This amendment to a solicitation provides responses to pre-proposal inquiries for a repair project at a Navy facility. The scope of work includes selective demolition, building HVAC replacement, roof replacement, structural repairs, bathroom renovations, electrical equipment replacements and associated work. Responses clarify that direct applied exterior finish systems are not included in the project scope, specify tile and lighting control equipment details, identify the manufacturer of existing electrical gear, and provide panel schedule and circuit breaker information.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
DESIGN-BID-BUILD REPAIR NAVY INFORMATION OPERATIONS DETACHMENT NAVSUBASE NEW LONDON, CT
The purpose of this Amendment is to provide repsonses for PPI's 2-9. This Amendment does NOT extend the proposal due date.
POC: Quin Conerly-Anderson; quin.conerly-anderso@navy.mil; 757-341-0089
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008520R0033
X 9B. DATED (SEE ITEM 11)
30-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-May-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008520R0033
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 03
The propose of this Amendment is to provide the following:
1. Responses to PPI’s 2-9 Pre-Proposal Inquiry Submission Form N4008520R0033 REPAIR NAVY INFORMATION OPERATIONS
DETATCHMENT NAVSUBASE NEW LONDON, CT
PPI
Date Submitted
LEAVE
BLANK
Reference Question Response
Page
Section Paragraph
2 05/19/20 18 00100 52.236-27 When will the site visit take place and what information do we have to submit beforehand?
Please see Amendment 02 posted on beta.sam.gov
3 05/19/20 AR101.1,
AR102.2,
A700
Rooms 116 & 117 call for ACT-2 per finish schedule.
RCP on AR101.1 lists ACT- 1 for these rooms. Please advise which tile for these rooms. Additionally, the basis of design Armstrong Ultima 1942 for ACT-1 is 2x2 product and not 2x4 as described in the finish schedule.
Rooms 116 and 117 shall receive finish ACT-2 per finish schedule, additionaly rooms 218 and 219 shall receive
ACT-2 NOT ACT-1.
Basis of design for ACT- 1 shall be Armstrong Ultima 1945 2x4 tile.
4 05/20/20 07 24
Please advise if Direct- Applied Exterior Finish System is part of this project and where it will be located.
Direct Applied Exterior Finish System is not part of the project. Section 07 24 10 does apply.
5 05/21/20 M-103.2 M-103.2 Shows heat trace on the roof. Not shown on any electrical panel schedules. Please advise.
Self-regulated cable rated 120 volt, 5watt per LF will be wired from a 20Amp/1pole 30mA GFI circuit breaker in panel P2C ckt.3.
6 05/21/20 E-600 Can the name of the manufacturer of the existing MSB be made available?
MSB is manufactired by General Electric AV-line type.
N4008520R0033
7 05/21/20 E-601 Can a panel schedule be provided for the new P2B panel
Panel P2B is existing being replaced with new at the same location.
New panel schedule shall match existing. Panel is not utilized to serve any new loads, so schedule is not available.
8 05/21/20 E-600 Please clarify on drawing E- 600 Key Notes (2) in regards to which breakers need to be changed out to 3P and what amperage do they need to be
Note #2 calls for new 150A-3P circuit breaker in existing space available within existing switchboard.
9 05/22/20 EL102.2 EL102.2 I have (4) items labeled RC. What does this stand for?
RC stands for lighting room controller.
(End of Summary of Changes)