot and adjust bid quantities accordingly.
CLIN 0001AF is correct for the sqarue foot unit. The CLIN description states "exterior stucco or cementitious asbestos contatining material (ACM) at Building 272." CLIN 0003H is also correct for the linear feet of ACM exterior sealant on Building 1498.
Price Proposal
Form
The price proposal form shows the South flooding flume work to be included under CLIN 0002AC. Which CLIN should the North flooding flume work be included under?
The North Flooding Flume work appears in the phase 2 drawings and is included in CLIN 0003.
1-MD301 Key Note 124 last sentence states, "If pipe condition is determined to be poor replace." Should the Contractor carry the cost of replacement in their bid or will this be handled as extra work if replacement is required?
If replacement is determined to be required this will be handled as extra work.
52 52.225-11 Entire Clause
Per the bid documents, this project is subject to FAR 52.225-11 (Buy America). We have requested certification for the generator sets referenced in section 26 32 15.00 from our factory. After submitting documentation for compliance with this requirement to our factory, we have received a request from the compliance department, to see if we can reach out to the contract officer on the project to discuss the generators, detailed in specification sections 263215. Although the generators are manufactured in the United States, they are unable to certify that the generators would satisfy the conditions necessary to qualify as “domestic construction material” under the current version of FAR 52.225-11, due to uncertainty created by the special domestic contact requirements for products deemed to consist “predominantly of iron or steel or a combination of both” that was introduced into this requirement in 2021.
Bid per RFP.
The current version of FAR 52.225-11 contains special domestic content requirements for products that are determined to consist “predominantly of iron or steel or a combination of both.” Determining (i) whether a product falls into that category, and (ii) if so, whether it meets the definition of a “domestic construction material,” requires a level of visibility into the costs and origin of the steel and iron content of the generators that most manufacturers do not presently have.
Because we cannot confidently assess the cost of iron/steel content added by suppliers who may be several tiers removed from the manufacturer of record in the supply chain for the generators, we lack the information we believe is necessary to certify that these generators are "domestic construction material" under FAR 52.225-11.
Due to this, it is very difficult to certify that the generators are Domestic Construction material as shown under FAR 52.225-11. Based on this, we would like to ask if a determination could be made that the generators from all vendors are not considered “predominately iron and steel”, to help clarify this requirement and obtain clear certification of compliance with FAR 52.225-11?
6 02-61-13 3.6.2 Excavation and Handling of Contaminated Material paragraph 3.6.2 states that Containerized liquids must be treated offsite. Is it the intent for contaminated groundwater collected from excavations to be hauled offsite for disposal?
It is the intent to discharge groundwater on-site.
Will the contractor be permitted to dewater excavations onsite and pump into another open excavation or pit near the active work area?
Store liquid from excavations in containers. Refer to paragraph 3.5.3 of Section 02 61 13 and paragraph 3.1.2 of Section 31 23 00.00 20.
Drawing
2-SS501;
Structrual
Notes 6.B.16 and 6.B.18 on 2-S-001
Please confirm all structural steel pipe supports shown on drawing 2-SS501 and all post installed anchors associated with these supports are to be galvanized per Structural Notes 6.B.16 and 6.B.18 on drawing 2-S-001. If otherwise, please specify material and/or coating.
Correct as stated, all post installed anchor bolts associated with 2-SS501 are hot dip galvanized.
Note 1/2-
MD127-
2-MD135;
Note 2/2-
MS323;
Detail B1/2-
SS501
Note 1 on drawings 2-MD127 thru 2- MD135 indicates guardrail and associated anchors along gallery to be "demolished as required". Key Note 2 on 2-MS323 indicates 2" clearance between pipe and NEW guardrail. Is the intent to replace this guardrail along entire length of gallery (where saltwater piping is installed) with new guardrail per detail B1/2-SS501?
The new component cooling piping will be installed directly atop the existing curb which will force the existing guardrail to be removed and replaced with new guardrail outboard the curb.
The new guardrail will be fabricated to miss the pipe support locations along the length of the gallery.
Det B1/2-
SS501
Note 4/1- S-504
Please confirm any replacement guardrail along gallery level of drydock as shown in detail B1/2-SS501 is to be painted safety yellow over galvanize the same as all other guardrail/handrail on Project per Note 4/1-S-504.
Safety yellow is required.
Det C1/2-
MS501
Please confirm material type and finish for the 2 beams spanning between knee-brace supports (MPS-01) as shown in det C1/2-MS501.
Hot dip galvanized steel.
Dets A1 and C3 on
2MS521
Please confirm material type and finish for the fire piping protection cages shown in details A1 and C3 on
2MS521.
GALV SCH. 80 XS PIPE
Drawing
2-SS501;
Structrual
Note 6.B.13 on 2-S-001
Please confirm Pipe Supports shown on 2-SS501 are to be installed with galvanized anchors per Structural Note 6.B.13 on 2-S-001. (we only ask because other hardware related to drydock pipe supports shown in mechanical drawings are called out as
316SS)
Correct as stated, all post installed anchor bolts associated with 2-SS501 are hot dip galvanized.
(End of Summary of Changes)