N4008023R0020 Amendment 0010.pdf

PDF 219 KB Posted

Attached to
N4008023R0020 LARGE PROJECTS MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) Federal contract opportunity
Solicitation number
N4008023R0020
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document is an amendment to a solicitation for an indefinite delivery, indefinite quantity multiple award construction contract for large general projects primarily in the Washington D.C. area of responsibility. The amendment revises the price schedule form and provides a continuation page for the price schedule. It also adds a note to a drawing specifying that approximately 85,000 cubic yards of surcharge material is needed early from an active stockpile at Joint Base Andrews for pre-consolidation due to site constraints, with 45,538 cubic yards of excess soil to be hauled back to the stockpile and 82,000 cubic yards of unsuitable spoils to be hauled offsite. The solicitation is issued by the Naval Facilities Engineering Command for the Department of the Navy to obtain pricing and contract vehicles for large construction projects.

View the file

Other files for this federal contract opportunity

Other files attached to N4008023R0020 LARGE PROJECTS MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC), newest first.
File Type Posted
23R0020 0012.pdf PDF
23R0020 Amendment 0011.pdf PDF
Propane Tank Information as shown on V-101.pdf PDF
V-101_Amend 6.pdf PDF
Specifications Table of Content_Amend 6.pdf PDF
GI-111_Amend 6.pdf PDF
E-102_Amend 6.pdf PDF
E-203_Amend 6.pdf PDF
E-504_Amend 6.pdf PDF
CG-403_Amend 6 (2).pdf PDF
CD-101_Amend 6 (2).pdf PDF
CS-502_Amend 6 (2).pdf PDF
CT-501_Amend 6 (2).pdf PDF
CT-102_Amend 6 (2).pdf PDF
CG-112_Amend 5.pdf PDF
CG-103A_Amend 5.pdf PDF
CU-103_Amend 5.pdf PDF
Bird Protection Netting Spec Amend 5.pdf PDF
Grade Crossing Active Control Device Specification and Details Amend 5.pdf PDF
L-104_Amend 5.pdf PDF
Pre-proposal and Site Visit Attendee Presentation.pdf PDF
Pre-proposal and Site Visit Attendee Log.pdf PDF
MDE 18-SF-0054 JADOC BORROW PITS SIGNED DWGS_1 of 3 AMEND 4.pdf PDF
CG-503_AMEND 4.pdf PDF
CG-403_AMEND 4.pdf PDF
CD-101_AMEND 4.pdf PDF
04___Soil Lab Test Results AMEND 4.pdf PDF
Attachment G - SBSP.pdf PDF
N4008023R0020 Amendment 0004.pdf PDF
MDE 18-SF-0054 JADOC BORROW PITS SIGNED DWGS_2 of 3 AMEND 4.pdf PDF
SSK-PreBid-Detonation Bunker Sand Layer Clarification AMEND 4 (1).pdf PDF
GI-114_AMEND 4.pdf PDF
E-103_AMEND 4.pdf PDF
CG-202_REV_AMEND 4.pdf PDF
CG-201_AMEND 4.pdf PDF
03___Boring Logs (1) AMEND 4.pdf PDF
01___Boring Location Diagram AMEND 4.pdf PDF
Attachment F - SBPCD.pdf PDF
02___Cross Sections AA and BB AMEND 4.pdf PDF
CS-503_REV.pdf PDF
GI-501_REV.pdf PDF
N4008023R0020 Amendment 0003.pdf PDF
P3002_31 11 00_AMENDMENT 001.pdf PDF
P-3002 IFC PLANS_REV_signed_Part 3 of 7.pdf PDF
P-3002 IFC PLANS_REV_signed_Part 6 of 7.pdf PDF
P-3002 IFC PLANS_REV_signed_Part 5 of 7.pdf PDF
N4008023R0020 Amendment 0001.pdf PDF
P-3002 IFC PLANS_REV_signed_Part 7 of 7.pdf PDF
P-3002 IFC PLANS_REV_signed_Part 4 of 7.pdf PDF
Attachment G - SBSP.docx DOCX document
Show all 50

N4008023R0020 LARGE PROJECTS MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N40080-23-R-0020 - INDEFINITE DELIVERY, INDEFINITE QUANTITY, MULTIPLE AWARD CONSTRUCTION CONTRACT FOR LARGE GENERAL

PROJECTS PRIMARILY IN THE WASHINGTON, D.C. AREA OF RESPONSIBILITY.

PLEASE SEE SF30 BLOCK 14 CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-May-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008023R0020

X 9B. DATED (SEE ITEM 11)

02-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-May-2023

CODE

NAVAL FACILITIES ENGINEERING SYS COMMAND

1314 HARWOOD STREET SE

WASHINGTON DC 20374

N40080 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008023R0020

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0010

The purpose of this amendment is to:

1. Revise Attachment H - Price Schedule Form

2. Provide P-3002 HCP Continuation- Page

1. Revise ATTACHMENT H – Price Schedule :

Provides revised “Attachment H P-3002 Price Schedule Form 8 May 23.

2. Provide P-3002 HCP Continuation- Page:

P-3002 HCP Continuation Page 8 May 23.

DWG Sheet GC-001 – Add Note 27 - For pre-consolidation effort, it is anticipated that 85,000 CY of surcharge material is needed and must come from the active stockpile located on Joint Base Andrews (shown on sheet GI-104). The Contractor is required to comply with the requirements in MDE No. 18-SF- 0054, when removing material from the stockpile area. The surcharge material is needed early for pre-consolidation due to the site constraints. This is due to the drainage way bisecting the site which needs to be kept open during pre-consolidation of the soil where the culvert will be installed. Additionally, conducting all of the pre-consolidation in two phases early in the project allows for south perimeter road to remain open throughout the construction. The value indicated by CLIN 0001B of 45,538 CY is the approximate amount of excess soil to be hauled to the active stockpile. The value indicated by CLIN 0001C of 82,000 CY is the anticipated amount of spoils required to be hauled off-site.

See Table 1 Below

Table 1

Total Cut (Sheet GC‐001) Note: Includes 85,000 CY pre‐consolidation Material from Stock Pile

271,995

Total Fill (Sheet GC‐001) 144,457

Excess Material to be Removed from Site Note: Includes 82,000 CY Unsuitable to offsite + 45,538 CY Suitable for Stockpile

127,538

(End of Summary of Changes)