Amendment 0015.pdf

PDF 85 KB Posted

Attached to
Design-Bid-Build, P409 Underwater Launch Test Facility (ULTF), Crane, Indiana
Solicitation number
N4008519R9186
Issued by

About this file

This document includes an amendment to a solicitation and details of the related federal contract opportunity. The amendment modifies the phased construction plan for a project to construct a new Underwater Launch Test Facility to support submerged launch testing and evaluation. Key details include that construction is to start in June 2020 and equipment outfitting is to be completed by September 2021. The facility will include an underwater launch pit, operational support building, warehouse building, water treatment facility, and mechanical and electrical building. Supporting site work will also be conducted. The project has specific phasing requirements, with Phase 1 work to be completed within seven months of award and Phase 4, achieving beneficial occupancy, to be finished within eighteen months of the construction contract award date. The opportunity is solicited by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
Streams and Wetlands Permit.pdf PDF
Amendment 0014.pdf PDF
NOSSA Final Site Approval.pdf PDF
NPDES Permit.pdf PDF
C2 OSB-A-017_C2 Weep Hole Edit.pdf PDF
G-002 Index Title Edit.pdf PDF
Spec Section 41 22 13.16 Page 2 Gantry Spec Typo.pdf PDF
G-003 Index Title Edit.pdf PDF
Amendment 0013.pdf PDF
UTF-C-002_CATEX Note 15 Removed.pdf PDF
Crane Test Facility Permit.pdf PDF
31 00 00 Blasting in LP only.pdf PDF
Amendment 0012.pdf PDF
PPI 109 UTF Drawing.pdf PDF
PPI 131 attachment Spec 22 00 00 Spec Edits.pdf PDF
Amendment 0011.pdf PDF
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
PPI 33 attachment_20200604rev1.pdf PDF
Amendment 0008.pdf PDF
UTF-C-103 Phasing Plan.pdf PDF
PPI 35 attachment_01 57 19 Edits.pdf PDF
PPI 33 attachment_20200604.pdf PDF
PPI 26 attachment_BLDG3680-1629197-UTF-C-201_207-2A-2B.pdf PDF
1629197dwgVol1_Sheet092-107_C.pdf PDF
1629197dwgVol2_Sheet302-321_T.pdf PDF
1629197dwgVol2_Sheet338-350_E.pdf PDF
ULTF_Geotechnical Design Report Rev 2_Volume 2_Part2.pdf PDF
1629197dwgVol1_Sheet063-080_C.pdf PDF
1629197dwgVol1_Sheet042-046_B.pdf PDF
ULTF_Geotechnical Design Report Rev 2_Volume 2_Part1.pdf PDF
1629197dwgVol1_Sheet015-026_V.pdf PDF
1629197spcVol1_Divs 00-06.pdf PDF
1629197dwgVol1_Sheet136-149_C.pdf PDF
1629197dwgVol2_Sheet150-167_G.pdf PDF
ULTF_Geotechnical Design Report Rev 2_Volume 1.pdf PDF
1629197dwgVol2_Sheet331-337_E.pdf PDF
1629197dwgVol1_Sheet051_062_C site exist and demo.pdf PDF
1629197dwgVol1_Sheet108-121_C.pdf PDF
1629197dwgVol2_Sheet168-188_S.pdf PDF
1629197dwgVol1_Sheet122-135_C.pdf PDF
1629197dwgVol1_Sheet081-091_C.pdf PDF
1629197dwgVol4_Sheet495-574_G.pdf PDF
1629197dwgVol1_Sheet001-014_G.pdf PDF
1629197spcVol3_Div 25.pdf PDF
1629197dwgVol1_Sheet047-050_B.pdf PDF
1629197spcVol2_Divs 07-23.pdf PDF
1629197dwgVol2_Sheet237-255_E.pdf PDF
Amendment 0007.pdf PDF
1629197dwgVol5_Sheet627-688_D.pdf PDF
Show 40 more

Latest 50 of 115 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

DBB P409 ULTF, Crane, IN

SEE BLOCK 14 CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Oct-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9186

X 9B. DATED (SEE ITEM 11)

11-Dec-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Oct-2020

CODE

NAVFAC MID ATLANTIC

ACQUISITION CORE

9324 VIRGINIA AVENUE

NORFOLK VA 23511-3095

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008519R9186

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SUMMARY OF CHANGES

The purpose of this modification is for the following:

1. Provide revised Phase Construction Plan

1. Revised Phased Construction Plan: Changes are in bold italic

Phased Construction Schedule

Within the overall project schedule, commence and complete the work in phases. Complete each phase of the work within the number of calendar days stated in the following schedule:

a. Schedule start day: The day designated as the beginning of a particular phase; the number listed is the number of calendar days from the award of contract.

b. Completion day: The day designated as the end of a given phase and the day the work in that phase must be completed; the number listed is the number of calendar days from the award of the contract.

c. Schedule:

NOTE: Determine the number of days required for each phase.

Phase Description Scheduled Start Date Completion Date Phase Plan Note 3 The following must be 100% complete 10/30/20 08/30/21 ꞏ relocated highway 486 ꞏ test equipment staging area ꞏ installation of foundations, concrete pads, trenching, conduit and other site improvements within test equipment staging area. 10 months after date of award.

Phase Plan Note 4a The launch pit shall be substantially 10/30/20 01/31/22 and 4b complete on/prior to 15 months after the date of award. the test equipment design/fabrication team shall be permitted coordinated and non-impactful access as identified below:

a.) crane access to all sides of the launch pit and cross flow area, 15 months after award through BOD.

b.) access to the west wall of the launch pit and sheave area for test equipment installation, 15 months after award through BOD.

N4008519R9186

Phase Plan Note 4c c.) access to the launch pit floor for test 10/30/20 02/28/22 equipment installation, 16 months after award through BOD.

Phase Plan Note 4d d.) access to the cross flow winch area 10/30/20 03/30/22 for test equipment installation, 17 months after award through BOD.

Phase Plan Note 4e e.) access to the VFD area for test 10/30/20 05/02/22 equipment installation, 18 months after award through BOD.

Phase Plan Note 4f f.) access from the test equipment pad to 10/30/20 05/30/22 the launch pit for moving an enclosure into place over the launch pit on the embedded plates, 19 months after award through BOD.

Phase Plan Note 5 The operations support building shall be 10/30/20 05/30/22 substantially complete on/prior to 19 months after the date of award. the test equipment design/fabrication team shall be permitted coordinated and non-impactful access to the low bay launch control center and launch control center equipment room through the double doors on the north side of the launch control center. completed improvements in these areas shall include but not be limited to electrical power, interior finishes and heating and air conditioning systems.

Phase Plan Note 6 The entire facility must be substantially 10/30/20 08/15/22 complete and fully accessibly to the test equipment design and fabrication team. 21 months, 15 days after date of award.

d. If the work of a particular phase is complete and accepted before the scheduled completion day, immediately begin work on the subsequent phase unless otherwise restricted.

(End of NAVFAC language)

The following have been deleted:

BLOCK 14 CONTINUATION PAGE

(End of Summary of Changes)

File details come from the government source that posted it. Updated .