This notice announces a proposed design-build construction services contract for Hurricane Florence Recovery Facilities at Marine Corps Air Station Cherry Point in North Carolina. The project includes five military construction projects: replacement of the Provost Marshall Office and Headquarters buildings, the Motor Transportation and Communication Shop, two Fire Stations, the Range Operations Center at Bombing Target 11, and the Station Academic Facility and Auditorium. Construction is to be completed within 1,826 calendar days of award of a firm-fixed price contract. The solicitation will utilize a two-phase evaluation including non-price and price factors, with technical factors combined being equal in importance to past performance and all non-price factors combined significantly outweighing price. Phase 1 non-price factors are technical approach, corporate experience and past performance. Phase 2 factors include safety, technical solution, project management/schedule and small business utilization along with price. The solicitation is designated unrestricted and open to all competitors with an anticipated award date of 20 July 2020. The NAICS code is 236220 and small business size standard is $39.5M.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9251
X 9B. DATED (SEE ITEM 11)
09-Oct-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PPIs, Revised PPF
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION
NO. 0016
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Apr-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
x
N40085-19-R-9251 0016
This amendment hereby incorporates:
1. Provides Revised Attachment F - Price Proposal Form “TTF Package 1 Price Proposal – 041620.pdf” to replace all previous versions of Price Proposal Form, including the incorrectly labeled “Attachment I Price
Proposal Form.”
2. Price PPI responses 1-19
Reference Question Government Response
Page Section Paragraph
Bid
Schedule
Please confirm that Building demolition work for each site/structure is to be carried with the Site work
CLINs (outside the 5 foot line) and not with the Facility work CLINs (inside the 5 foot line).
Include costs for demolition in the Site Work CLINs.
Bid
Schedule
Please confirm that the full value of demolition for Building 294 is to be carried 100% with the Security Office
CLIN # and none of this scope is associated with the Headquarters
CLIN #
Include costs for demolition of building 294 in the Site Work
CLIN 0001BC.
Bid
Schedule
Please confirm that there is no Option
2 for the P254 Station Academic
Facility/Auditorium Replacement. The options are 1, 3 and 4 per the schedule and skip 2.
In the Price Proposal Form, revise CLIN 0020 to read
"Option 2 for P254", CLIN 0021 to read "Option 3 for P254".
Bid
Schedule
Please confirm that there are no
Options 2 or 3 for the P142 Fire
Station Replacement(s). The options are 1 and 4 per the schedule and skip 2 and 3.
In the Price Proposal Form, revise CLIN 0038 to read
"Option 2 for P142B".
Bid
Schedule
Please confirm that there are no
Options 2 or 3 for the P130 Motor
Transportation/ Communication Shop
Replacement. The options are 1 and 4 per the schedule and skip 2 and 3.
In the Price Proposal Form, revise CLIN 0043 to read
"Option 2 for P130".
6 2 Part 3, 6.0
ESR,
A1010
A101002
RFP indicates to provide material protection for elements exposed to corrosive soils or chlorides; however, the specific environmental exposure categories and classes are not defined.
What are the specific ACI sulfate exposure and F, W, and C durability categories that the foundation and building should be designed for?
Geotechnical Reports were provided in RFP for reference.
Bid per RFP
7 1 Part 3, 6.0
ESR,
D40
2 The RFP does not identify whether fire alarm/MNS systems are required in all buildings of the Range Operations
Facility? Please confirm if FA/MNS is just for the main building? Or if it is also required for either the Range
Operations Tower or covered storage?
Bid per RFP. The "facility" as stated in section D4010 is defined as all three structures in section 1.0 of the RFP.
8 5 Part 3, 6.0
ESR
D4090
1 Commercial cooking equipment is not provided in this building, rather a residential range is to be provided.
Can this range be protected per UFC 3-
600-01 criteria using a UL 300A listed residential range top extinguishing system or may the cooking surface be
Bid per RFP. ESR E109002
FOOD SERVICE EQUIPMENT
for P246, P142A and P142B all indicate requirement for
"commercial" food service equipment equiped with temperature limited burners?
pdf page 17
RFP
Chapter 3 /
3.2.1
Please confirm if the existing underwater concrete piles at building
9014 are to be demolished.
See ESR H60. Bid per RFP
Part 3 -
Chapter
6/ESRD20-
RFP
D2030003
This section states "Floor drains are not perimited in the vehicle maintenance bays". Normally trench drains would be added at the foot of the vehicle bays. Please confirm that no floor drains are to be installed in the vehicle bays.
Bid per RFP
RFP
142A &
142B
Section 3
E101004
Is the equipment listed for Laundry, PPE cleaning, and Kitchen Appliances part of CLIN 0027 for 142A and CLIN
0034 for 142B? Please confirm.
142B
What is the defined area of paving to be done for CLIN 0033?
Bid Per RFP. CLIN 0033 is "Add repaving of parking lot next to
Building 193."
The RFP states to pave the entire parking lot - in Part 3, Chapter 3, section 3.2.2.2.
142B
What is the defined area of paving to be done for CLIN 0038?
Bid Per RFP. CLIN 0038 is "Add repaving of parking lot next to
Building 192."
The RFP states to pave the entire parking lot - in Part 3, Chapter 3, section 3.2.2.2.
142B
Will the secured parking lots require fencing and keypad entry?
BID PER RFP as stated in
Section 3.2.2.5.
142B
Will the secured parking lots require personnel gates, lift bars or slide gates?
BID PER RFP as stated in
Section 3.2.2.5.
16 2 Part 3, 6.0
ESR,
A1010
A101001 and
A101002
RFP indicates to provide material protection for elements exposed to corrosive soils or chlorides; however, the specific environmental exposure categories and classes are not defined.
What are the specific ACI sulfate exposure and F, W, and C durability categories that the foundation and building should be designed for?
Bid per RFP
17 7 Part 3, 6.0
ESR,
D4090
1 Please define "Building Code" as used in the context of this paragraph? The
DOD Building Code (UFC 1-200-01) states that Chapter 4 of the IBC shall only be adopted as specifically referenced by UFC 3-600-01. There are no specific references to stages or platforms in UFC 3-600-01, therefore it would appear that the stage/platform should be regulated by the requirements of Chapter 12.4.6 of
NFPA 101 (2018). This edition of
NFPA 101 does not require hose valve outlets be provided for stages or platforms.
18 The SF1442 provided with the original
RFP release in Phase I is the latest version, and shows a shows a due date of 08 November 2019, which was revised in AM0014, as well as submission of Original and 9 copies, which was revised in AM0010. Please confirm whether a new SF1442 for
Phase II will be issued by NAVFAC
OR if we are to make the amended revisions on the current SF1442.
The SF1442 is the original RFP document. All subsequent changes to the RFP, including changed or subsequent phase proposal due dates, are issued via amendment on form SF30. A new SF1442 will not be issued.
Please abide by guidance as set forth in the subsequent amendments for Phase II proposal due dates.
19 We request an extension of the due date, to 1-week after receipt of outstanding price PPI responses.
Bid per RFP.
| 19R9251 AMENDMENT COVER |
| 19R9251 0015 |
AMendment 4-21