Amendment 0011.pdf
PDF 187 KB Posted
- Solicitation number
- N4008519R9186
About this file
This document summarizes a federal contract solicitation for the design and construction of an Underwater Launch Test Facility. The solicitation requires construction starting in June 2020 and equipment outfitting in September 2021. Key work includes an Underwater Launch Pit, Operational Support Building, Warehouse Building, Water Treatment Facility, and Mechanical and Electrical Building. Supporting site work involves pavements, utilities, and environmental mitigation. Construction will be phased with deadlines for storage pad completion at seven months, shared pit access at twelve months, shared low bay access at sixteen months, and overall completion at eighteen months after award. The solicitation is issued by the Naval Facilities Engineering Command for qualified offerors to design and build specialized test facilities supporting submerged launch operations at Crane, Indiana.
View the file
Other files
Show 40 more
Latest 50 of 115 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
DBB P409 ULTF at NSA Crane, IN
The purpose of this amendment is as follow s:
1. Provide responses to remaining PPIs;
2. Provide Phased Construction Schedule;
3. Revised Liquidated Damages Clause
POC: Gary Milton, gary.milton1@navy.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 21
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9186
X 9B. DATED (SEE ITEM 11)
11-Dec-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Jun-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9186
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
BLOCK 14 CONTINUATION PAGE
The purpose of this amendment is as follows:
a. Provide responses to remaining PPIs
b. Provided Phased Construction Schedule
c. Provided revised Liquidated Damages clause
a. Responses to remaining PPIs
PPI
Date Submitted
LEAVE
BLANK
Reference Response
Page Section Paragraph Question
70 06/05/20 Dwgs. 256, 257, 260, and 261 of
The proposed new aerial fiber optic crosses several railroads and highways. Are these infrastructure crossings entirely government owned or will railroad protective liability (RPL) insurance, permit fees, and/or flagger expenses be required with this proposal?
Response to be provided in a future amendment.
71 06/05/20 Div 25, 26, 28, and 33
Will the Buy American Act or Trade Agreement Act apply to the dry type transformers, the large liquid filled transformers, or the smaller panelboards required? It is our understanding that this equipment is not covered by Spec 01 30
01.00 for the FFE package.
Spec section 01 30
01.00 does not apply to the referenced equipment. The Buy American Act and Trade Agreements Act applies to this project as a whole, no exemptions. Referenc e FAR clause 52.225- 12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements, and FAR Clause 52.225-11 Buy American -
Construction Materials Under Trade Agreements), included with the solicitation package
72 06/05/20 Dwg 336 of
26 13 26 2.3.c page 5 Drawing UTF-E-105 seems to indicate a typical outdoor aisle switchgear enclosure, however 261326 paragraph 2.3.c mentions cooling. The drawing doesn’t appear to show HVAC installed on the enclosure. Is a typical MVA outdoor enclosure required or an IPA solution?
(Response: The intent is for the switchgear manufacturer to provide the switchgear, enclosure, lighting, receptacles, heating and air conditioning for the aisle, AC and DC panelboards as a package.)
73 06/05/20 Dwgs 297 of 742
Drawing UTF-ES602 note 2 and note 4 appear to indicate the (2) transformers associated with the VFD’s, the VFD’s themselves, the (2) MV Swithgear units, and (4) MCC's are provided by others.
Please confirm.
Equipment within the Crossflow VFD Area (keynote 2) and the M&E Building (MEB) (keynote 4) are provided by others. The (2) MV Swithgear Units
(MVISA & MVISB)
are in the SOW.
74 06/05/20 Dwgs 332 & 333 of
Please confirm that transformer TS-1, the transformer surge arresters, and all Duke Energy installed materials are to be supplied by others.
Transformer TS-1 and the transformer surge arresters are included in the SOW. Only the Duke Energy installed material are by others.
75 06/05/20 31 56 00 2.1.1 Specifications Section 31 56 00, Paragraph
2.1.1 states that the slump for concrete used in the slurry wall shall be a minimum of 7 inches and a maximum of 9 inches. It is our experience from many slurry wall projects all over the world that the slump flow value is better suited for measurement of workability of tremie concrete used in slurry walls.
We respectfully request
The original slump requirement of 7" to 9" is consistent with the "Industry Practice Standards and DFI Practice Guidelines for Structural Slurry Walls" published in 2005 by the Deep Foundations Institute.
However, this was published in 2005 and does warrant reconsideration based on newly accepted industry standards.
ASTM C143 notes that for slumps the specification to allow an alternate to slump by using a slump flow value of 21" ±2".
Should the Government object to the usage of the recommended slump flow value, we respectfully request the Specification to be amended to allow for a maximum slump value of greater than 9” greater than 9", the typical slump test does not provide significance. Agree that slumps greater than 9" are more accurately measured using the suggested slump flow value.
The request for 21" +/- 2" is on the very high end according to "Guide to Tremie Concrete for Deep Foundations" by the joint EFFC/DFI Concrete Task Group.
Slump flow value as a means of providing slump testing will be permitted, but the allowable slump flow shall be 19" +/- 2".
76 06/05/20 31 56 00 3.5.3.1 Specifications Section 31 56 00, Paragraph
3.5.3.1 calls for airlifting of the slurry wall panels 1 hour immediately prior to placing concrete. Since the excavation will be carried out with a trench cutter type equipment which utilizes a powerful submersible pump to remove the cuttings and subsequently clean the bottom of the excavation, the requirement for airlifting is not needed.
Furthermore, the specified requirement would mean airlifting while the cage is already in the panel.
The best practice is to proceed with placing concrete as soon as the cage is in without further delay. We respectfully request that
Since the excavation will be completed with a trench cutter type equipment and is predominately in rock, the requirement is revised.
Consider the requirement to clean the bottom of the panel by air lifting within 1 hour removed from Section
3.5.3.1. However, the
sand content measured 12" above the bottom of the trench within 1 hour of placing concrete will still need to meet the necessary requirements.
Furthermore, consider "Step A" of Section
3.4.5 reworded slightly to ensure the panel is cleaned by hydromill equipment within 24 hours of this requirement be removed from the Specifications.
concrete placement.
"Cleaning of panel must be done by hydromill equipment or other approved method. The cleaning operations must be completed within 24 hours prior to initiation of concrete placement."
77 06/05/20 31 56 00 2.1.1.1 Specifications Section 31 56 00, Paragraph 2.1.1.1, the fly ash content in cementitious material is defined as 10 to 15 percent.
Is it possible to increase the fly ash proportion of the cementitious material to 35 percent or alternative slag proportion of the cementitious material up to 50 percent?
Per PPI Response # 39, the maximum fly ash content in Section
2.1.1.1 of 31 56 00 is changed to 25 percent. The maximum fly ash content is further revised to 35 percent in Section 2.1.1.1 of 31 56 00 per request.
However, consistent with notes on Drawing LPS-S-101, the concrete used in the slurry wall shall be shown to have a minimum compressive strength of 5,000 psi at 28 days.
The use of Ground Granulated Blast- Furnance Slag (GGBS) conforming to ASTM C989 for a portion of the cementitious material will be accepted. The maximum percent of total cementitous materials by weight including fly ash and GGBS shall not exceed 50 percent.
78 06/05/20 12 and 21 31 00 00 3.2.5.2,
3.2.5.3 and 3.8.1
Specification require the removal and replacement of Unyielding and Unstable material in excavations.
No additional compensation will be provided for unyielding materials.
Review the geotechnical report
How will the bidder be compensated for this additional work?
for subsurface information.
Compensation for removal, disposal and replacement of unanticipated unstable and unsatisfactoray material will be evaluated if encountered.
79 06/05/20 22 31 00 00 3.9 The specification states to stockpile and use coarse rock from excavations for constructing slopes or embankments next to streams.
Is the intent of this specifation to utilize all the rock from excavations on site?
Utilize excavated material where suitable and can meet specification requirements for general site fill, embankment slopes or stream bank protection. Transport approximately 12,000 cy to the designated stockpile location on Base. The remaining excess must be removed from the base.
80 06/08/20 Sheet 358 Volume 3 Drawing
On drawing OSB-S- 202/ C1 calls for double angle braces but calls out for L6x4x1/2x3/4LBB.
How thick is the angle?
This seems to be a typo.
Also similar notation are used on other structural elevation drawings like WHS-S-
201, WTB-S-201,
MEB-S-201.
Please clarify?
The double angle braces in the OSB, WHS, WTB and MEB follows the notation "A"x"B"x"C"x"D", where "A" and "B" are the lengths of each toe of the angle, "C" is the thickness of each angle, and "D" is the spacing between the two angles. Details OSB- S-505/ C1 and C2 show the 3/4" gusset plates and intermediate spacing plates that will be placed in the gap between the angles.
81 06/08/20 150 Volume 2 Drawings
LP-CS401 (sheet 150 of
742) shows WALL
MOUNTED LADDER
WITH REMOVABLE
ENTRY SYSTEM
AND LANDINGS
PLATFORMS,
referring drawing UTF-
The ladder and railing system must be fabricated by a company having a minimum of 10 years experience specifically fabricating ladder and
C-516 for details.
Our steel fabricator found there is not much detail on how the ladder is made or the platforms attached.
Please provide more details for the adequate pricing?
platform systems. All materials must be high grade structural aluminum. Working load limit must support 1000 lbs without failure. All fittings and attachments must be designed by the manufacturer. The system must be OSHA compliant and have a 10 year warranty. Submit shop drawing for approval.
82 06/08/20 223 Volume 2 Drawings
Drawing LPS-S-137 Slab Plan shows a longitudinal construction joint and optional transverse construction joints (see Note 3). NOTE 3 states "At the Contractor’s option, transverse joints may be used in the slab.
If using transverse joints the slab shall be placed in 8 pours with with joints placed at a maximum of 42 ft".
Is the intent that the base slab shall be poured either in 2 or 8 pours and no other combination pour combination allowed?
Please confirm.
The intent of the note was that the slab would be poured in either 2 pours or 8 pours. However, other combinations of pours, such as 4 for instance, utilizing the transverse and longitudinal constructions joints shown on LPS-S-137 would be approved.
The thermal modeling and thermal gauges required for mass concrete would have to be consistent with the selected slab pouring sequence.
84 6.9.20 UTF-C-001
(51 or 742)
Grading Notes
13 & 30 Note 13 states that the Contractor my Process the Rock onsite to minimize export. Note 30 on the same page states that the Aggregate Base must be INDOT #53 Base.
Please clarify if processed stone meeting the INDOT #53 gradation, but not having an INDOT certification is acceptable.
Substitution of INDOT #53 with processed on-site materials is acceptable contingent upon the material meeting the strength , durability and gradation of INDOT #53. Submit appropriate lab reports for approval.
87 6.9.20 WTB-D-
Details A1 & A3 are shown as having the same scale of 3/32"=1'- 0". Please confirm the proper scale for detail A3.
Detail A1 scale is correct. Detail A3 is Not to Scale.
88 6.9.20 42 22 00 00 Table II Drawing WTB-DT550 PIPE SCHEDULE lists the compressed air pipe as SSt/AL material, following spec 22 00
00. However Table II in this spec lists pipe under Service C (Compressed Air Lubricated) as carbon steel or copper pipe.
Please verify the correct material for the compressed air piping, and the spec section applicable.
Black steel or copper is fine within the building, however all CA piping outside of the compressor building and into the pit must be SS (See A1 Pneumatic Schematic on Dwg
WTB-DT502)
89 6.9.20 17 40 05 13 2.7.10.3 Valve manufacturers are telling us that regarding the electric operators, they cannot meet the rating/torque requirements of the 6" & 8" butterfly valves and still be under a 15 lb weight limit. Please confirm this weight limit is not applicable.
This requirement can be waived.
90 6.9.20 WTB-D-
Detail A1 Detail A1 Sanitary Lift Station Section notes the Precast Wet Well is provided by Others.
Please verify furnishing of this wet well is not in our scope of work. Will it also be installed by others, or delivered to the site for for the contractor to install?
The wet well is included in the contract. Disregard "Provided By Others". Just to clarify, the pump station vendor generally only provides the aboveground unit and not the wet well.
91 6.9.20 WTB-D-
Detail A1 If the contractor is responsible to furnish the Sanitary Lift Station Wet Well (see previous question), one note indicates the wet well is to be HDPE lined, while the note directly below it indicates it is to receive a bitumastic coating and points to
Bitumastic coating should be indicated on outside. HDPE lining is correct.
the inside of the wet well. Please verify if the wet well is to receive a HDPE liner or a bitumastic coating.
92 6.9.20 OSB-P-601 On the Air Compressor Schedule on OSB-P- 601, AC-2 shows that it serves the LRSE Building. Other than the underground compressed air lines shown on UTF-CU102 (no size indicated), we cannot locate any Plumbing or Process drawings which indicate what this air compressor AC-2 serves. Please provide drawing of what this system serves, pipe routing, and pipe sizing if it is to be included in our scope.
Detail A1 on sheet UTF-C-511 provides the pipe size, material stub-up locations and requirements. Sheets LP-CG401 and 402 indicates the pipe routing.
93 6.9.20 UTF-
CU102
Sheet UTF-CU102 shows a lines labeled as HPA running between the Cross Flow Pit and the Launch Pit. "HPA" is not one of the lines identified on the
PIPING SCHEDULE
on WTB-DT504. What is this line? Where does it run to/from? What is the sizing? What are the specs?
See Legend on UTF- C-004 for HPA line designation. Detail A1 on sheet UTF-C- 511 provides the pipe size, material stub-up locations and requirements. Sheets LP-CG401 and 402 indicates the pipe routing. See spec section 22 15 13.16
94 6/10/2020 WTB-A-
101, and
WTB-A-
Keynote 3 on Page WTB-A-101 notes the raised platform in the WTB as '4' H grated raised steel' but detail C1 on Page WTB-A- 404 notes the platform as 1-1/2" Fiberglass Grating. What is the raised platform made of
- steel or FRP?
Keynote #3 on WTB - A- A-101 describes that the raised steel framed platform is 4 feet high off of the concrete floor slab.
This should indicate 3' - 9 1/2" instead of 4' to match the details on sheet WTB-A-404.
Plan detail C1 on
WTB -A-404
describes that the finished floor is a 1 1/2" thk. fiberglass grating that is secured to the steel floor framing system of the raised platform.
Therefore, a 1 1/2" thk. fiberglass grating is mounted to the raised steel platform creating a floor surface to it can be accessed to get to the equipment on the platform. Note the steps up on the right.
Fiberglass flooring.
Also see WTB-S-503 and 504
95 6/10/2020 C-002, C104
Per C-002 (sheet 52), note 7, we are to haul off material off-site. On C-104 (sheet 58), there is a brush export stockpile shown. Please confirm that we will be allowed to use the brush stockpile shown.
Confirmed
96 6/10/2020 CG111,
CG112
Per CG111 and 112 (sheets 86, 87), it shows to restore disturbance with bituminous pavement from STA 16+00 to 23+30 on Hwy 486. Please confirm that the rest of the pavement on Hwy 486 is gravel.
Confirmed
97 6/10/2020 OSB-A-012 04 00 00 Wall Partition types 10 and 13 do not label the size and finish of the CMU shown. Please advise.
All masonry shown for this project are 8" x 8" x 16" CMU.
98 6/10/2020 UTF-C-002 Utility note 24 on C- 002 call for temporary power until the electric is extended to the site.
When will the electric be extended to the site?
Duke Energy infrastructure extension to the site will be completed prior to September 30, 2020. Connection to the facility substation is pending contractor completion of the facility substation. Duke Energy power will not be available until after the substation is complete. Coordinate with the contracting officer 8 weeks prior to completion.
100 6/10/2020 Page 15 RFI29 &
UTF-C-103
The answer states note 32 will be revised to indicated 10 months.
Was it your intent to reissue Drawing UTF- C-001 and not UTF-C- 103 to show the change to match the RFI? The purpose of this question is to find out why UTF- C-103 was issued by Ammendment 0008.
(Please note: The title block and dates for UTF-C-103 match the Ammendment 0007 issuance of this drawing and it appears there are no changes on UTF-C- 103 attached to Ammendment 0008)
The duration is 10 months, not 7 months.
Sheet UTF-C-103 correctly indicates 10 months.
101 6/10/2020 C-503 Per detail A3, Crane Pad Typical Detail, there is a note for existing subgrade that points to a layer of compacted aggregate.
Please confirm the existing subgrade elevation that we are to start construction from.
Disregard the "Existing Subgrade" note. See the response to PPI #12. Submit shop drawing for approval.
102 6/10/2020 ES111-
ES121
For the new fiber optic cable extension, please confirm that all utility poles, besides utility pole UP-S1, are either existing or furnished and installed by Duke Energy.
Confirmed
103 6/10/2020 UTF-C-506 Detail A2 on sheet UTF-C-506 shows a surface mounted bollard. Please clarify whether the bollard is concrete filled. Also, please clarify whether the cap on top of the bollard steel or HDPE.
Concrete filled with steel cap
104 6/10/2020 WTB-DP-
4/18/1965 Sheet WTB-DP-101 shows two hypochlorite storage totes in the Chemical Area #3 room. Please confirm that these are the two chemical storage units refered to in spec section 13 34 23.
Correct
105 6/10/2020 WTB-S-506 Detail C4 on sheet WTB-S-506 shows the connection of the eave plate at the roof. Please confirm whether the eave plate and the channel supports need to be welded in the field or if they can be welded in the shop and brought out to the site.
Field welds were indicated to allow for flexibility in plate placement (to avoid conflicts with connections, other discipline elements, etc.). Shop welds are permitted, however, provided the contractor coordinates plate placement with all other elements.
106 6/10/2020 WTB-S-506 Detail C1 on sheet WTB-S-506 showsthe connection of the rake plate at the roof. Please confirm whether the rake plate and the channel supports need to be welded in the field or if they can be welded in the shop and brought out to the site.
Field welds were indicated to allow for flexibility in plate placement (to avoid conflicts with connections, other discipline elements, etc.). Shop welds are permitted, however, provided the contractor coordinates plate placement with all other elements.
107 6/10/2020 ES114-
ES121
There are multiple utility poles labeled
"POLE TO BE
REPLACED". Please provide detailed information as to the equipment and cabling that is currently installed on all poles that are labeled to be replaced.
Disregard the "POLE
TO BE REPLACED"
note. No utility poles need to be replaced.
108 6/10/2020 ES115 Pole "3-58 1/2" has a note "POLE TO BE REMOVED". Does this pole need to be replaced with a new pole?
Disregard the "POLE
TO BE REMOVED"
note. No utility poles need to be replaced.
109 6/10/2020 ES610 There is a note 14 near CHH-DE. However, there is no 14 in
14. A 4-Foot Long by 4-Foot Wide by 4- Foot Deep
Keynotes. Please provide Keynote #14
Communications Handhole CHH-DE, provided by Duke Energy. Added Sheet Keynote 3 to CHH- DE and revised the description of Sheet Keynote 10. See attached drawing
UTF-ES610.
110 06/09/20 17 31 00 00 Earthwork q Specifications call out for the contractor to perform a pre and post blast inspection of all structures on the project site and all structures within the area shown on the plans. However we have not found the map indicating which structures and what distances these inspections are to be done.
Please provide.
The intent is to monitor the site during blasting, including structures constructed during this contract as well as the closest magazine storage building. The base expressed concerns with the Lake Greenwood dam, the closest point being the spillway. No other structures are near the site. The PPV for these locations is included 31 00 00 3.2.5.5
111 06/09/20 14 31 00 00 Earthwork f Peak Particle Velocities for blasting are not exceed 2.0 inches per second for structures onsite.
What is the criteria or for onsite structures?
For instance, once the slurry walls are constructed will they be considered an onsite structure? Typically structures are inhabited structures.
Please clarify.
Structures include newly constructed structures under this contract as well as the nearest magazine storage building and the Lake Greenwood dam. None of these structures are inhabited but the Base expressed concern that monitoring occur to ensure their integrity. See 31 00 00 3.2.5.5
112 06/09/20 5 31 00 00 Earthwork
1.3.2 Section 31 page 5 of
Volume 4 specifications call out for a blasting plan to be prepared and sealed by a registered professional engineer. There are really no registered professional engineers that are blasters or blasting
The intent is that a Qualified Person with experience as a blasting consultant prepare the plan. The professional engineer requirement was intended to ensure that the planned generated blast accelerations do not consultants. We request that this specification be changed to replace the RPE and add QP (Qualified Person).
The USACE's definition for QP - Qualified person: one who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated his/her ability to solve or resolve problems related to the subject matter, the work, or the project.
Please consider this request.
damage any new or existing structures and requires a review of the overpressure and the potential extent of flying rock.
A blasting consultant should prepare the plan and the plan be reviewed by an engineer.
113 06/09/20 29 Volume 1 Specificatio n
3.7.5 Are we going to be able
to set up a magazine site on the facility somewhere? This will be the safest and most efficient to store the explosives onsite without have to bring them in and out everyday. Transportatio n is always your biggest safety exposure. Specification Volume 1 3.7.5 states that onsite storage is possible "when permitted”.
Response to be provided in a future amendment.
114 06/09/20 Addendum 6 - Question
Per Addendum 6, Question #53, the response clarified that all surplus excavated material is clean. Could the Navy confirm that excess excavated material (beyond the 12,000 CY which has a defined dump location on Base) is to be hauled outside of the Navy Base limits?
Confirmed
115 06/10/20 9 Please confirm that the prime contractor shall receive credit toward percentage goals set forth in the Small Business Subcontracting Plan for small business concerns performing as both first-tier and lower-tier subcontractors.
Only first tier subcontractors will be credited.
117 06/10/20 UTF-C-003 Volume 1 Drawings
UTF-C-003 shows that all the concrete (slabs on ground, footings, retaining wall, and other concrete including piers) is 4,000 PSI.
However, in OSB-S- 003, it states in the concrete material schedule note 2, that exterior concrete applies to stoops, aprons, equipment pads, etc. Outside the building envelope that are exposed to weather to be 5,000 PSI. Is this the owner’s intent to use 5,000 PSI only shown on the building concrete drawings?
The exterior concrete shown on the structural building drawings shall comply with ACI 318-14 requirements for exposure class F3 (concrete subjected to deicing chemicals), which requires 5000 psi strength -- such concrete includes door stoops; slab on ground below Warehouse canopy;
WSA foundation; and FPE foundation.
Exterior concrete elements shown elsewhere (e.g. civil drawings, launch pit drawings) shall comply with requirements of the drawings on which said concrete elements are shown.
The structural drawings shall govern over the civil drawings in the locations referenced.
121 06/11/20 3 01 32 17.00
1.8 Spec section 01 32
17.00 20 paragraph 1.8 requires the contractor to “Prepare and maintain project schedules using Microsoft Projects….”.
However under Paragraph 1.10.3 they talk about “at a minimum, include the following settings
Confirmed contractor will use Primavera P6, not Microsoft Project.
….these settings requirements pertain to Primavera settings and Not Microsoft Project.
We request to use the industry standard Primavera P6. Please confirm the contractor can utilize Primavera P6 to prepare and maintain project schedules.
122 06/11/20 11 01 32 17.00
1.10.3 2. Specification 01 32
17.00 20 paragraph
1.10.3 provides Schedule Software Setting and Restrictions.
The settings and restrictions provided in sub paragraphs 1.10.3 c., d., d(1), d(2), d(3), d(4), d(5), d(6), d(7) and d(8) are all written for Primavera P6 schedule software settings and are not available in Microsoft Project settings. Please allow the contractor to utilize Primavera P6 to prepare and maintain projects schedules. Or rewrite the above mentioned specification sections utilizing applicable Microsoft Project schedule settings and not Primavera Schedule Settings.
Confirmed contractor will use Primavera P6, not Microsoft Project.
124 06/11/20 PPI 33
Attachemen t
Two different Revisions to 01 57 19 were provided in Amendment 8, please clarify which document is to be used.
PPI 33 attachment Rev 1, spec section 01 45 00.00 20 is to be used. Only one attachment for 01 57 19 was provided.
130 06/08/20 (93)
UTF-
CU102
Air Compressor Enclosure - Plans show air lines leaving the compressor building in two directions but no additional information at Launch Pit as to where these lines terminate, continue to or connnect to. Please
Detail A1 on sheet UTF-C-511 provides the pipe size, material stub-up locations and requirements. Sheets LP-CG401 and 402 indicates the pipe routing. Also see PPI 92 and the response clarify.
131 06/08/20 (93) UTF-
CU102
(642) WTB-
DP103
22 15 13.16
Spec section 22 15
13.16 40 describes several different types of pipe materials for compressed air piping.
Plan shet UTF-CU-102 doesn't indicate pipe material. Plan sheet WTB-DP103 doesn't indicate pipe material.
Please clarify the intended pipe material to be used for interconnecting inside the building, underground and exposed.
See Detail A1 on sheet UTF-C-511 for the pipe size, material stub-up locations and requirements for piping at the Launch Pit area. Sheets LP- CG401 and 402 indicates the pipe routing. See spec section 22 15 13.16 40 for High Pressure Air and 22 00 00 for service air. See WTB- DT504 for pipe material in that building. See attached edits to Spec section 22 00 00
132 06/08/20 (124)
UTF-C-503
A3 Is there a specification or detail on the construction/assembly of the hardwood crane mat sections?
The crane mats shall be purchased from a Crane Mat Manufacturing company with a minimum of 10 years experience fabricating hardwood crane mats.
The mats shall be solid hardwoods or oak and delivered to the jobsite pre-assembled. The detail indicates 8' wide but 6' wide would also be acceptable.
133 06/08/20 33 32 13.13 1.3 The 4th paragraph states 'approved equals' shall be submitted for approval 15 days prior to bid date. There is no basis of design manufacturer listed for the pumps nor a list of acceptable pump manufacturers. Please provide both the basis of design pump manufacturer and approved equal pump manufacturers.
Design Basis for the Grinder Pumps - Make: Sulzer; Model:
Piranha PE100/2-E- 60 Hz, proposed approved equals must be submitted for approval.
134 06/08/20 Geotechnica l Report
It is not clear if the Geotechnical Design Report prepared by Jacobs/Terracon, Underwater Launch Test Facet, dated February 28, 2020, is a Contract Document.
Please clarify. If it is not a Contract Document, please identify the technical data in the report upon which the Contractor may rely.
Yes, it is a contract document
136 06/11/20 13 and 14 31 00 00 Page 13 a. Slurry Wall Protection indicates the contractor is responsible for designing & providing cushion to protect the slurry wall.
Page 14 paragraph f.
indicates peak particle velocity of each component. Please detail what the "Structures onsite" is refering to with a PPV of 2.0 inches per second? We have assumed that this requirement does not apply to our slurry wall per the requirements indicated on page 13 above. We will design the appropriate PPV for the blasing around the slurry wall. Please confirm
The intent is to confirm to the base that the nearby magazine structures and the dam not be damaged. The PPV given for them is 0.5 ips. This was brought up by the owner several times and is not believed to be an issue to either off site location. The blaster should consider any newly constructed structures, including the slurry wall to avoid damage. There are no known existing structures on site.
137 06/11/20 5 05 12 00 1.3 Per paragraph 1.3 the "Work must be fabricated by an AISC Certified Steel Fabricator" Can this requirement be waived or modified for this project. Many of the local, instate, certifed SBE suppliers do not have this certification.
This requirement is eliminating several good qualified companies.
No. This requirement ensures a desired steel quality level and is intended to preclude rework (and costs thereof). AISC's Certified Company Search tool shows 27 steel fabricators within the state of Indiana that maintain BU (building) certification.
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
SUPPLEMENTARY INSTRUCTIONS
b. Phased Construction Schedule
Within the overall project schedule, commence and complete the work in phases. Complete each phase of the work within the number of calendar days stated in the following schedule:
a. Schedule start day: The day designated as the beginning of a particular phase; the number listed is the number of calendar days from the award of contract.
b. Completion day: The day designated as the end of a given phase and the day the work in that phase must be completed; the number listed is the number of calendar days from the award of the contract.
c. Schedule:
NOTE: Determine the number of days required for each phase.
Phase Description Scheduled Start Date Completion Date
Phase Plan Note 3 The following must be 100% complete 9/15/20 07/15/21 ꞏ relocated highway 486 ꞏ test equipment staging area ꞏ installation of foundations, concrete pads, trenching, conduit and other site improvements within test equipment staging area. 10 months after date of award.
Phase Plan Note 4a The launch pit shall be substantially 9/15/20 12/15/21 and 4b complete on/prior to 15 months after the date of award. the test equipment design/fabrication team shall be permitted coordinated and non-impactful access as identified below:
a.) crane access to all sides of the launch pit and cross flow area, 15 months after award through BOD.
b.) access to the west wall of the launch pit and sheave area for test equipment installation, 15 months after award through BOD.
Phase Plan Note 4c c.) access to the launch pit floor for test 9/15/20 01/15/22 equipment installation, 16 months after award through BOD.
Phase Plan Note 4d d.) access to the cross flow winch area 9/15/20 02/15/22 for test equipment installation, 17 months after award through BOD.
Phase Plan Note 4e e.) access to the VFD area for test 9/15/20 3/15/22 equipment installation, 18 months after award through BOD.
Phase Plan Note 4f f.) access from the test equipment pad to 9/15/20 4/15/22 the launch pit for moving an enclosure into place over the launch pit on the embedded plates, 19 months after award through BOD.
Phase Plan Note 5 The operations support building shall be 9/15/20 4/15/22 substantially complete on/prior to 19 months after the date of award. the test equipment design/fabrication team shall be permitted coordinated and non-impactful access to the low bay launch control center and launch control center equipment room through the double doors on the north side of the launch control center. completed improvements in these areas shall include but not be limited to electrical power, interior finishes and heating and air conditioning systems.
Phase Plan Note 6 The entire facility must be substantially 9/15/20 06/30/22 complete and fully accessibly to the test equipment design and fabrication team. 21 months, 15 days after date of award.
d. If the work of a particular phase is complete and accepted before the scheduled completion day, immediately begin work on the subsequent phase unless otherwise restricted.
(End of NAVFAC language)
c. DELETE THE FOLLOWING CAUSE:
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $40,000 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
REPLACE WITH:
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of (See Phased Liquidated Damage amounts listed below) for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
Phased Liquidated Damages amounts Contractors are advised that LD’s will be assessed on a per calendar day basis, in the amounts shown below for the phases indicated in the plans and specs. Please refer to Sheet 57 of 742 Drawing UTF-C-103, Phasing Plan Notes 3, 4, 5, and 6.
Phasing Plan Notes 3- $30k per cal day Phasing Plan Notes 4- $25k per cal day Phasing Plan Notes 5- $20k per cal day Phasing Plan Notes 6- $20k per cal day
(End of Summary of Changes)