This document is a quality control plan specification for a construction project to renovate the Dry Dock 2 Complex at the Portsmouth Naval Shipyard in Kittery, Maine. The specification outlines quality control requirements for the construction including establishing a quality control program, organization, plan, meetings, three phases of control, submittal review and approval, testing, inspections, documentation and non-compliance procedures. Key aspects of the quality control program include designating a QC manager and specialists to oversee definable features of work. It also requires preparatory and initial phase meetings, follow-up checks, additional meetings if quality issues arise, and maintaining testing, rework and as-built records. Subcontractors must participate in meetings and phases of control covering their scope of work.

View the file

Other files

File Type Posted
Attachment G Rev 5 18MAY21.pdf PDF
Amendment 0011.pdf PDF
Amendment 0010.pdf PDF
CD-101.pdf PDF
27 10 00.pdf PDF
S-505.pdf PDF
S-504.pdf PDF
Volume 2 - Architectural.pdf PDF
Attachment G Rev 4 14MAY21.pdf PDF
Volume 2 - E-501.pdf PDF
Volume 3 - Architectural.pdf PDF
C-101.pdf PDF
S-520.pdf PDF
Amendment 0009.pdf PDF
S-533.pdf PDF
C-107.pdf PDF
C-102.pdf PDF
Amended DWGs-PPI 198.pdf PDF
09 90 00.pdf PDF
08 71 00.pdf PDF
Amendment 0008.pdf PDF
A-405 A-407 A-410 A-412 A-413 A-421 A-516.pdf PDF
Attachment G Rev 3 12MAY21.pdf PDF
Appendix A_p.5-6_Tower 6.pdf PDF
Appendix A_p.1-2_Enclosure 8.pdf PDF
Appendix A_p.7-8_Tower 5.pdf PDF
Appendix A_p.3-4_Enclosure 5.pdf PDF
Amendment 0007.pdf PDF
Attachment F Rev 1.2 27APR21.pdf PDF
Amendment 0006.pdf PDF
Vol 2 Mechanical Fan Revisions.pdf PDF
11 14 00.pdf PDF
AMD 05 - 23 05 93.pdf PDF
Volume 3 A-503.pdf PDF
Vol 2 Mechanical - Temp Monitoring.pdf PDF
Amendment 0005.pdf PDF
Vol 2 S-550.pdf PDF
Vol 2 S-551.pdf PDF
Price Proposal Form Rev. 1.1 14APR21.pdf PDF
07 91 13.pdf PDF
23 00 00.pdf PDF
Volume 2 A-503.pdf PDF
Vol 3 Electrical and Controls Revisions.pdf PDF
05 05 20.00 27.pdf PDF
Vol 2 Electrical Fan Revisions.pdf PDF
23 05 93 Attachments.pdf PDF
Vol 3 S-515.pdf PDF
01 33 00 DD2 Complex Submittal Register.pdf PDF
Vol 2 Electrical and Controls Revisions.pdf PDF
AMD 05 - 40 95 00.pdf PDF
Show 40 more

Latest 50 of 131 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD#2 Complex Amendment 2021-04-05 Portsmouth Naval Shipyard, Kittery, ME

SECTION 01 45 00.00 20

QUALITY CONTROL (PWD ME)

07/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Quality Control (QC) Plan; G

Submit a Construction QC Plan prior to start of construction.

QC Manager Qualifications; G

QC Specialists; G

Project Engineer Qualifications; G

1.3 INFORMATION FOR THE CONTRACTING OFFICER

Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer.

The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, CQC Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.

Deliver the following to the Contracting Officer during Construction:

a. CQC Report: Email the report by 10:00 AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.

b. Contractor Production Report: Submit the report electronically by 10:00 AM the next working day after each day that work is performed and for every seven consecutive calendar days of no-work.

c. Preparatory Phase Checklist: Submit the report electronically in the

SECTION 01 45 00.00 20 Page 1 same manner as the CQC Report for each Preparatory Phase held.

d. Initial Phase Checklist: Submit the report electronically in the same manner as the CQC Report for each Initial Phase held.

e. QC Specialist Reports: Submit the report electronically by 10:00 AM the next working day after each day that work is performed.

f. Field Test Reports: Mail or hand-carry the original within two working days after the test is performed, attached to the original CQC Report and one copy attached to each QC Report copy.

g. Monthly Summary Report of Tests: Submit the report as an electronic attachment to the CQC Report at the end of each month.

h. Testing Plan and Log: Submit the report as an electronic attachment to the CQC Report, at the end of each month. A copy of the final Testing Plan and Log shall be provided to the OMSI/eOMSI preparer for inclusion into the OMSI/eOMSI documentation.

i. Rework Items List: Submit lists containing new entries daily, in the same manner as the CQC Report.

j. CQC Meeting Minutes: Within two working days after the meeting is held, submit the report as an electronic attachment to the CQC Report.

k. QC Certifications: As required by the paragraph entitled "QC Certifications."

l. Bridge Crane Fabrication QC Reports: Submit daily QC reports for crane fabrication to confirm the work is being performed in accordance with the contract requirements.

1.4 QC PROGRAM REQUIREMENTS

Establish and maintain a QC program as described in this section. The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, historic coordination drawings review and approval testing, completion inspections, and QC certifications and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this Contract. The QC program must cover on-site and off-site work and be keyed to the work sequence. Off-site work includes fabrication work including steel fabrication, ductwork fabrication, bridge crane fabrication, coatings, and is not restricted to major definable features of work. The Contractor must clearly identify the off-site work QC resources as part of the QC plan and program requirements. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager.

The QC Manager, Project Superintendent and Project Manager must work together effectively. Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job. The QC Manager will be subject to removal by the Contracting Officer for non-compliance with the QC requirements specified in the contract, faiure to perform the duties of the QC Manager specified herein or failure to manage the QC program.

SECTION 01 45 00.00 20 Page 2

1.4.1 Acceptance of the Construction Quality Control (QC) Plan

Acceptance of the QC Plan is required prior to the preconstruction meeting per specification 01 30 00.00 22 paragraph 1.7. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications. All QC organization personnel are subject to acceptance by the Contracting Officer. The Contracting Officer may require the removal of any individual for non-compliance with quality requirements specified in the Contract.

1.4.2 Preliminary Construction Work Authorized Prior to Acceptance

The only construction work that is authorized to proceed prior to the acceptance of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying.

1.4.3 Notification of Changes

Notify the Contracting Officer, in writing, of any proposed changes in the QC Plan or changes to the QC organization personnel, a minimum of 10 work days prior to a proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

1.5 QC ORGANIZATION

1.5.1 QC Manager

1.5.1.1 Duties

Provide a QC Manager at the work site to implement and manage the QC program. The QC Manager shall not perform the duties of Project Superintendent nor the duties of Project Manager or SSHO. The QC Manager is required to attend the partnering meetings, QC Plan Meetings, Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control, except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The QC Manager is responsible for managing and coordinating the three phases of control and testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities and shall not be the Special Inspector. The QC manager must be on site at all times.

1.5.1.2 Qualifications

An individual with a minimum of 10 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual must have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 , and have experience in the areas of hazard identification, safety compliance, and sustainability.

SECTION 01 45 00.00 20 Page 3

1.5.1.3 Construction Quality Management Training

In addition to the above experience and education requirements, the QC Manager must have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the QC Manager does not have a current certification, they must obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.

1.5.1.4 Alternate QC Manager Duties and Qualifications

Designate an alternate for the QC Manager at the work site to serve in the event of the designated QC Manager's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year. The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.

1.5.2 QC Specialists Duties and Qualifications

Provide a separate QC Specialist at the work site for each of the areas of responsibilities, specified in Part 3, Execution, of the technical sections, who shall assist and report to the QC Manager and who will have no duties other than their assigned quality control duties. QC Specialists are required to attend the Coordination and Mutual Understanding Meeting, QC meetings and be physically present at the construction site to perform the three phases of control and prepare documentation for each definable feature of work in their area of responsibility at the frequency specified below while the area of responsbility work is being performed. The frequency indicates the minimum number of full days on site the QC Specialist is expected to be on site and engaged on the project on a per week basis.

The QC Specialist must submit a site visit report within two working days of the site visit and the visit must detail the areas and elements of the project reviewed and highlight any deficiencies documented. The reports must be included in the daily report distribution.

A resume for each QC specalist must be submitted and approved by the Contracting Officer prior to beginning any work on the submittal development for the area of responsibility. The frequency of engagement of the QC specialist identified in the table below is to begin prior to development of construction submittals. All QC specialists must be a 1st tier subcontractor and independent third party with no affiliations to the Contractor performing the work.

Area of Responsibility Qualification/Experience in Area of Responsibility

Frequency

MECHANICAL SYSTEMS 10 YEARS MECHANICAL SYSTEMS 2 / WEEK

SECTION 01 45 00.00 20 Page 4

Area of Responsibility Qualification/Experience in Area of Responsibility

Frequency

BUILDING ENVELOPE -

FLASHING & WATER/AIR

INFILTRATION

10 YEARS WALL SYSTEM

CONSTRUCTION & FLASHING

2 / WEEK

CONTROLS SYSTEMS 10 YEARS INDUSTRIAL CONTROLS 2 / MONTH

MOVABLE ROOFS 10 YEARS INDUSTRIAL CONTROLS &

MACHINES EXPERIENCE

2 / WEEK

BRIDGE CRANES 10 YEARS BRIDGE CRANE

FABRICATION EXPERIENCE

2 / MONTH

1.5.3 Project Engineer(s)

Provide a Project Engineer(s) at the work site to identify engineering problems and ensure solutions are implemented. The Project Engineer(s) shall not perform the duties of QC Manager nor the duties of the Project Superintendent nor the duties of the Project Manager or SSHO. The Project Engineer(s) is required to attend the partnering meetings, QC Plan Meetings, Coordination and Mutual Understanding Meeting, NAVFAC Red Zone meetings, conduct weekly projet status meetings, assist with the three phases of control, except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The Project Engineer is responsible for assisting and coordinating the three phases of control and testing laboratory personnel and any other inspection and testing personnel required by this Contract. The Project Engineer or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.5.3.1 Project Engineer Qualifications

An individual with a minimum of 5 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual must have at least 2 years' experience as a Project Engineer. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability. Any replacement personnel shall have the same or better qualifications than the previous individual. The resumes for the personnel must provide a summary of projects of similar size and responsibility.

1.5.3.2 Construction Quality Management Training

In addition to the above experience and education requirements, the Project Engineer must have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the Project Engineer does not have a current certification, they must obtain the CQM for Contractors

SECTION 01 45 00.00 20 Page 5 course certification within 90 calendar days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.

1.6 QUALITY CONTROL (QC) PLAN

1.6.1 Construction Quality Control (QC) Plan

1.6.1.1 Requirements

Provide, for acceptance by the Contracting Officer, a Construction QC Plan submitted in a three-ring binder that includes a table of contents, with major sections identified with tabs, with pages numbered sequentially:

a. QC ORGANIZATION: A chart showing the QC organizational structure.

b. NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, for each person in the QC organization. Include the CQM for Contractors course certifications for the QC Manager and Alternate QC Manager as required by the paragraphs entitled "Construction Quality Management Training" and "Alternate QC Manager Duties and Qualifications".

c. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.

d. OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide. Example: The structural engineer who designs the HVAC skid system.

e. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager and stating that they are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility of the QC Manager and Alternate QC Manager to implement and manage the three phases of control, and their authority to stop work which is not in compliance with the Contract. Letters of direction are to be issued by the QC Manager to all other QC Specialists outlining their duties, authorities, and responsibilities. Include copies of the letters in the QC Plan.

f. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as specified in Section 01 33 00 SUBMITTAL

PROCEDURES.

g. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs entitled "Accreditation Requirements", as applicable.

h. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test.

SECTION 01 45 00.00 20 Page 6

Use Government forms to log and track tests.

i. PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track, and complete rework items. Use Government forms to record and track rework items.

j. DOCUMENTATION PROCEDURES: Use Government form.

k. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines and is an item or activity on the construction schedule. Include in the list of DFOWs, but not be limited to, all critical path activities on the NAS. Include all activities for which this specification requires QC Specialists or specialty inspection personnel. Provide separate DFOWs in the Network Analysis Schedule for each design development stage and submittal package.

l. PROCEDURES FOR PERFORMING THE THREE PHASES OF CONTROL: Identify procedures used to ensure the three phases of control to manage the quality on this project. For each DFOW, a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. Conduct the Preparatory and Initial Phases and meetings with a view towards obtaining quality construction by planning ahead and identifying potential problems for each DFOW.

m. PERSONNEL MATRIX: A personnel matrix showing for each section of the specification who will review and approve submittals, who will perform and document the three phases of control, and who will perform and document the testing.

n. PROCEDURES FOR COMPLETION INSPECTION: Procedures for identifying and documenting the completion inspection process. Include in these procedures the responsible party for punch out inspection, pre-final inspection, and final acceptance inspection.

o. TRAINING PROCEDURES AND TRAINING LOG: Procedures for coordinating and documenting the training of personnel required by the Contract.

Include a sample record of training for reporting what systems were included in the training, who provided the training, when and where the training was performed and who attended the training.

p. ORGANIZATION AND PERSONNEL CERTIFICATIONS LOG: Procedures for coordinating, tracking and documenting all certifications on subcontractors, testing laboratories, suppliers, personnel, etc. QC Manager will ensure that certifications are current, appropriate for the work being performed, and will not lapse during any period of the contract that the work is being performed.

q. DAILY REPORT FORM: Template that includes fields for the following:

1) Date.

2) Sequential report number.

3) Weather and temperature.

4) Number of personnel on site by trade or by subcontract.

5) Kind and number of major equipment on site.

6) Tests performed and their results, if known.

7) Materials and equipment delivered to the site and their conditions.

SECTION 01 45 00.00 20 Page 7

8) Names, affiliations, and positions of visitors to the site with brief explanations of the reasons for visits.

9) Brief description of each work activity, noting items that were completed that day.

10) Items of work that need attention at a later date, and why.

11) Any accidents and injuries.

12) Items of concern with respect to maintenance of quality.

13) Any other items of significance.

r. OFF-SITE QC COVERAGE: Identify the off-site work QC resources provided for all off-site fabrication locations and the procedures utilized to maintain communication between subcontractors and prime contractor to ensure QC requirements are maintained. Plan shall identify the reports that will be submitted with the daily reports to document the off-site QC coverage including the work performed and any deficiencies.

1.7 QC PLAN MEETINGS

Prior to submission of the QC Plan, the QC Manager will meet with the Contracting Officer to discuss the QC Plan requirements of this Contract.

The purpose of this meeting is to develop a mutual understanding of the QC Plan requirements prior to plan development and submission and to agree on the Contractor's list of DFOWs.

1.8 COORDINATION AND MUTUAL UNDERSTANDING MEETING

After submission of the QC Plan, and prior to the start of construction, the QC Manager will meet with the Contracting Officer to present the QC program required by this Contract. When a new QC Manager is appointed, the coordination and mutual understanding meeting shall be repeated.

1.8.1 Purpose

The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, design intent, environmental requirements and procedures, coordination of activities to be performed, special inspections, and the coordination of the Contractor's management, production, and QC personnel. At the meeting, the Contractor will be required to explain in detail how three phases of control will be implemented for each DFOW, as well as how each DFOW will be affected by each management plan or requirement as listed below:

a. Waste Management Plan.

b. IAQ Management Plan.

c. Procedures for noise and acoustics management.

d. Environmental Protection Plan.

e. Environmental regulatory requirements.

1.8.2 Coordination of Activities

Coordinate activities included in various sections to assure efficient and orderly installation of each component. Coordinate operations included under different sections that are dependent on each other for proper

SECTION 01 45 00.00 20 Page 8 installation and operation. Schedule construction operations with consideration for indoor air quality as specified in the IAQ Management Plan.

1.8.3 Attendees

As a minimum, the Contractor's personnel required to attend include an officer of the firm, the Project Manager, Project Superintendent, QC Manager, Alternate QC Manager, QC Specialists, A/E, Environmental Manager, and subcontractor representatives or approved by the Contracting Officer.

Each subcontractor who will be assigned QC responsibilities shall have a principal of the firm at the meeting. Minutes of the meeting will be prepared by the QC Manager and signed by the Contractor, the A/E and the Contracting Officer. Provide a copy of the signed minutes to all attendees and shall be included in the QC Plan.

1.9 QC MEETINGS

After the start of construction, conduct weekly QC meetings by the QC Manager at the work site with the Project Superintendent, and the foremen who are performing the work of the DFOWs. The QC Manager shall prepare the minutes of the meeting and provide a copy to the Contracting Officer within one working day after the meeting. The Contracting Officer may attend these meetings. As a minimum, accomplish the following at each meeting:

a. Review the minutes of the previous meeting.

b. Review the schedule and the status of work and rework.

c. Review the status of submittals.

d. Review the work to be accomplished in the next two weeks and documentation required.

e. Resolve QC and production problems (RFI, etc.).

f. Address items that may require revising the QC Plan.

g. Review Accident Prevention Plan (APP).

h. Review environmental requirements and procedures.

i. Review Waste Management Plan.

j. Review IAQ Management Plan.

k. Review Environmental Management Plan.

l. Review the status of training completion.

m. Review the progress of As-Builts and O&M Documentation.

n. Review Non-Compliance Notices and any actions required to address non-complaint work/actions.

1.10 THREE PHASES OF CONTROL

Adequately cover both on-site and off-site work with the Three Phases of

SECTION 01 45 00.00 20 Page 9

Control and include the following for each DFOW.

1.10.1 Preparatory Phase

Notify the Contracting Officer at least five two work ing days in advance of each preparatory phase meeting. Meeting invites must be provided to the projet team for the prepatory phase meetings. The meeting will be conducted by the QC Manager and attended by the QC Specialists, the Project Superintendent, SSHO, and the foreman responsible for the DFOW or as approved by the Contracting Officer. When the DFOW will be accomplished by a subcontractor, that subcontractor's foreman shall attend the preparatory phase meeting. Document the results of the preparatory phase actions in the daily Contractor Quality Control Report and in the Preparatory Phase Checklist.

The scheduling of meetings can only be initiated when a complete agenda demonstrating all the preparatory requirements have been completed and the associated documentation provided.

Perform the following prior to beginning work on each DFOW:

a. Review each paragraph of the applicable specification sections.

b. Review the Contract drawings.

c. Verify that field measurements are as indicated on construction and/or shop drawings before confirming product orders, in order to minimize waste due to excessive materials.

d. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required.

e. Review the testing plan and ensure that provisions have been made to provide the required QC testing.

f. Examine the work area to ensure that the required preliminary work has been completed.

g. Coordinate the schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.

h. Arrange for the return of shipping/packaging materials, such as wood pallets, where economically feasible.

i. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data.

j. Discuss specific controls used and construction methods, construction tolerances, workmanship standards, layout/survey controls (horizontal and vertical controls) necessary, and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.

k. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Material Safety Data Sheets (MSDS) are submitted.

SECTION 01 45 00.00 20 Page 10

l. When the DFOW will be accomplished by a subcontractor, that subcontractor's foreman shall attend the Initial phase meeting.

1.10.2 Initial Phase

Notify the Contracting Officer at least five two work days in advance of each initial phase. When construction crews are ready to start work on a DFOW, conduct the initial phase with the QC Specialists, the Project Superintendent, SSHO, and the foreman responsible for that DFOW. Observe the initial segment of the DFOW to ensure that the work complies with Contract requirements. Document the results of the initial phase in the daily CQC Report and in the Initial Phase Checklist. Repeat the initial phase for each new crew to work on-site, or when acceptable levels of specified quality are not being met.

The scheduling of meetings can only be initiated when a complete agenda demonstrating all the initial phase requirements have been completed and the associated documentation provided.

Perform the following for each DFOW:

a. Establish the quality of workmanship required.

b. Resolve conflicts.

c. Ensure that testing is performed by the approved laboratory.

d. Check work procedures for compliance with the APP and the appropriate AHA to ensure that applicable safety requirements are met.

1.10.3 Follow-Up Phase

Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily CQC Report:

a. Ensure the work is in compliance with Contract requirements.

b. Maintain the quality of workmanship required.

c. Ensure that testing is performed by the approved laboratory.

d. Ensure that rework items are being corrected.

e. Ensure manufacturers representatives have performed necessary inspections if required and perform safety inspections.

1.10.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same DFOW if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a DFOW is resumed after substantial period of inactivity, or if other problems develop. Conduct additional preparatory and initial phase meetings on the same Definable Feature of Work (DFOW) for all work that is on-going where one or more of the following circumstances apply:

1. If there are any quality control issues or if the work is determined

SECTION 01 45 00.00 20 Page 11 to be unacceptable.

2. The quality control personnel are not the same that were initially briefed at the original meetings.

3. The on-site production supervision or subcontractor/work crew have changed.

4. Work on a DFOW is resumed after a substantial period (1 month) of inactivity.

5. The Contracting Officers Representative determines additional meetings are needed to address any other problems.

6. If there are any deviations/changes/modifications to the scope of the DFOW elements modified from the original meeting.

7. If there are any changes to the methods of execution, weather conditions that may impact the execution or quality of the work.

1.10.5 Notification of Three Phases of Control for Off-Site Work

Notify the Contracting Officer at least two weeks prior to the start of the preparatory and initial phases. The Contractor must track off-site work in the three-week look ahead schedule.

1.11 SUBMITTAL REVIEW AND APPROVAL

Procedures for submission, review and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES.

1.12 TESTING

Except as stated otherwise in the specification sections, perform sampling and testing required under this Contract. The testing and retesting shall be performed at no additional cost to the Government.

1.12.1 Accreditation Requirements

Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory's scope of accreditation must include the appropriate ASTM standards (E 329, C 1077, D 3666, D 3740, A 880, E 543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA.

The policy applies to the specific laboratory performing the actual testing, not just the Corporate Office.

1.12.2 Laboratory Accreditation Authorities

Laboratory Accreditation Authorities include the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology at http://ts.nist.gov/ts/htdocs/210/214/214.htm , the American Association of State Highway and Transportation Officials (AASHTO) program at http://www.transportation.org/aashto/home.nsf/frontpage , International Accreditation Services, Inc. (IAS) at http://www.iasonline.org , U. S. Army Corps of Engineers Materials Testing Center (MTC)at http://www.wes.army.mil/SL/MTC/ , the American Association for Laboratory Accreditation (A2LA) program at http://www.a2la.org/ , the Washington Association of Building Officials (WABO) at http://www.wabo.org/ (Approval authority for WABO is limited to projects within Washington State), and the Washington Area Council of Engineering Laboratories

SECTION 01 45 00.00 20 Page 12

(WACEL) at http://www.wacel.org/labaccred.html (Approval authority by WACEL is limited to projects within Facilities Engineering Command (FEC) Washington geographical area).

1.12.3 Capability Check

The Contracting Officer retains the right to check laboratory equipment in the proposed laboratory and the laboratory technician's testing procedures, techniques, and other items pertinent to testing, for compliance with the standards set forth in this Contract.

1.12.4 Test Results

Cite applicable Contract requirements, tests or analytical procedures used. Provide actual results and include a statement that the item tested or analyzed conforms or fails to conform to specified requirements. If the item fails to conform, notify the Contracting Officer immediately.

Conspicuously stamp the cover sheet for each report in large red letters "CONFORMS" or "DOES NOT CONFORM" to the specification requirements, whichever is applicable. Test results must be signed by a testing laboratory representative authorized to sign certified test reports.

Furnish the signed reports, certifications, and other documentation to the Contracting Officer via the QC Manager. Furnish a summary report of field tests at the end of each month, per the paragraph entitled "INFORMATION

FOR THE CONTRACTING OFFICER".

1.12.5 Test Reports and Monthly Summary Report of Tests

Furnish the signed reports, certifications, and a summary report of field tests at the end of each month to the Contracting Officer. Attach a copy of the summary report to the last daily Contractor Quality Control Report of each month. Provide a copy of the signed test reports and certifications to the OMSI preparer for inclusion into the OMSI documentation.

1.13 QC CERTIFICATIONS

1.13.1 CQC Report Certification

Contain the following statement within the CQC Report: "On behalf of the Contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge, except as noted in this report."

1.13.2 Invoice Certification

Furnish a certificate to the Contracting Officer with each payment request, signed by the QC Manager, attesting that as-built drawings are current, coordinated and attesting that the work for which payment is requested, including stored material, is in compliance with Contract requirements.

1.13.3 Completion Certification

Upon completion of work under this Contract, the QC Manager shall furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the Contract."

Provide a copy of this final QC Certification for completion to the OMSI

SECTION 01 45 00.00 20 Page 13 preparer for inclusion into the OMSI documentation.

1.14 COMPLETION INSPECTIONS

All inspections must be indicated in the three-week look ahead and project schedule.

1.14.1 Punch-Out Inspection

Near the completion of all work or any increment thereof, established by a completion time stated in the Contract Clause entitled "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager and the CxA (if applicable) must conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved drawings, specifications and Contract. Include in the punch list any remaining items on the "Rework Items List", which were not corrected prior to the Punch-Out Inspection. Include within the punch list the estimated date by which the deficiencies will be corrected.

Provide a copy of the punch list to the Contracting Officer. The QC Manager, or staff, must make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government "Pre-Final Inspection". Rework items list, shall be complete prior to request for pre-final inspection.

1.14.2 Pre-Final Inspection

The Government and QCM will perform this inspection to verify that the facility is complete and ready to be occupied. A Government "Pre-Final Punch List" will be documented by the QC Manager as a result of this inspection. The QC Manager will ensure that all items on this list are corrected prior to notifying the Government that a "Final" inspection with the Client can be scheduled. Any items noted on the "Pre-Final" inspection must be corrected in a timely manner and be accomplished before the contract completion date for the work, or any particular increment thereof, if the project is divided into increments by separate completion dates.

1.14.3 Final Acceptance Inspection

Notify the Contracting Officer at least 14 calendar days prior to the date a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final acceptance inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, the CA, and others deemed necessary. Attendees for the Government will include the Contracting Officer, other FEAD personnel, and personnel representing the Client. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the Contract Clause entitled "Inspection of Construction."

1.14.4 Failed and Rescheduled Inspections

The Contractor will be responsible for the Government's team costs for additional inspections resulting from failed inspections and rescheduled inspections. The Contractor will be responsible for reimburising the Government at $1000/day per person for any tests that are required due to

SECTION 01 45 00.00 20 Page 14 previous failed tests, incomplete inspections, and/or rescheduling inspections due to Contractor not being complete and ready for test or inspection.

1.15 DOCUMENTATION

Maintain current and complete records of on-site and off-site QC program operations and activities.

1.15.1 Construction Documentation

Reports are required for each day that work is performed and must be attached to the Contractor Quality Control Report prepared for the same day. Maintain current and complete records of on-site and off-site QC program operations and activities. The forms identified under the paragraph "INFORMATION FOR THE CONTRACTING OFFICER" will be used. Reports are required for each day work is performed. Account for each calendar day throughout the life of the Contract. Every space on the forms must be filled in. Use N/A if nothing can be reported in one of the spaces. The Project Superintendent and the QC Manager must prepare and sign the Contractor Production and CQC Reports, respectively. The reporting of work must be identified by terminology consistent with the construction schedule. In the "remarks" sections of the reports, enter pertinent information including directions received, problems encountered during construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site, quality control problem areas, deviations from the QC Plan, construction deficiencies encountered, meetings held. For each entry in the report(s), identify the Schedule Activity No. that is associated with the entered remark.

1.15.2 Quality Control Validation

Establish and maintain the following in a series of three ring binders.

Binders shall be divided and tabbed as shown below. These binders must be readily available to the Contracting Officer during all business hours.

a. All completed Preparatory and Initial Phase Checklists, arranged by specification section.

b. All milestone inspections, arranged by Activity Number.

c. An up-to-date copy of the Testing Plan and Log with supporting field test reports, arranged by specification section.

d. Copies of all contract modifications, arranged in numerical order.

Also include documentation that modified work was accomplished.

e. An up-to-date copy of the Rework Items List.

f. Maintain up-to-date copies of all punch lists issued by the QC staff to the Contractor and Sub-Contractors and all punch lists issued by the Government.

1.15.3 Testing Plan and Log

As tests are performed, the CA and the QC Manager will record on the "Testing Plan and Log" the date the test was performed and the date the

SECTION 01 45 00.00 20 Page 15 test results were forwarded to the Contracting Officer. Attach a copy of the updated "Testing Plan and Log" to the last daily CQC Report of each month, per the paragraph "INFORMATION FOR THE CONTRACTING OFFICER".

Provide a copy of the final "Testing Plan and Log" to the eOMSI preparer for inclusion into the eOMSI documentation.

1.15.4 Rework Items List

The QC Manager must maintain a list of work that does not comply with the Contract, identifying what items need to be reworked, the date the item was originally discovered, the date the item will be corrected by, and the date the item was corrected. There is no requirement to report a rework item that is corrected the same day it is discovered. Attach a copy of the "Rework Items List" to the last daily CQC Report of each month. The Contractor is responsible for including those items identified by the Contracting Officer. Rework items list must include all items identified in the Contracting Officer Representative's field reports. reports. This will be reconciled on a weekly basis at the QC meeting. Entity generating the item must be noted and is required for concurrence that an item is closed. Rework items list, shall be complete prior to request for pre-final inspection. Rework, observations, and ongoing work shall be tracked as such.

1.15.5 As-Built Drawings

The QC Manager is required to ensure the as-built drawings, required by Section 01 78 00.00 22 CLOSEOUT SUBMITTALS (PWD ME) are kept current on a daily basis and marked to show deviations which have been made from the Contract drawings. Ensure each deviation has been identified with the appropriate modifying documentation (e.g. PC No., Modification No., Request for Information No., etc.). The QC Manager must initial each revision. Upon completion of work, the QC Manager will furnish a certificate attesting to the accuracy of the as-built drawings prior to submission to the Contracting Officer.

1.16 NOTIFICATION ON NON-COMPLIANCE

The Contracting Officer will notify the Contractor of any detected non-compliance with the Contract. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time for excess costs or damages by the Contractor.

1.17 DEFECTIVE WORK

Check work as it progresses, but failure to detect any defective work or materials must in no way prevent later rejection if defective work or materials are discovered, nor obligate the Contracting Officer to accept such work.

PART 2 PRODUCTS

Not used.

SECTION 01 45 00.00 20 Page 16

PART 3 EXECUTION

3.1 PREPARATION

Designate receiving/storage areas for incoming material to be delivered according to installation schedule and to be placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. Store and handle materials in a manner as to prevent loss from weather and other damage. Keep materials, products, and accessories covered and off the ground, and store in a dry, secure area. Prevent contact with material that may cause corrosion, discoloration, or staining. Protect all materials and installations from damage by the activities of other trades.

All materials must be stored in accordance with the manufacturers recommendations and requirements. The Government will reject work where mateirals were used and not stored properly prior to install.

3.2 CRITICAL SUBMITTAL PROCESS

The following long-lead-time item submittals require additional steps to ensure a quality process is achieved:

The Contractor shall submit documentation to demonstrate that progress is being made toward these submittals within 30-days of Contract Award Date unless otherwise noted.

The Contractor shall then submit the above listed critical submittals in accordance with the appropriate specification section a maximum of 90 days following Contract Award Date unless otherwise noted.

a. Enclosure 5 and Enclosure 7 Weight Management Plan (01 11 00)

b. Contractor Coordination Drawings (01 33 00)

c. Enclosure 5 Crane Weight Management Plan (41 22 13.14)

d. Mechanical Detail Ductwork Shop Drawings (23 00 00 and 23 74 00)

e. Flexible Ductwork Connectors (23 00 00) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 120 calendar days from Contract Award.

f. Dampers (23 00 00) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 120 calendar days from Contract Award.

g. Structural Steel Fabrication Shop Drawings (05 12 00) - Submit progress documentation within 40 calendar days from Contract Award, Provide submittal within 120 calendar days from Contract Award.

h. Controls Shop Drawings & Product Data (40 95 00) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 180 calendar days from Contract Award.

i. Touchscreen HMI (40 95 00) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 180 calendar days from Contract Award.

SECTION 01 45 00.00 20 Page 17

j. Commissioning Plans (01 91 13) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 180 calendar days from Contract Award.

k. DALT Testing Plans and Volume Calculations (23 05 93) - Submit progress documentation within 60 calendar days from Contract Award, Provide submittal within 180 calendar days from Contract Award.

-- End of Section --