RFQ N4008024R2225 Amend 0005.pdf

PDF 1 MB Posted

Attached to
Regional Hazardous Waste Services
Solicitation number
N4008024R2225
Issued by

About this file

This document is Amendment 0005 to a Request for Proposal (RFP) for a firm fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract to provide recurring and non-recurring hazardous waste management services at various Navy and Marine Corps locations in the Washington D.C. metropolitan area.

The amendment addresses changes to the contract requirements, including revisions to the Performance Work Statement in Sections C and F, as well as changes to FAR clauses 52.212-1 and 52.212-2. The contract has a base year and four 12-month option years, plus a 6-month option to extend services. This is a 100% small business set-aside opportunity under NAICS code 562112 for Hazardous Waste Collection. Proposals are due on August 15, 2024 by 12:00 pm Eastern Time.

View the file

Other files

File Type Posted
Section J 0200000-01 thru 06.pdf PDF
SECTION J-180000-01 thru 04.pdf PDF
Copy of RFI RESPONSES N4008024R2225 Final.xlsx XLSX spreadsheet
RFQ N4008024R2225 Entirety.pdf PDF
NEW Copy of ELIN TABLES BLANK Final updated.xlsx XLSX spreadsheet
ATTACHMENT C PPQ.docx DOCX document
N4008024R2225 Amend 0004.pdf PDF
N4008024R2225 AMENDMENT 0004 MEMO SIGNED.pdf PDF
N4008024R2225 AMENDMENT 0003.pdf PDF
J-1800000-01 Historical Data Working (1).xlsx XLSX spreadsheet
N4008024R2225 RFI AMENDMENT.pdf PDF
HAZARDOUS WASTE ATTACHMENT C BLANK PPQ N4008024R2225.pdf PDF
Copy of ELIN TABLES BLANK Final updated.xlsx XLSX spreadsheet
Copy of RFI Questions and Answers.xlsx XLSX spreadsheet
N4008024R2225 HAZARDOUS WASTE RFP AMEND 1.pdf PDF
J-0200000-04 Form Background Check and Access.pdf PDF
WD 2015-4279 REVISION 23.pdf PDF
J-0200000-04- Form I9.pdf PDF
J-0200000-03 29 CFR 1910 - OSH Standards.pdf PDF
WD 2015-4265 REVISION 26.pdf PDF
WD 2015-4329 REVISION 25.pdf PDF
J-0200000-03 NDWINST 5090.1 - Region CHRIMP.pdf PDF
J-0200000-04- Form I9 (1).pdf PDF
J-0200000-04 Form Tass Registration Form (1).pdf PDF
N4008024R2225 HAZARDOUS WASTE RFP.pdf PDF
Copy of ELIN TABLES BLANK Final.xlsx XLSX spreadsheet
WD 2015-4281 REVISION 28.pdf PDF
WD 2015-4269 REVISION 24.pdf PDF
J-0200000-03 NASPAXRIVINST 5090.5A Regulated Waste Management Plan Implementation Order.pdf PDF
J-0200000-04 Form DD 254.pdf PDF
0100000 C General Information Updated MAR 13.docx DOCX document
J-0200000-03 OPNAVINST 5090-1D.pdf PDF
J-0200000-03 NASPAXRIVINST 5090.2A NASPRC FACILITY RESPONSE PLAN AND SPCC.pdf PDF
J-0200000-04 Form Tass Registration Form.pdf PDF
J-0200000-04 Form DD 1172-2 (Blank).pdf PDF
0200000 C Management and Administration (1).docx DOCX document
J-0200000-05 GFF.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REVIEW RFP IN ITS ENTIRETY AS THERE WERE MAJOR CHANGES

This amendment is to address the RFI the governmenrt received and to answ er those questions. Changes to J 0200000 C and F as w ell as chnages to J 18000000 C and F. Additional changes to FAR 52.212-1 and 52.212-2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 71

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Jul-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008024R2225

X 9B. DATED (SEE ITEM 11)

05-Jun-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Jul-2024

CODE

COMNAVFACSYSCOM WASHINGTON

1314 HARWOOD ST

WASHINGTON DC 20374

N40080 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008024R2225

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been modified:

PROPOSAL SUMMARY

Naval Facilities Engineering Systems Command (NAVFAC) Washington 1314 Harwood Street, SE

BLDG 212, 4th Floor Navy Yard Washington, DC 20375

Proposals due date is Thursday 15 August 2024 at 12:00 pm (noon) Eastern Time.

NAVFAC Request for Proposal (RFP) A.1 RFP Description of the requirement:

This requirement is for both recurring and non-recurring, performance based, Hazardous Waste services to provide hazardous waste management operations, watchstanders for specific Navy sites, spill containment / spill control materials cleanup and removal, and hazardous material (HM), hazardous waste (HW), regulated waste (RW) and transportin support of the military missions, within the Washington Navy Yard and various surrounding regional locations throughout the Washington DC Metropolitan area, as shown below:

Washington Navy Yard (WNY) Washington Headquarters Service Pentagon (WHS) United States Marine Corp Barracks (8th and I) Naval Maritime Intelligence Center (NMIC) United States Naval Observatory (USNO) Naval Surface Warfare Center Carderock Division (NSWCCD) Arlington Service Center (ASC) Naval Support Facility Dahlgren (DAHL) Naval Support Facility Indian Head (IH) Naval Support Facility Indian Head, Stump Neck Site (SN) Naval Air Station PAX River and Webster Field (PAX) NRC Solomon’s Island (PAX) PWD Annapolis, United States Naval Academy (USNA) and Naval Support Facility (NSF) Naval Support Activity Bethesda (NSAB) - Primary tenant WRNMMC Naval Support Facility Olney

A.2 Product Service Code / NAICS Code:

The applicable Product Service Code is: V112 which is for: Transporation/Travel/Relocation-Transportation: Motor Freight and: the applicable: North American Industry Classification System Code, is: 562112, which is the code associated with: Hazardous Waste Collection, whose industry comprises establishments primarily engaged in collecting and/or hauling hazardous waste within a local area and/or operating hazardous waste transfer stations.

Hazardous waste collection establishments may be responsible for the identification, treatment, packaging, and labeling of waste for the purposes of transport.

A.3 Set-Aside / Competition Strategy:

This requirement is solicited using provisions of FAR Subsection 19.502-2, restricting this as a 100%, Small

Business Set Aside Competition, amongst responsible Small Business Offerors whom are also, otherwise qualified.

You must be a small business for the above NAICS.

A.4 Type of Contract / Business Arraignment:

One (1) Base Year and four (4) twelve month option years and one (1) six-month option to extend services , Firm Fixed price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) type contract will be solicited, evaluated and awarded. The proposed Contract Line Item Numbers and their associated Periods of Performance (PoP) are shown below:

Contract Year Anticipated PoP Dates Base Year (CLINS 0001 and 0002) 01 February 2025 – 31 January 2026 Option Year 1 (CLINS 0003 and 0004) 01 February 2026 – 31 January 2027 Option Year 2 (CLINS 0005 and 0006) 01 February 2027 – 31 January 2028 Option Year 3 (CLINS 0007 and 0008) 01 February 2028 – 31 January 2029 Option Year 4 (CLINS 0009 and 0010) 01 February 2029 – 31 January 2030 52.217-8 Option to Extend Services (CLIN 0011 and 0012) To be completed no later than 31 July 2030

WAGE DETERMINATION: Service Contract Labor Standards (formerly referred to as Service Contract Act) wage determination. Refer to wage determination attachment.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

PERFORMANCE WORK STATEMENT

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Acquisition of Additional Work

1.3 Background Information

1.4 Navy PBSA Approach

1.5 Standard Template

1.6 Related Information

1.7 Verification of Workload and Conditions

Partnering Philosophy

1.8 Contractor's Knowledge

1.9 Technical Proposal Certification

0100000 – General Information Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, sampling and other items necessary to provide hazardous waste management operations, watchstanders for specific Navy sites, spill containment / spill control materials cleanup and removal, and hazardous material (HM), hazardous waste (HW), regulated waste (RW) and transport outlined below and described in this Performance Work Statement (PWS) at various Navy and Marine Corps locations in the District of Columbia, Maryland, and Virginia and geographical area “outside the fence line”, where there is a potential for either Recurring Work may be added to the contract or Non-Recurring work issued, e.g., Naval Air Station Jacksonville, Florida and outlying areas supported by this installation performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.

Various locations shall include:

Washington Navy Yard (WNY) Washington Headquarters Service Pentagon (WHS) United States Marine Corp Barracks (8th and I) Naval Maritime Intelligence Center (NMIC) United States Naval Observatory (USNO) Naval Surface Warfare Center Carderock Division (NSWCCD) Arlington Service Center (ASC) Naval Support Facility Dahlgren (DAHL) Naval Support Facility Indian Head (IH) Naval Support Facility Indian Head, Stump Neck Site (SN) Naval Air Station PAX River and Webster Field (PAX) NRC Solomon’s Island (PAX) PWD Annapolis, United States Naval Academy (USNA) and Naval

Support Facility (NSF) Naval Support Activity Bethesda (NSAB) - Primary tenant WRNMMC Naval Support Facility Olney

The PWS is organized into annexes. Annex 1 is "General Information". Annex 2 contains the on-site project management and administration requirements.

Annexes 3 through 18 contain the technical requirements. The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff (N/A) Annex 4 Public Safety( N/A) Annex 5 Air Operations ( N/A) Annex 6 Port Operations ( N/A) Annex 7 Ordnance ( N/A) Annex 8 Range Operations ( N/A) Annex 9 Health Care Support ( N/A) Annex 10 Supply ( N/A) Annex 11 Personnel Support ( N/A) Annex 12 Morale, Welfare and Recreation Support ( N/A) Annex 13 Galley ( N/A)

Annex 14 Housing ( N/A) Annex 15 Facilities Support ( N/A) Annex 16 Utilities ( N/A) Annex 17 Base Support Vehicles and Equipment ( N/A) Annex 18 Environmental

1.2 Acquisition of Additional

Work

The Government reserves the right to acquire additional environmental services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.3 Background Information Hazardous Waste Services are provided to various DON locations within 100 mile radius of the Washington Navy Yard by means of a combination Recurring Work and Non-Recurring Work contract.

1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.

The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements. Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items. Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated to the Exhibit Line Items.

1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.7 Verification of Workload

and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.

All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.9 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

0200000 – Management and Administration

Spec Item Title 2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities

2.4.3 Government-Furnished Vehicles and Equipment

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Work Reception

2.6.2 Work Control

2.6.3 Work Schedule

2.6.4 Deliverables

2.6.5 Service Interruptions

2.6.6 Quality Management System (QMS)

2.6.6.1 Quality Management (QM) Plan

2.6.6.2 Quality Inspection and Surveillance

2.6.6.3 Quality Inspection and Surveillance Report

2.6.7 Property Management Plan

2.6.8 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.1.5 On Site Supervisor

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Annual Training for Contractor and Government Personnel

2.7.2.3 Employee Appearance

2.7.2.4 Employee Conduct

2.7.2.5 Identification as Contractor Employee

2.7.2.6 Removal of Employees

2.7.2.7 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility Related

Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Contingency Plan for Severe Weather

2.9.4.4 Emergency Response Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tagout)

2.9.4.8 Health Hazard Control Program and Hazard Communication Program

2.9.4.9 Fire Prevention Program

2.9.5 Heat/Cold Stress Monitoring

2.9.5.1 Lead Compliance and Abatement Plan

2.9.5.2 Radiation Safety Program

2.9.5.3 Respiratory Protection Program

2.9.5.4 Site Sanitation Plan

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Regulated Waste Disposal

2.10.2.2 Spill Prevention, Containment, and Clean-up

2.10.2.3 Hazardous Material Management

2.10.2.4 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.5 Noise Control

2.10.2.6 Salvage

2.10.2.7 Asbestos Containing Material (ACM)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Recurring Work Preparation of Proposals

2.14.2 Notification to the Government for Work Above the Recurring Work Limitations

2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

0200000 - Management and Administration

2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS.

Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work. Waste shall be collected as scheduled during periods of inclement weather unless specific approval to delay collections is requested by the Contractor and received from the KO. Such approval will normally be granted by the KO/COR only in cases of particularly severe weather, such a heavy snow, tropical storm, or hurricane, etc.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, Christmas Day, and Juneteenth. When a scheduled collection falls on a holiday, all scheduled collections shall be made on the following work day. All rescheduled holiday collections shall be accomplished in addition to all normal collections for that day at no additional cost to the Government.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F.

Excludes work to be performed during specified hours. There will be no additional compensation for work performed outside regular working hours.

2.2.2 Wage

Determinations

Wage Determinations are included in J-0200000-02.

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative and coordination meetings. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

2.3.2 Training for

Maintenance and Operation of New and Replacement

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

Systems and Equipment

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre- Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract Partnering

Administration

Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process. Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager Site Safety and Health Officer

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F. The Contractor shall provide all supporting information or data required to support such permit applications. The Contractor shall be responsible for all other permits or licenses required to support hazardous waste handling processes (such as but not limited to: state certification for transporter of hazardous waste and vehicle permits for same, if necessary). The Contractor shall ensure that supporting documentation for the currency of contractor employee training, permits, and/or licenses shall be maintained at contractor employee workspaces in the event of regulator inspections.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

.Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property.

The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions. Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version (currently 2010). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.

2.3.9 Forms Refer to J-0200000-04 for forms referenced in this Annex.

2.4 Government-

Furnished Items Government-Furnished Items will be provided in "AS-IS" condition and their use is at the option of the Contractor. The total or partial breakdown or failure of Government-Furnished Items shall not relieve the Contractor of the responsibility to perform the requirements of this contract.

The Contractor shall provide periodic servicing, maintenance, and repair of the Government-Furnished Items accepted for use at no additional cost to the Government. Servicing, maintenance, and repair shall be provided in accordance with the manufacturer’s recommendations. The Contractor shall generate work orders in NAVFAC Maximo per Spec Item 2.6.8 for all servicing, maintenance, and repair activities performed on Government-Furnished Items.

At the completion of the contract, all Government-Furnished Items shall be returned to the Government in the same condition as received, except for reasonable wear and tear. Government-Furnished Items, which becomes worn out due to normal wear and tear, shall be returned to the Government and its replacement shall be the responsibility of the Contractor at no additional cost to the Government. The Contractor shall be responsible for the cost of any repairs or replacement caused by Contractor negligence or abuse.

The Government may inspect Government-Furnished Items at any time and without notice.

2.4.1 Government-

Furnished Property

(GFP)

Per FAR 45.101, “Property in the possession of, or directly acquired by, the Government and subsequently furnished to the contractor for performance of a contract. Government furnished property includes, but is not limited to, spares and property furnished for repairs, maintenance, overhaul, or modification.”

Government owned equipment being taken off installation by a contractor is GFP.

Example: Items being fixed + spare parts + any materials given to industry are all considered GFP.

Real property, government facilities, inventory/supplies consumed in performance of requirement, vehicles and equipment used only on federal installations - could be considered incidental to performance, or consumables – not GFP.

The Government will furnish or make available to the Contractor certain Government Property for use in connection with this contract. The use of GFP for any other purposes is prohibited. GFP is provided and shall be managed by the Contractor in accordance with Section H; paragraph H.XX Government- Furnished Property.

A list of Government Furnished Property that will be made available to the Contractor is provided in J-0200000-05

2.4.2 Government-

Furnished Facilities

The Contractor shall be responsible and accountable for the facilities accepted for use and shall take adequate precautions to prevent fire hazards, odors, and vermin.

Janitorial and refuse collection services for the facilities shall be provided by the Contractor. The Contractor shall obtain written approval from the KO prior to making any modifications or alterations to the facilities.

1. A list of the facilities that will be made available to the Contractor is provided in J-0200000-05.

2.4.3 Government-

Furnished Vehicles and Equipment

The government will not furnish any equipment for the Contractor’s use. The Contractor shall provide all required equipment. The government reserves the right to use its own equipment to verify the accuracy of contractor weighing or measuring equipment. Refer to J-0200000-05 for a listing of all GFE.

2.4.4 Government-

Furnished Utilities

The Government will make available water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

The Contractor is responsible for the cost of all utilities at all Government-provided facilities and any additional Contractor-owned facilities, at prevailing Naval Station rates. The Contractor will be billed directly for all utilities provided to all Contractor occupied facilities. Utility rates billed to the Contractor will be at the following rates:

2. Electrical - the current rate for electrical services is $111.82 MWH

3. Water - the current rate for water is $13.23 per KGAL

4. Wastewater (Sewage) - the current rate for sewage services is $14.06 per

KGAL, based on 100% of the water consumption Variations in Rates: Utility rates are subject to change. Changes in one or more utility rates shall not be basis for adjustment to the contract price or a claim unless the deviation from the quoted price for a utility rate exceeds 15%. When a utility rate varies by more than 15%, the contract price will be adjusted to reflect the amount the actual charge exceeds the rate quoted; however, the Government will only be liable for the amount of cost exceeding 15% of the rate quoted. For example, if a quoted rate increases by 16%, the Government will only be liable for 1% of the rate increase. Vice versa if the quoted rate decreases by 16%.

Historically, electrical and water utility consumption at the Facilities provided of Contractor use has averaged approximately 351 MWH of electricity and 316 KGAL annually. However, historical data associated with contracts prior to this solicitation may present data that may not be representative of the requirements specified in this contract.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government.

Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance.

The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

The Contractor shall submit a detailed Work Management Plan in electronic format to the KO for approval per Section F. This plan shall include the following elements at a minimum: Work processes from requirement delivery from the Government to close out by the Contractor.

2.6.1 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.

2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.

All wastes shall have a correct DD1348 form with proper DODACC/UIC numbers to ensure disposal by DRMO contractor from the 90 storage sites.

The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Section F. At a minimum, work schedules shall include:

Description of service(s) to be accomplished Location Date service(s) are scheduled to be accomplished

2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business. The Contractor shall provide a plan of Vehicle Routes and Collection Schedules that minimize the impact and effects of the interference of Government business. This plan and schedule shall be submitted to the Government for approval as specified in Section F deliverables. In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall make all arrangements through the appropriate office necessary to obtain access to buildings, facilities and other work areas, and when necessary, arrange for them to be opened and closed by the controlling authority. The Government may issue keys to the Contractor. The Contractor shall use due diligence and be responsible for compromised security systems to include replacement costs that result from its action or inaction. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:

The date and time the work was initially coordinated.

The name and phone number of the Government person with whom the work was initially coordinated.

The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in Sections

C, F, H, I, J, and within the Directives, Instructions, and References. The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format.

Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website.

Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.5 Service

Interruptions

If any scheduled Hazardous Waste Removal Services or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers verbally and in writing or email as soon as possible before, but not less than 1 hour before known interruption of scheduled services. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.6 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

Accurate documentation of work processes, procedures, and output measures.

A systematic procedure for assessing compliance with performance objectives and standards.

Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.6.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.6.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.6.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.7 Property

Management Plan

The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Items, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, key control, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.

2.6.8 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

Additionally, the PM shall possess at a minimum a Bachelor’s Degree in Science (B.S.) with a minimum of 5 years’ experience in the environmental field.

-Informational Note: The PM may serve in the capacity of other listed Key Personnel. The pre-requisites of the Key Personnel position shall be relevant and current.