About this file

This pre-solicitation notice seeks design-build construction services for Hurricane Florence recovery projects at Marine Corps Air Station Cherry Point in North Carolina. The projects include construction of a PMO/H&HS headquarters building, motor transportation/communication shop, fire stations, a range operations center, and academic facility/auditorium. The anticipated contract value is between $100-250 million, with a performance period of 1,826 calendar days from award. The solicitation will utilize best value tradeoff source selection with technical approach, experience, past performance, safety, technical solution, project management, and small business participation as evaluation factors. Price will also be considered. The NAICS code is 236220 and small business size standard is $39.5 million. The RFP is expected to issue on October 7, 2019 with drawings and specifications.

View the file

Other files

File Type Posted
19R9251 0018.pdf PDF
19R9251 0017.pdf PDF
TFF Package 1 Price Proposal-041620.pdf PDF
19R9251 0016.pdf PDF
200131 TFF-1 REVISED FINAL RFP - P246.pdf PDF
200131 TFF-1 REVISED FINAL RFP - P142A.pdf PDF
200131 TFF-1 REVISED FINAL RFP - P142B.pdf PDF
200131 TFF-1 REVISED FINAL RFP - P254.pdf PDF
200131 TFF-1 REVISED FINAL RFP - P162A.pdf PDF
ATTACHMENT H REVISED.pdf PDF
19R9251 0015.pdf PDF
19R9251 0014.pdf PDF
19R9251 0013.pdf PDF
19R9251 0012.pdf PDF
ATT G TFF-1 Geotech - redfile.pdf PDF
19R9251 0011.pdf PDF
19R9251 0010.pdf PDF
One Day Pass Request.xlsx XLSX spreadsheet
Map to B-163.pdf PDF
19R9251 0009.pdf PDF
200131 Part 5 Specifications.pdf PDF
19R9251 0008.pdf PDF
19R9251 0005.pdf PDF
19R9251 0006 PH II.pdf PDF
19R9251 0007.pdf PDF
19R9251_0004.pdf PDF
19R9251_0003.pdf PDF
19R9251_0002.pdf PDF
One_Day_Pass_Request.xls XLS spreadsheet
19R9251_0001.pdf PDF
N4008519R9251.pdf PDF
N4008519R9251.pdf PDF
Attachment_F_PPQ.pdf PDF
Attachment_H_Proposed_Project_Durations.pdf PDF
Attachment_D_SB_Subcontracting_Record.pdf PDF
Attachment_B_SECNAV_5512.pdf PDF
Attachment_E_SB_Part_Commit_Strat.pdf PDF
Attachment_A_-_PPI_Inquiry_Log.xls XLS spreadsheet
Attachment_G_Sub_Plan.pdf PDF
N4008519R9251.pdf PDF
Attachment_C_Con_Des_Exp_Proj_Data_Theater.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-1

ATTACHMENT F – PRICE PROPOSAL FORM

1.1 CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the CLIN lump sum price for the following items:

CLIN 0001 – P162 BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0001 shall provide the full project scope, excluding other Base Bids (CLIN

0002 to 0005) and options, complete and in place in accordance with the RFP even if not specifically listed below.

0001A: P162A HH&S &MWHS-2 Headquarters:

Price for provision of all work for P162A complete.

Basis of Bid for CLIN 0001A shall be the Total Amount for CLIN 0001A, but not including the work indicated or specified to be provided under any other CLIN or option.

DESCRIPTION ESTIMATED

QUANTITY

UNIT TOTAL PRICE

0001AA All work complete in accordance with the RFP for CLIN 0001A including

0001AB, 0001AC, 0001AD

and 0001AE, but not including the work indicated or specified under 0001B.

1 LS $

0001AB Complete work for the facility Exterior Enclosure in accordance with the RFP.

Enter selected Exterior Enclosure System below:

1 LS $

0001AC Complete work for the facility inside the 5 foot line

1 LS $

0001AD Complete work for the site work outside the 5 foot line

0001AE Design work for CLIN 0001A 1 LS $

F-2

0001B: P162 B PMO Building:

Price for provision of all work for P162B complete.

Basis of Bid for CLIN 0001B shall be the Total Amount for CLIN 0001B, but not including the work

UNIT TOTAL PRICE

0001BA All work complete in accordance with the RFP for CLIN 0001B including 0001BB, 0001BC, 0001BD and 0001BE but not including the work indicated or specified under 0001A.

1 LS $

0001BB Complete work for the facility Exterior Enclosure in accordance with the RFP.

0001BC Complete work for the facility inside the 5 foot line

1 LS $

0001BD Complete work for the site work outside the 5 foot line

0001BE Design work for CLIN 0001B 1 LS $

Total CLIN 0001 (0001AA + 0001BA): $

CLIN 0002 – P254 BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0002 shall provide the full project scope, excluding other Base Bids (CLIN

0001 and 0003 to 0005) and options, complete and in place in accordance with the RFP even if not specifically listed below.

0002: P254 Station Academic Facility/Auditorium Replacement:

Price for provision of all work for P254 complete.

Basis of Bid for CLIN 0002 shall be the Total Amount for CLIN 0002, but not including the work

F-3

QUANTITY

UNIT TOTAL PRICE

0002AA All work complete in accordance with the RFP for CLIN 0002 including 0002AB, 0002AC, 0002AD and

0002AE.

1 LS $

0002AB Complete work for the facility Exterior Enclosure in accordance with the RFP.

Enter selected Exterior Enclosure System below:

1 LS $

0002AC Complete work for the facility inside the 5 foot line

1 LS $

0002AD Complete work for the site work outside the 5 foot line

0002AE Design work for CLIN 0002 1 LS $

CLIN 0003 – P246 BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0003 shall provide the full project scope, excluding other Base Bids (CLIN

0001, 0002, 0004, 0005) and options, complete and in place in accordance with the RFP even if not specifically listed below.

0003: P246 BT-11 Range Operations Center Replacement:

Price for provision of all work for P246 complete.

Basis of Bid for CLIN 0003 shall be the Total Amount for CLIN 0003, but not including the work indicated or specified to be provided under any other CLIN or options.

UNIT TOTAL PRICE

0003AA All work complete in accordance with the RFP for CLIN 0003 including 0003AB, 0003AC and 0003AD.

1 LS $

0003AB Complete work for the facility inside the 5 foot line

F-4

0003AC Complete work for the site work outside the 5 foot line

0003AD Design work for CLIN 0003 1 LS $

CLIN 0004 – P142 BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0004 shall provide the full project scope, excluding other Base Bids (CLIN

0001, 0002, 0003, 0005) and options, complete and in place in accordance with the RFP even if not specifically listed below.

0004A: P142A Main Fire Station Replacement:

Price for provision of all work for P142A complete.

Basis of Bid for CLIN 0004A shall be the Total Amount for CLIN 0004A, but not including the work

UNIT TOTAL PRICE

0004AA All work complete in accordance with the RFP for CLIN 0004A including 0004AB, 0004AC, 0004AD and 0004AE but not including the work indicated or specified under 0004B.

1 LS $

0004AB Complete work for the facility Exterior Enclosure in accordance with the RFP.

0004AC Complete work for the facility inside the 5 foot line

1 LS $

0004AD Complete work for the site work outside the 5 foot line

0004AE Design work for CLIN 0004A 1 LS $

F-5

0004B: P142B Satellite Fire Station:

Price for provision of all work for P142B complete.

Basis of Bid for CLIN 0004B shall be the Total Amount for CLIN 0004B, but not including the work

UNIT TOTAL PRICE

0004BA All work complete in accordance with the RFP for CLIN 0004B including

0004BB, 0004BC, 0004BD

and 0004BE, but not including the work indicated or specified under 0004A

1 LS $

0004BB Complete work for the facility Exterior Enclosure in accordance with the RFP.

0004BC Complete work for the facility inside the 5 foot line

1 LS $

0004BD Complete work for the site work outside the 5 foot line

0004BE Design work for CLIN 0004B 1 LS $

Total CLIN 0004 (0004A + 0004B): $

CLIN 0005 – P130 BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0005 shall provide the full project scope, excluding other Base Bids (CLIN

0001 to 0004) and options, complete and in place in accordance with the RFP even if not specifically listed below.

0005: P130 Motor Transportation/Communication Shop Replacement:

Price for provision of all work P130 complete.

Basis of Bid for CLIN 0005 shall be the Total Amount for CLIN 0005, but not including the work indicated or specified to be provided under any other CLIN or options.

UNIT TOTAL PRICE

0005AA All work complete in accordance with the RFP for CLIN 0005 including

0005AB, 0005AC, 0005AD

and 0005AE.

F-6

0005AB Complete work for the facility Exterior Enclosure in accordance with the RFP.

0005AB Complete work for the facility inside the 5 foot line

1 LS $

0005AC Complete work for the facility inside the 5 foot line

0005AD Design work for CLIN 0005 1 LS $

F-7

Refer to paragraph 1.3 for Planned Modification Bid notes.

CLIN 0006– Planned Modification for P162A – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the RFP and in accordance with the following schedule:

CLIN ITEM GOVERNMENT

FF&E

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

AMOUNT)

0006 FF&E $1,062,094

CLIN 0007– Planned Modification for P162A – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with the RFP and in accordance with the following schedule:

ESS ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0007 (GOVT ESS

ESTIMATE + HAR

0007 ESS $194,100

CLIN 0008– Planned Modification for P162A – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

RFP and in accordance with the following schedule:

A/V ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0008 (GOVT A/V

ESTIMATE + HAR

0008 A/V $412,200

F-8

CLIN 0009 – Option 1 for P162A: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP even if not specifically listed below. Refer to paragraph 1.2 for explanation of option.

UNIT TOTAL PRICE

Non-load bearing cold-formed steel stud exterior wall backup construction

LS

CLIN 0010 – Option 2 for P162A - Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Provide terrazzo floor and base

CLIN 0011– Planned Modification for P162B – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0011 (GOVT FF&E

ESTIMATE + HAR

0011 FF&E $1,700,055

CLIN 0012– Planned Modification for P162B – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

F-9

ESS ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0012 (GOVT ESS

ESTIMATE + HAR

0012 ESS $242,855

CLIN 0013– Planned Modification for P162B – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0013 (GOVT A/V

ESTIMATE + HAR

0013 A/V $615,300

CLIN 0014 – Option 1 for P162B: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

CLIN 0015 – Option 2 for P162B: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Provide terrazzo floor and base

F-10

CLIN 0016– Planned Modification for P254 – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0016 (GOVT FF&E

ESTIMATE + HAR

0016 FF&E $777,615

CLIN 0017– Planned Modification for P254 – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0017 (GOVT ESS

ESTIMATE + HAR

0017 ESS $96,000

CLIN 0018– Planned Modification for P254 – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0018 (GOVT A/V

ESTIMATE + HAR

0018 A/V $808,700

CLIN 0019 – Option 1 for P254: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

F-11

CLIN 0020 – Option 2 for P254: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Increase parking area by 20%

CLIN 0021 – Option 3 for P254: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Provide repaving of parking lot next to Post Office

CLIN 0022– Planned Modification for P246 – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0022 (GOVT FF&E

ESTIMATE + HAR

0022 FF&E $549,590

F-12

CLIN 0023– Planned Modification for P246 – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0023 (GOVT ESS

ESTIMATE + HAR

0023 ESS $121,200

CLIN 0024– Planned Modification for P246 – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0024 (GOVT A/V

ESTIMATE + HAR

0024 A/V $88,700

CLIN 0025 – Option 1 for P246: Not Used.

CLIN 0026 – Option 2 for P246: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Demolish current ROC building

CLIN 0027– Planned Modification for P142A – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

F-13

FF&E

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0027 (GOVT FF&E

ESTIMATE + HAR

0027 FF&E $1,794,805

CLIN 0028– Planned Modification for P142A – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0028 (GOVT ESS

ESTIMATE + HAR

0028 ESS $81,615

CLIN 0029– Planned Modification for P142A – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0029 (GOVT A/V

ESTIMATE + HAR

0029 A/V $135,600

CLIN 0030 – Option 1 for P142A: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

F-14 steel stud exterior wall backup construction in administration area

CLIN 0031 – Option 2 for P142A: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Provide training catwalk

CLIN 0032 – Option 3 for P142A: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Recreational facilities demolition

CLIN 0033 – Option 4 for P142A: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Add repaving of parking lot next to Building 193

CLIN 0034– Planned Modification for P142B – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

F-15

FF&E

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0034 (GOVT FF&E

ESTIMATE + HAR

0034 FF&E $977,420

CLIN 0035– Planned Modification for P142B – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0035 (GOVT ESS

ESTIMATE + HAR

0035 ESS $75,410

CLIN 0036– Planned Modification for P142B – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0036 (GOVT A/V

ESTIMATE + HAR

0036 A/V $151,500

CLIN 0037 – Option 1 for P142B: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

F-16 steel stud exterior wall backup

CLIN 0038 – Option 2 for P142B: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Add repaving of parking lot next to Building 192

CLIN 0039– Planned Modification for P130 – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0039 (GOVT FF&E

ESTIMATE + HAR

0039 FF&E $1,289,144

CLIN 0040– Planned Modification for P130 – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL ESS

ESTIMATED

AMOUNT FOR CLIN

0040 (GOVT ESS

ESTIMATE + HAR

0040 ESS $160,440

F-17

CLIN 0041– Planned Modification for P130 – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (A/V) complete in accordance with the

HAR (NTE 5%) HAR

AMOUNT

(GOVT A/V

ESTIMATE X

HAR%)

TOTAL A/V

ESTIMATED

AMOUNT FOR CLIN

0041 (GOVT A/V

ESTIMATE + HAR

0041 A/V $222,300

CLIN 0042 – Option 1 for P130: Price includes the following: NOT USED

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP steel stud exterior wall backup

CLIN 0043 – Option 2 for P130: Price includes the following:

Price for the Total Amount to provide the full option scope complete and in place in accordance with the RFP

Add the fueling station

1.2 Explanation of CLIN Items

CLIN 0001

Total amount of Base Amount CLIN 0001 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of specific work items as defined as follows:

CLIN 0001A: P162 A HH&S & MWHS-2 Headquarters - includes all P162F A Base Bid Work not included in CLIN 0001B and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

F-18

0001AA: All work complete in accordance with the RFP for CLIN 0001A and including the work indicated or specified under 0001AB through 0001AE.

0001AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. Enter selected Exterior Enclosure in the space provided.

0001AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, and equipment for construction of the facility and all incidental and related work.

0001AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and equipment for grading and drainage, paving, utilities, and all incidental and related work.

0001AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, electrical, and all incidental and related work.

CLIN 0001B: P162 B PMO Building - includes all P162F B Base Bid Work not included in CLIN 0001A and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

0001BA: All work complete in accordance with the RFP for CLIN 0001B and including the work indicated or specified under 0001BB through 0001BE.

0001BB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

0001BC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0001BD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0001BE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0002

Total amount of Base Amount CLIN 0002 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0002: P254 Station Academic Facility/Auditorium Replacement - includes all P254F Base Bid

Work and includes, but is not limited to, the design and construction of the building and site utilities;

providing construction permitting fees, and all incidental and related work.

0002AA: All work complete in accordance with the RFP for CLIN 0002 and including the work indicated or specified under 0002AB through 0002AE.

F-19

0002AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

0002AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0002AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0002AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0003

Total amount of Base Amount CLIN 0003 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0003: P246 BT-11 Range Operations Center Replacement - includes all P246F Base Bid Work and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

0003AA: All work complete in accordance with the RFP for CLIN 0003 and including the work indicated or specified under 0003AB through 0003AD.

0003AB: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0003AC: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0003AD: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0004

Total amount of Base Amount CLIN 0004 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0004A: P142 A Main Fire Station Replacement - includes all P142F A Base Bid Work not included in CLIN 0004B and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

0004AA: All work complete in accordance with the RFP for CLIN 0004A and including the work indicated or specified under 0004AB through 0004AE.

0004AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the apparatus bays and other spaces required by criteria in the RFP. Enter

F-20 selected Exterior Enclosure in the space provided.

0004AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0004AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0004AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0004B: P142 B Satellite Fire Station - includes all P142F B Base Bid Work not included in CLIN

0004A and includes, but is not limited to, the design and construction of the building and site utilities;

providing construction permitting fees, and all incidental and related work..

0004BA: All work complete in accordance with the RFP for CLIN 0004B and including the work indicated or specified under 0004AB through 0004AE.

0004BB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the apparatus bays and other spaces required by criteria in the RFP. Enter selected Exterior Enclosure in the space provided.

0004BC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0004BD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0004BE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0005

Total amount of Base Amount CLIN 0005 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0005: P130 Motor Transportation/Communication Shop Replacement - includes all P130F Base

Bid Work and includes, but is not limited to, the design and construction of the building and site utilities;

providing construction permitting fees, and all incidental and related work.

0005AA: All work complete in accordance with the RFP for CLIN 0005 and including the work indicated or specified under 0005AB through 0005AE.

F-21

0005AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. Enter selected Exterior Enclosure in the space provided. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the apparatus bays and other spaces required by criteria in the RFP.

0005AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0005AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0005AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0006 – Planned Modification for P162A

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the RFP.

CLIN 0007 – Planned Modification for P162A

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0001A.

CLIN 0008 – Planned Modification for P162A

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0001A.

CLIN 0009 – Option 1 for P162A NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load bearing cold-formed steel framing exterior wall back-up construction.

CLIN 0010 – Option 2 for P162A

Provide terrazzo floor and base construction, in lieu of porcelain tile and base construction.

CLIN 0011 – Planned Modification for P162B

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0012 – Planned Modification for P162B

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this

F-22 item and shall be priced in the base bid CLIN 0001B.

CLIN 0013 – Planned Modification for P162B

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0001B.

CLIN 0014 – Option 1 for P162B NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load

CLIN 0015 – Option 2 for P162B

Provide terrazzo floor and base construction, in lieu of porcelain tile and base construction.

CLIN 0016 – Planned Modification for P254

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0017 – Planned Modification for P254

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0002.

CLIN 0018 – Planned Modification for P254

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0002.

CLIN 0019 – Option 1 for P254 NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load

CLIN 0020 – Option 2 for P254

Price for the work, design, and equipment to increase the parking area outside the facility by 20%.

CLIN 0021 – Option 3 for P254

Price for the work and equipment to repair and repave the parking lot next to the Post Office.

CLIN 0022 – Planned Modification for P246

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0023 – Planned Modification for P246

F-23

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0003.

CLIN 0024 – Planned Modification for P246

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0003.

CLIN 0025 – Option 1 for P246

Not used.

CLIN 0026 – Option 2 for P246

Price for the work, equipment, and expenses to demolish the existing ROC building.

CLIN 0027 – Planned Modification for P142A

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0028 – Planned Modification for P142A

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0004A.

CLIN 0029 – Planned Modification for P142A

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0004A.

CLIN 0030 – Option 1 for P142A NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load bearing cold-formed steel framing exterior wall back-up construction in the administration areas. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the apparatus bays and other spaces required by criteria in the RFP.

CLIN 0031 – Option 2 for P142A

Price for the work, design, and materials to construct the training catwalk.

CLIN 0032 – Option 3 for P142A

Price for the work and equipment to demolish the recreational facilities.

CLIN 0033 – Option 4 for P142A

F-24

Price for the work, materials, and equipment to repair and repave the parking lot next to Building 193.

CLIN 0034 – Planned Modification for P142B

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0035 – Planned Modification for P142B

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0004B.

CLIN 0036 – Planned Modification for P142B

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0004B.

CLIN 0037 – Option 1 for P142B NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load bearing cold-formed steel framing exterior wall back-up construction in the administration areas. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the apparatus bays and other spaces required by criteria in the RFP.

CLIN 0038 – Option 2 for P142B

Price for the work, materials, and equipment to repair and repave the parking lot next to Building 4203.

CLIN 0039 – Planned Modification for P130

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0040 – Planned Modification for P130

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0005.

CLIN 0041 – Planned Modification for P130

Price to procure and supervise installation of the Audio/Visual Equipment (A/V) complete in accordance with the RFP. A/V design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0005.

CLIN 0042 – Option 1 for P130 NOT USED

In lieu of reinforced CMU or reinforced concrete exterior wall back-up construction, provide non-load bearing cold-formed steel framing exterior wall back-up construction in the administration areas. The reinforced CMU or reinforced concrete exterior wall back-up construction requirement will remain for the

F-25 maintenance bays and other spaces required by criteria in the RFP.

CLIN 0043 – Option 2 for P130

Price for the work, design, equipment, and materials to add the covered fueling station.

1.3 Planned Modification Bid Notes:

a. The estimated amounts for FF&E and A/V have been supplied by the Government, to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E and A/V including freight and installation charges. The Government FF&E Estimate is only an estimated amount.

b. If awarded, line items will be funded separately after completion of FF&E and A/V design package review by the Government, and receipt of appropriate funding by the Government. Requirements and details are provided in E10, EQUIPMENT and E20, FURNISHINGS of the RFP..

c. Bonding is not required for the design, procurement and installation of FF&E.

d. Offerors may propose a Handling and Administration Rate (HAR) for the FF&E and A/V not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E and A/V. The proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the

FF&E and A/V. The proposed HAR is a fixed rate.

e. The Government is not obligated to award the Planned Modification line item(s). Should the Government choose to award the Planned Modification, the line item will be awarded as a negotiated modification to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E and A/V.

f. If awarded, the FF&E and A/V modifications will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the

FF&E and A/V without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the FF&E and A/V as modifications. No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date. If the Government decides to negotiate and award the furniture modification with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final FF&E and A/V packages were submitted within the approved schedule deadlines and sufficient lead time for the FF&E and A/V were not available and the Government's award of the modification is in the last six months of the contract.

1.4 GENERAL NOTES

a. Submit offers using this Price Proposal Form.

b. Except when it is determined in accordance with FAR 17.206 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by calculating the sum total price for CLINs 0006 through 0049 to the total price for CLINs 0001 through 0005. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s).

F-26

c. The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

d. A firm-fixed proposed price is required for all CLINs. No provision is made for economic price adjustment.

e. The Government reserves the unilateral right to award options to the Contractor at the proposed price within one hundred twenty (120) calendar days after contract award. The Government reserves the unilateral right to award planned modifications to the Contractor at the proposed price within five hundred forty (540) calendar days after contract award.

f. The performance period for the work required by base price shall be 1400 (fourteen hundred) calendar days from the date of award (includes 15 days for submission and approval of required bonds and insurance). If any or all of CLINs 0006 through CLIN 0043 are exercised, the contract completion date remains the same as that of the base price work (CLINs 0001 through 0005), as the work required by these options can be performed concurrent to the base work.

g. If CLIN 0006 through CLIN 0043 are exercised, additional bonding and consent of surety is required.

Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.