This amendment modifies a solicitation for the replacement of the Dry Dock 1 caisson at the Portsmouth Naval Shipyard in Kittery, Maine. The proposed project provides for the fabrication, delivery, and installation of a new steel caisson with mechanical and electrical systems to interface with the existing dry dock structure. Key changes in the amendment include revising the test pressures for piping and valve components from 150 psi to 60 psi and 15 psi, specifying materials like 316L stainless steel and Super Duplex 2507 for components, adding fire alarm transmitter requirements, and revising coating system tables for valves and piping. The Navy is procuring these services through full and open competition solicitation N4008521R0272 with an expected award date in 2022.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION NO. N40085-21-R-0272, DESIGN-BID-BUILD, RM-13-1458 DRY DOCK 1 CAISSON REPLACEMENT, PORTSMOUTH NAVAL
SHIPYARD, KITTERY, MAINE
See Continuation Page(s).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Dec-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008521R0272
X 9B. DATED (SEE ITEM 11)
23-Nov-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Dec-2021
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008521R0272
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
CONTINUATION SHEET
SWBS 095-505 PIPING, VALVES AND VALVE ACTUATORS
In the paragraph entitled “Field Testing of Piping:”, delete the first sentence in its entirety and replace with the following:
“Test all piping systems to demonstrate a watertight seal for 15 minutes at 150 psi, 60 psi and 15 psi with clean fresh water.”
In the paragraph entitled “Field Inspection and Testing of Gate Valves:”, in the second sentence, delete “Test all gate valves to” and replace with “Test all gate valves at 60 and…”
In the paragraph entitled “Field Inspection and Testing of Gate Valves:”, in the fifth sentence, delete “test the valve body to bonnet connection to” and replace with “test the valve body to bonnet connection at 60 and…”
In the paragraph entitled “Field Inspection and Testing of Butterfly Valves:”, in the second sentence, delete “Test all butterfly valves to” and replace with “Test all butterfly valves at 60 and…”
In the paragraph entitled “Field Inspection and Testing of Butterfly Valves:”, in the fifth sentence, delete “test the valve body to bonnet connection to” and replace with “test the valve body to bonnet connection at 60 and…”
In the paragraph entitled “Field Inspection and Testing of Check Valves:”, in the first sentence, delete “at 20 psi” and replace with “at 60 and 20 psi…”
In the paragraph entitled “Performance and Leak Test:”, delete the paragraph in its entirety and replace with the following:
“The alignment between the hull and blind flange cover pad eyes must be verified while securing each blind flange in the open position. Verify proper seating of each blind flange to the inlet of piping with gasket and inlet screen in place.
Blind flanges must be hydrostatic tested in the field upon installation in accordance with ASME B31.3. Blind flanges must be bolted to the inlet pipes with gasket and inlet screen in place and tested under normal service conditions to demonstrate compliance. The test pressure must not be less than two (2) times the design pressure of 20 psi for 15 minutes. Provide clean fresh water for testing to prevent corrosion of the piping material. Allowable leakage is zero.”
SWBS 436b. FIRE AND FLOODING ALARM SYSTEM
After the second paragraph, add the following:
“Fire alarm transmitter shall be King-Fisher KFRTI-8S combination transmitter/receiver. Transmitter must operate on 120V, utilize a NEMA 3R enclosure, be an FCC licensed unit, and be compatible with conventional (non-addressable) Fire Alarm Control Panels (FACP’s). Transmitter must also have long life rechargeable battery backup, have automatic self-testing, and be Factory Mutual Approved.”
SWBS 503b. MATERIALS
In the paragraph entitled “Pump Discharge Column and Discharge Elbow:”, in the first sentence, change “316” to “316L”.
In the paragraph entitled “Shafting:”, delete the sentence in entirety and replace with the following:
“Each impeller bowl shaft shall be constructed of K500 Monel material. The line shaft shall be constructed of 316L stainless steel material.”
In the paragraph entitled “Impeller and Propellers:”, in the last sentence of the first paragraph, change “316” to “316L”.
In the paragraph entitled “Pump Suction and Discharge Bowl:”, in the last sentence, change “316” to “316L”.
In the paragraph entitled “Air Relief/Vacuum Valves:”, in the fifth sentence of the first paragraph, change “316” to “316L”.
SWBS 505b. MATERIALS
In the fourth paragraph, change “Type 316” to “Type 316L” in all instances.
After the fourth paragraph, add the following:
“Inlet screens shall be constructed of Super Duplex 2507 stainless steel with an 1/8-inch thick EPDM rubber gasket.”
SWBS 505c. VALVES
In subsection “505c.4 Butterfly Valves:,” in the last sentence of the sixth paragraph, delete “Type 316 or” in its entirety.
In subsection “505c.6 Epoxy Coating:”, in the first sentence of the second paragraph, add “total” after “The exterior coating shall be applied to a”.
In subsection “505c.6 Epoxy Coating:”, in the second sentence of the second paragraph, add “total” after “The interior coating shall be applied to a”.
In subsection “505c.6 Epoxy Coating:,” at the end of the last paragraph, add the following:
“Refer to Table 631-2a – BALLAST TANK VALVES for specific requirements for surface preparation and application of coating system for the internal/external surfaces of the valves.”
SWBS 505d. VALVE ACTUATORS AND MANUAL OPERATORS
In subsection “505d.1 Valve Actuators:”, at the end of the first paragraph, add the following:
“The Contractor’s shop drawing shall identify the series for the Limitorque L120 valve actuators.
It is the responsibility of the Contractor along with the gate and butterfly valve manufacturers and the valve actuator manufacturer to coordinate the sizing/selection of the valve actuators based on the torque requirements of the specific valves to be provided at the specified pressure ratings and minimum cycle speeds for valves opening and closing, etc. presented hereinafter.”
In subsection 505d.1, paragraph entitled “Gear Box:,” delete the third sentence in the second paragraph in its entirety and replace with the following:
“The gearing shall consist of a self-locking worm shaft, alloy bronze worm gear and heat-treated steel spur gear.”
In subsection “505d.3 Valve Reach Rods/Torque Tubes, Guide Bearings, Couplings:”, in the section entitled “Guide Bearings:”, change “316” to “316L” in all instances.
In subsection “505d.3 Valve Reach Rods/Torque Tubes, Guide Bearings, Couplings:”, in the section entitled “Stuffing Boxes:”, change “316” to “316L”.
SWBS 631f. SYSTEM LOCATIONS
Delete Table 631-2a in its entirety and replace with the following:
“Table 631-2a – BALLAST TANK VALVES”
SURFACE SURFACE
PREPARATION
PRIMER STRIPE COAT
FINAL COAT
Ductile Iron Valves (internal)
Near White Metal Blast (NACE-
2/SSPC-SP-10)
One coat MIL-PRF- 23236, Class 7 (non-high solids) Amber color, 4-8 MILS DFT
One coat MIL-PRF- 23236, Class 7 (non-high solids) White color, 2-3 MILS DFT
Ductile Iron Valves (external)
Near White Metal Blast (NACE-
2/SSPC-SP-10)
One coat MIL-PRF- 23236, Class 7 (non-high solids) Amber color, 4-8 MILS DFT
One coat MIL-PRF- 23236, Class 7 (non-high solids) Buff color, 6-10 MILS DFT
One coat MIL-PRF- 23236, Class 7 (non-high solids) White color, 10-12 MILS DFT
25 MILS Total Minimum
SWBS 631g. BALLAST TANK PIPING
Delete Table 631-7 in its entirety and replace with the following:
“Table 631-7 – BALLAST TANK PIPING SURFACES”
SURFACE
SURFACE
PREPARATION
PRIMER STRIPE COAT FINAL COAT
Internal surfaces of non-galvanized ferrous metal piping, fittings, Near White Metal Blast (NACE-
2/SSPC-SP-10)
One coat MIL-PRF- 23236, Class 7 Amber color, 4-8 MILS DFT
Two coats MIL-PRF- 23236, Class 7, White color, 2-3 MILS DFT
External surfaces of non-galvanized ferrous metal piping, fittings, and supports
Near White Metal Blast (NACE-
2/SSPC-SP-10)
One coat MIL-PRF- 23236, Class 7 (non-high solids), Amber color, 4-8 MILS DFT
One coat MIL-PRF- 23236, Class 7 (non-high solids) Haze Grey color, 6-10 MILS DFT
One coat MIL-PRF- 23236, Class 7 (non-high solids) White color, 10-12 MILS DFT
25 MILS Total Minimum DFT (Total of all coats)
DOCUMENT 00 01 15 LIST OF DRAWINGS
1.2 CONTRACT DRAWINGS
The following drawing is revised as of 03 December 2021:
On NAVFAC Dwg. No. 12852208
REPLACE OS523 Floodwall Details with revised drawing sheet accompanying this amendment.
---END OF AMENDMENT---
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by reference:
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2020 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2020 252.204-7021 Contractor Compliance with the Cybersecurity Maturity
Model Certification Level Requirement
NOV 2020
The following have been deleted:
252.223-7999