N4008022R3927 Solicitation.pdf
PDF 557 KB Posted
- Attached to
- SEAWALL REPAIRS FOR FARRAGUT AND SANTEE BASIN, UNITED STATES NAVAL ACADEMY, ANNAPOLIS, MD
- Solicitation number
- N4008022R3927
About this file
This is a solicitation for construction services to repair portions of the seawall at Farragut Field and Santee Basin at the United States Naval Academy in Annapolis, Maryland. The work includes constructing a new sheet pile wall outboard of the existing bulkheads along Farragut Field and utilizing the existing tieback system at Santee Basin, with a new tieback system to be constructed inland of the existing bulkhead at Farragut Field. Offerors must submit proposals by June 10, 2022 following requirements for technical factors, pricing, representations and certifications, and past performance information. The agency plans to award a firm-fixed price contract for the base requirements and any selected options.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEAWALL REPAIRS FOR FARRAGUT, ROBERT CROWN AND SANTEE BASIN, UNITED STATED NAVAL ACADEMY, ANNAPOLIS, MD
THE NORTH AMERICA INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE IS 237990 WITH A SIZE STANDARD OF $39.5M.
CONTRACT TYPE: Firm Fixed Price
SHAMARIAN PLUMMER (410) 293-1074
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
03-May-2022
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________10 Jun 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVAL FACILITIES ENGINEERING SYS COMMAND
1314 HARWOOD STREET SE
WASHINGTON DC 20374
N40080
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: (202) 685-3192 TEL: FAX:
N4008022R3927 54
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008022R3927
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each
BASE BID
FFP
Phase 1A of the Farragut Field bulkhead FOB: Destination
NET AMT
0002 1 Each
OPTION OPTION 1
FFP
Phase 1B of the Farragut Field bulkhead
0003 1 Each
OPTION OPTION 2
FFP
Phase 1C of the Farragut Field bulkhead
0004 1 Each
OPTION OPTION 3
FFP
BULKHEAD PHASE 2
0005 1 Each
OPTION OPTION 4
FFP
SEAWALL EXTENSION, PHASE 3
0006 400 Gallon
OPTION OPTION 5
FFP
REMOVAL/DISPOSAL OILY WATER
0007 3,500 Cubic Feet
OPTION OPTION 6
FFP
REMOVAL CONTAMINATED SOILS
0008 3,500 Cubic Feet
OPTION OPTION 7
FFP
PROVISION & COMPACTION OF FILL
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
0004 N/A N/A N/A N/A
0005 N/A N/A N/A N/A
0006 N/A N/A N/A N/A
0007 N/A N/A N/A N/A
0008 N/A N/A N/A N/A
Section 00 21 13 - Instructions to Bidders
CLAUSES INCORPORATED BY REFERENCE
52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.215-1 Instructions to Offerors--Competitive Acquisition DEC 2021 52.217-5 Evaluation Of Options JUL 1990 52.222-5 Construction Wage Rate Requirements--Secondary Site of the
Work
MAY 2014
52.236-28 Preparation of Proposals--Construction OCT 1997
CLAUSES INCORPORATED BY FULL TEXT
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm-fixed contract resulting from this solicitation.
(End of provision)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
28% 6.9%
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Annapolis, MD.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from NAVFAC Washington, 1314 Harwood St, Building 212, Washington DC 20374.
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) One (1) Government scheduled site visit will be conducted for the project. Refer to the Instruction to Offerors for site visit information.
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Department of Defense Federal Acquisition Regulation Supplement (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section 00 21 16 - Instructions to Proposers
INSTRUCTIONS TO OFFERORS
1. TITLE: SEAWALL REPAIRS FOR FARRAGUT AND SANTEE BASIN, UNITED STATES NAVAL
ACADEMY, ANNAPOLIS, MD
2. PROJECT DESCRIPTION: The work to be performed is to repair portions of the seawall at Farragut Field and Santee Basin at the Naval Academy in Annapolis, MD. The intent of the Seawall Repairs for Farragut Field and Part of Santee Basin project is to provide a 75-year service life by repairing the sheet pile bulkheads along Farragut Field and the east side of Santee Basin. The basis of design calls for the construction of a new sheet pile wall outboard of the existing. Santee Basin will utilize the existing tieback system while Farragut Field will utilize a new tieback system constructed inland of the existing for lateral stability.
3. POINT OF CONTACT: The primary point of contact for this procurement is ShaMarian Plummer at shamarian.n.plummer.civ@us.navy.mil. The secondary point of contact is Lindsay Brown at lindsay.m.brown14.civ@us.navy.mil.
4. DISCLOSURE OF MAGNITUDE: In accordance with DFAR 236.204 (ii), the estimated magnitude of construction is $25,000,000 and $100,000,000.
5. CONTRACT TYPE: Firm Fixed Price
6. ACQUISITION STRATEGY: Unrestricted Basis with Full and Open Competition Source Selection.
7. NORTH AMERICA INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE: Classification System 237990 with a size standard of $39.5M
8. SOURCE SELECTION PROCESS: Best Value Source Selection (BVSS) Trade-Off.
9. CONTRACT COMPLETION DATE: Work under this contract shall commence 15 days after award and shall be completed within 730 days after contract award (this includes 15 days for bond approval).
10. PROPOSAL ACCEPTANCE PERIOD: The Offeror’s proposal acceptance period is 90 days from the receipt of proposals.
11. PRE-PROPOSAL CONFERENCE/SITE VISIT:
Date: Wednesday, May 18, 2022 Time: 10:00 AM EST Location: There will only be one scheduled site visit. Please meet in the Parking Lot at Halligan Hall (building that is outside of the USNA main gates): Address: 181 Wainwright Drive, Annapolis, MD 21402
All personnel interested in attending the Site Visit must provide the following information to shamarian.n.plummer.civ@us.navy.mil and lindsay.m.brown14.civ@us.navy.mil no later than 13 May 2022 by
12:00 PM.
(1) First Name
(2) Last Name
(3) Email
(4) Phone Number
(5) Company Name
12. REQUEST FOR INFORMATION (RFI): Offerors are required to review the entire Solicitation package before submitting questions. All inquiries must be submitted May 27, 2022 by 2:00 PM EST. All inquiries must be submitted in writing, utilizing the Request For Information Form, and emailed ShaMarian Plummer shamarian.n.plummer.civ@us.navy.mil and Lindsay Brown lindsay.m.brown14.civ@us.navy.mil. No tables please.
13. DELIVERY OF PROPOSAL: Proposals shall be received electronically no later than 2:00 PM EST on 10 JUNE 2022. Proposals shall be submitted utilizing the Solicitation Module in the Procurement Integrated Enterprise Environment (PIEE). Department of Defense (DoD) training for industry partners is available at https://dodprocurementtoolbox.com/site_pages/solicitation-module. Additional Web Based Training is available at https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml. Please send an email to shamarian.n.plummer.civ@us.navy.mil and lindsay.m.brown14.civ@us.navy.mil confirming submission of your proposal.
Please allow SUFFICIENT TIME for your proposal to be received within the Government’s electronic system prior to the proposed cutoff date/time. All proposals must be received prior to the due date and time.
Any proposals submitted after the time set for receipt will be documented with the date and hour of receipt and may be held unopened until after award. The file shall be documented in accordance with FAR 15.208.
Facsimile copies and hard copies will NOT be accepted. NO HAND DELIVERY IS
ALLOWED.
14. PROPOSAL ORGANIZATION AND FORMAT: The proposal submitted in response to this solicitation shall be clear, concise, and shall contain sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposals should not simply rephrase or restate the Government’s requirements, but rather should demonstrate convincing rationale to address how the offeror intends to meet these requirements. The offer shall be compliant with the requirements as stated in the RFP.
Nonconformance with the solicitation requirements, specified organization and content may result in elimination or misevaluation of the proposal. All claimed technical capabilities to meet the requirements shall be realistic and are subject to verification by the Government. Offerors should assume that the Government has no prior knowledge of the offeror’s business and that the Government will base its evaluation on the information contained in the offeror’s proposals.
Cross-Referencing: To the greatest extent possible, each volume shall be written on a stand-alone basis so that its contents may be evaluated with a minimum of cross referencing to other volumes of the proposal.
Information required for proposal evaluation which is not found in its designated volume will be assumed to have been omitted from the proposal. Cross-referencing within a proposal volume is permitted where its use would conserve space without impairing clarity.
Volume I: Technical Proposal – Factors 1-5: Volume I shall contain the Offerors entire technical proposal in a single pdf., sectioned appropriately by major evaluation factor (excluding Factor 6 - Small Business Utilization) with the following characteristics:
(1) Text pages 8 ½ x 11 format, minimum 10 point font.
(2) Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address.
(3) Technical Factors 1-5
Volume II: Technical Proposal – Factor 6: Volume II shall contain the Offerors entire technical proposal in a single pdf., for Factor 6, Small Business Utilization only, with the following characteristics:
(1) Text pages 8 ½ x 11 format, minimum 10 point font.
(2) Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address.
(3) Technical Factor 6
Volume III: Price Proposal: Volume III shall contain the Offerors price proposal in a single pdf. With the following information In the pricing volume, the Offeror shall provide the following information:
1. Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address.
2. Text pages 8 ½ x 11 format, minimum 10 point font.
3. Completed SF 1442 signed with all amendments acknowledged.
4. Completed Price Schedule.
5. Online Representation and Certifications and proof of registration in System for Award Management
(SAM)
6. Confirmation of filing of VETS-4212 and/or VETS report for the cycle.
7. Bid Guarantee in accordance with FAR Clause 52.228-1 Bid Guarantee.
8. Responsibility Determination Information (see below).
The offeror is required to submit a complete Price Schedule that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00010 – Solicitation Contract Form in SF 1442. All required proposal documents shall be submitted in accordance with FAR 15.208.
(i) Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide its DUNS Number, CAGE code, and Federal Tax ID number with its proposal.
(ii) Bid bond (SF-24). Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.
(iii) SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by the Solicitation is not provided in SAM, include the representation or certification in your price proposal.
(iv) FAPIIS Certification. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) Certification as required by FAR 52.209-7, Information Regarding Responsibility Matters.
(v) VETS-4212 registration. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm, if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report.
Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.
ADDITIONAL INFORMATION TO BE SUBMITTED WITH PRICE PROPOSAL
PACKAGE:
1. RESPONSIBILITY DETERMINATION INFORMATION - In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards.
The offeror shall provide the following information in the price proposal package:
- One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
- The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.
- Description of offeror’s facilities and equipment.
- Other offeror’s work presently under contract.
Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.
15. BASIS FOR AWARD
a. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.
b. As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with offeror (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
c. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
d. all technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price.
e. Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified weakness(s) and the associated risk to successful contract performance resulting from the weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
16. EVALUATION FACTORS FOR AWARD
1. The solicitation requires the evaluation of price and the following non-price factors:
Factor 1 - Experience Factor 2 - Past Performance
Factor 3 - Safety Factor 4 - Key Personnel Factor 5 - Management and Project Delivery Approach Factor 6 - Small Business Utilization
The distinction between experience and past performance is that experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
2. The relative order of importance of the non-price evaluation factors is the technical factors, Factors, 1, 3, 4, 5, and 6 are of equal importance to each other and, when combined are equal in importance to the past performance evaluation/performance confidence assessment factor, Factor 2. When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-price evaluation factors) are approximately equal to price.
The importance of price will increase if the Offerors’ non-price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
Price:
(1) Solicitation Submittal Requirements: Submit the following:
• SF 1442, signed and all amendments acknowledged
• Completed Price Schedule
(2) Basis of Evaluation: The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items. The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in the solicitation. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
Non-price Factors:
FAR Part 9.6 defines Contractor team arrangements. Contractor team arrangement, as used in this subpart, means an arrangement in which -- (1) Two or more companies form a partnership or joint venture to act as a potential prime Contractor; or (2) A potential prime Contractor agrees with one or more other companies to have them act as its subcontractors under a specified Government contract or acquisition program.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent /LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent/LLC/LTD member companies will have meaningful involvement in the performance of the contract in order for the experience information of the affiliate/subsidiary/parent/LLC/LTD member companies to be considered. The proposal shall state specific commitments of technical resources (e.g., personnel, management, equipment that the affiliate/subsidiary/parent/LLC/LTD member companies shall commit to the performance of this contract). In particular, the proposal shall clearly state the specific commitments of resources of the affiliate/subsidiary/parent/LLC/LTD member companies in terms of the work it will either self-perform or manage on behalf of the Offeror in the performance of the contract.
The Offeror shall submit a signed copy of partnership agreement, teaming agreement, or letter of commitment for each member of the Offeror’s team (e.g., partner, team member, subcontractor, parent company, subsidiary, or other affiliated company, etc.) whose projects are submitted to demonstrate Construction or Design Experience. The Government will not consider any project submitted for Factor 1 if it was performed by a firm other than the Offeror and there is no supporting partnership agreement, teaming agreement, or letter of commitment. Additional joint venture agreements are not permitted on MAC Task Orders. Note: See specific restrictions on the use of subcontractor experience under Factor 1.
Factor 1 – Experience:
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information:
Construction Experience:
Submit a minimum of two (2) and a maximum of five (5) construction projects for the Offeror that best demonstrates your experience on projects that are similar in size, scope, and complexity to this project. Each of the projects does not need to meet all three requirements (size, scope, and complexity). However, the combination of projects must demonstrate all requirements of size, scope, and complexity (i.e. at least one of the projects must meet the size requirement, at least one of the projects must meet the scope requirement, and the aggregate of projects must meet the complexity requirements). For purposes of this evaluation, a relevancy is further defined as:
• Relevancy: Waterfront construction either new or renovated/reconstructed.
• Size: 500 linear foot or longer water frontage and/or final construction cost of $20,000,000 or greater.
• Scope: Waterfront construction either new or renovated/reconstructed that consist of the driving of sheet pile and/or driving of pile
• Complexity: Work performed on facilities that required installation of steel sheet pile with tie rod installation.
Projects submitted for the Offeror shall be completed within the past ten (10) years of the date of issuance of this
RFP.
In addition to the above size, scope and complexity definitions, a construction project must be performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.
The attached Construction Experience Form (Attachment 1) is MANDATORY and SHALL be used to submit project information. Except as expressly allowed by the Contracting Officer, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. Offerors who fail to submit experience for all Joint Venture members may be rated lower.
Offerors are still limited to a total of five (5) projects combined.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.
The Offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offer must provide a letter of commitment and an explanation of the meaningful involvement the subcontractor will have in performance of this contract. More weight may be given to the Offeror’s projects than to those submitted for subcontractors. Substitution of identified subcontractors will not be permitted without Contracting Officer approval.
(b) Basis of Evaluation:
The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s aggregate experience will be used as a means of evaluating the relevancy of the submitted experience and the capability of the Offeror to successfully meet the requirements of the RFP. Individual projects that include all relevancy characteristics (size, scope, and complexity) may be considered more favorably. The Government will only review five projects. Any projects submitted in excess of the five (5) for Construction Experience will not be considered.
Proposals may be strengthen if submitted projects demonstrate the following:
1. Projects that demonstrate experience with additional site reconstruction/development of surface features, or restoration/reconstruction of navigational features, or restoration/reconstruction of historic features.
2. Projects that demonstrate experience and successful execution of work in congested site, or requiring phasing of the work.
3. Offerors who submit relevant projects that demonstrate experience self-performing relevant features of work may receive a higher rating than those who do not demonstrate self-performance. Overhead, project management, or site management are not considered self-performance of work. Projects where the Offerors performance was limited in that manner may be considered less favorably than those that do not demonstrate that limitation.
Factor 2 – Past Performance:
(a) Solicitation Submittal Requirements:
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1, Experience. If a completed CPARS evaluation is not available for a project that was submitted under Factor 1, the Offeror shall submit Past Performance Questionnaires (PPQ) (Attachment 6) for that project. An Offeror shall not submit a PPQ when a completed CPARS is available.
Evidence of customer satisfaction shall be from the owner and/or their representative responsible for the construction contract administration of construction projects. For construction contractors, it shall not be from the designer on a design-build project.
Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other NAVFAC RFPs.
However, previously completed PPQs in full text submitted for other RFPs may be submitted. Previously completed PPQs do not need to be identical to Solicitation Attachment 6, but they must include all information requested in
Solicitation Attachment 6 in order to be accepted. All PPQs shall be complete, contain client’s signature, and include all information requested in Solicitation Attachment 6. This does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s).The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, ShaMarian Plummer, at shamarian.n.plummer.civ@us.navy.mil.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1, Experience. Offerors may also address any adverse past performance issues. Explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
Performance award or additional information submitted will not be considered.
(b) Basis of Evaluation:
This evaluation will consider how well the Offeror’s team performed on relevant projects submitted under Factor 1 – Experience and may also consider past performance on other projects currently documented in known sources.
The Government will consider the recency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s team’s past performance will be used as a means of evaluating the Offeror’s team’s probability to successfully meet the requirements of the RFP.
Recency and relevancy is defined as:
1. Recency: Project completed within the past ten (10) years of the date of issuance of this RFP.
2. Relevancy: General Construction (new, repair, renovation, and/or alteration)
Offerors lacking relevant past performance history will receive a NEUTRAL Confidence rating.
Past performance ratings of “Substantial Confidence” or “Satisfactory Confidence” hold more value than a “Neutral Confidence” rating and will be considered more favorably in the evaluation of past performance.
Factor 3 – Safety:
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information on the Safety Data Sheet (Attachment 2):
The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative as described further below. For a partnership, joint venture, the Offeror shall submit separate DART, TCR for the specified five (5) CY for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.
NOTE: DART and TCR shall not be submitted for subcontractors.
(1) DART Rate: Submit five (5) previous complete calendar years’ [CY2017, CY2018, CY2019, CY2020, CY2021] worth of data (not an overall average). If the Offeror has no DART rate or a DART rate of 0.00, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
a. Dart cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.
b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.
(2) TCR Rate: Submit five (5) previous complete calendar years’ [CY2017, CY2018, CY2019, CY2020, CY2021] worth of data (not an overall average). If the Offeror has no TCR rate or a TCR rate of 0.00, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required, that includes any corrective actions taken for improvement.
a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.
b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.
(3) Technical Approach for Safety: Submit a narrative that addresses the following:
a. Describe the Offeror’s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describe the evaluation process used to select potential subcontractors.
c. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout the performance of the contract (to include their own in-house workforce).
d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page.
(4) The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
(b) Basis of Evaluation:
The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
(1) DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low
Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the DART rate to the level of risk:
Risk DART Rate Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0
(2) TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low
Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to
High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the TCR rate to the level of risk:
Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49 Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0
(3) The Technical Approach to Safety Narrative. To determine the degree to which the Offeror:
a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.
c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.
d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page. Information on pages beyond this will not be considered.
The Government reserves the right to review other available sources (public/Government internal) of information.
These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
Factor 4 – Key Personnel
(a) Solicitation Submittal Requirement:
Provide detailed resume and qualification information as defined in the contract documents for the Quality Control (QC) Manager, Underwater QC firm, and Underwater QC Team leader, Structural QC Specialist, and Superintendent. Information shall not exceed two (2) pages, 8 ½” x 11”, per individual. Do not include photographs.
(b) Basis of Evaluation:
Key Personnel will be evaluated based on the information provided when compared to contract requirements.
Experience exceeding 125% of contract requirements will be considered a strength. Substitutions of proposed team members after proposal acceptance will not be allowed without Contracting Officer approval. Key Personnel substitutions must have equal to or better qualifications, experience, and performance. Best value will be determined when this score is compared to other Offerors score for this rating factor.
Factor 5 – Management and Project Delivery Approach
(a) Solicitation Submittal Requirement:
Solicitation Submittal Requirements: Provide a narrative which shall not exceed four (4) 8 ½” x 11” pages, detailing the contractor’s understanding of the project, and their proposed plan for delivery of the project with specific focus on its timely completion. Specific items to be addressed include:
(1) General outline of major/critical path activities, including logistic plans to execute the work within the available land side footprint. If use of barge mounted equipment or logistic support is proposed it must be identified here.
(2) Procedures to ensure accountability for quality of work and promote timely completion of rework items to allow for follow-on work that does not conceal deficient work, including oversight by QC and field staff in coordination with Government QA.
(3) Early actions over the life of the project that would support successful safe progress along with Red Zone procedures and any additional resources to be provided for this effort.
(4) Process for transition from the Definable Feature of Work based 3-phase QC procedures to the Completion Inspection three step process. Address completion of Commissioning, Critical Systems Acceptance with Government staff throughout project work and prior to finishing the Pre-Final Inspection cycle to allow for successful Final Acceptance Inspection.
(5) Plan for addressing historical and historic preservation elements of project to ensure successful execution and compliance with Historic Preservation Requirements and re-establishment of Triton light for navigational purposes at the completion of work including temporary navigational markings/light while Triton light is out of service.
(b) Basis of Evaluation:
The evaluation will be based on demonstrated understanding of the contract requirements, the completeness of the total content, the likelihood for successful project execution, and degree of risk minimization shown in the Offeror’s proposed approach. Factor 5 will be evaluated to gauge the likelihood for successful project execution.
Offerors that provide a narrative that addresses A – E, demonstrating or referencing parts of the Statement of Work and explaining how the Offeror’s QC team would coordinate with the On-Site Gov’t Construction Management Team to successfully deliver the project, including mitigating schedule and performance risks, may be given a strength.
Factor 6 – Small Business Utilization and Participation
It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Historically Underutilized Business Zone Small Business (HUBZone SB), Woman-Owned Small Business (WOSB), Small Disadvantaged Business (SDB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.
NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract.
This is the start of the file's text. The full file is on GovTribe.