Amend 0001_SF30.pdf
PDF 375 KB Posted
- Solicitation number
- N4008425R0066
About this file
This is Amendment 0001 to solicitation N4008425R0066 for an Indefinite Delivery/Indefinite Quantity (IDIQ) Design-Bid-Build Multiple Award Construction Contract (MACC) for Atsugi, Japan. The amendment was issued on March 5, 2025 by NAVFAC Far East.
The amendment provides responses to pre-proposal inquiries (PPI) numbers 001-007, updates the Contract Specialist's email address to emiko.uyama2.ln@us.navy.mil, and adds Atsugi DBB MACC Seed Project Drawings (Enclosures 1 and 2). The amendment does not extend the original solicitation response date of February 28, 2025. Offerors must acknowledge this amendment in Block 19 of Standard Form 1442. The document includes a comprehensive list of solicitation sections (00 10 00 through 00 73 02) and attachments including pre-proposal inquiry forms, specifications, seed project documents, site visit request lists, and various exhibits covering construction experience, past performance, safety requirements, and pricing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0004.pdf | ||
| Amend 0004 Enclosure 1_PPI.pdf | ||
| Amd 0003 Enclosure 1_PPI.pdf | ||
| N4008425R0066-Amendment 0003.pdf | ||
| Pre-proposal Conference Slides_25 Mar 2025 Fin.pptx | PPTX presentation | |
| N4008425R0066 Amendment 0002_PPI Attachment 1 - EXHIBIT A.docx | DOCX document | |
| N4008425R0066 Amendment 0002_21MAR25.pdf | ||
| Amd 0002 Enclosure 1_PPI.pdf | ||
| N4008425R0066 Amendment 0002_PPI Attachment 1 - EXHIBIT C.docx | DOCX document | |
| Amend 0001_Encl 1_Inquiry and Response.pdf | ||
| 4_Site Visit Request List.xlsx | XLSX spreadsheet | |
| EXHIBIT A thru D.pdf | ||
| N4008425R0066_SF1442.pdf | ||
| 1_Pre-Bid_Inquiry_Form.xlsx | XLSX spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ), DESIGN-BID-BUILD MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR
ATSUGI, JAPAN
See Continuation Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Mar-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008425R0066
X 9B. DATED (SEE ITEM 11)
28-Feb-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Mar-2025
CODE
NAVFAC FAR EAST
CORE EXECUTION TEAM
PSC 473 BOX 13
FPO AP 96349-0013
N40084 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008425R0066
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0001
A. Government response to pre-proposal inquiries (PPI) numbers 001 through 007 are provided as Enclosure
(1) to this amendment. The solicitation remains unchanged unless it is amended in writing on a Standard Form 30.
B. Contract Specialist Email address stated in Section 00 10 00 – Solicitation “10. Pre-Proposal Inquiries (PPI)”, and 00 21 16 – Instruction to Proposers “1 PRE-PROPOSAL INQUIRIES (PPIs)” is changed to emiko.uyama2.ln@us.navy.mil
C. Atsugi DBB MACC Seed Project Drawings are added.
SF1442 SECTION TITLE
00 10 00 Solicitation 00 21 00 Instructions (Solicitation Provisions) 00 21 16 Instructions to Proposers 00 22 16 Supplementary Instructions to Proposers (Evaluation Factors for Award) 00 45 00 Representations and Certifications 00 70 00 Conditions of the Contract 00 72 00 General Conditions (Contract Clauses) 00 73 00 Supplementary Conditions 00 73 01 Contract Type / Performance; Special Contract Requirements 00 73 02 Task Order Issuance Procedures
ATTACHMENT TITLE
1 Pre-Proposal Inquiry Form 2 Atsugi DBB MACC Specification 3 Atsugi DBB MACC Seed Project 4 Site Visit Request List 5 Atsugi DBB MACC Seed Project Drawing – Enclosure 1 6 Atsugi DBB MACC Seed Project Drawing – Enclosure 2
Exhibit TITLE A Construction Experience Project Data Sheet B Past Performance Questionnaire C Safety Narrative D Price Proposal Form
D. Offerors shall acknowledge this amendment in Block 19 of the Standard Form 1442 submitted.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .