This document contains amendments to a task order and basic contract for a physical security and access control multiple award construction contract. The amendments add new technical requirements for active vehicle barriers, including operational capabilities and equipment requirements documents. The contract is a 100% small business set-aside with one reserve for a women-owned small business. It uses a two-phase design-build selection for awarding between three to five indefinite-delivery indefinite-quantity contracts. The solicitation number is N3943020R2201 and covers both selection phases with the intent to award the multiple award construction contracts for physical security and access control systems through the Naval Facilities Engineering Command.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
4 JAN 2020
NAVFAC Anti-Terrorism/Force Protection (AT/FP) Ashore Program Physical Security/Access Control Systems – 2 (PS/AC-2) Contract
Task Order (TO) #X001 Replace Active Vehicle Barriers (AVBs), Naval Support Activity (NSA) Orlando, FL, Project
Amendments to the Task Order (TO) #X001 PWS are provided as follows:
1. Include additional Technical Information for Active Vehicle Barriers (AVBs). Make the following changes to the Task Order PWS:
a. Part 2, Section 01 11 00, 1.3.c.2.a. Technical Information: Active Vehicle Barriers –, First Sentence. After “The NAVFAC AT/FP Ashore Program technical performance requirements and operational capabilities for Active Vehicle Barriers (AVBs) are provided in the following documents: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, List Date:
May 2019; UFC 4-022-01 Entry Control Facilities Access Control Points dated 27 July 2017; and UFC 4- 022-02 Selection and Application of Vehicle Barriers, Change 1, dated 9 August 2010” insert the following: “; and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019”.
b. Part 2, Section 01 11 00, 1.3.c.2.a. Technical Information: Active Vehicle Barriers –. Below “Document Names: UFC 4-022-02, Change 1, dated 9 August 2010 – Document Name:
ufc_4_022_02_2009_c1.pdf (UFCs are available on the Whole Building Design Guide Web site:
http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4). The Contractor shall use the latest version at the time of solicitation of this Task Order, as applicable.” insert the following: “Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019 – Document Name: AVB Operational & Equipment Capabilities 28Mar19.pdf. The Contractor shall use the latest version at the time of solicitation of this Task Order, as applicable.”
c. Part 3, Chapter 1, Section 1.0, Physical Security/Access Control (PS/AC) Systems Description, Fourth Paragraph, First Sentence. After “This Task Order PWS incorporates generalized instructions from the List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, UFC 4-022-01 Entry Control Facilities Access Control Points, and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert the following: “, and Active Vehicle Barrier (AVB) Operational/ Equipment Capabilities”.
d. Part 3, Chapter 1, Section 1.0, Physical Security/Access Control (PS/AC) Systems Description, Fourth Paragraph, Third Sentence. After “The Site Specific Information for this Task Order PWS includes: Appendix C Site Analysis Report; and the List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, UFC 4-022-01 Entry Control Facilities Access Control Points, and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert the following: “, and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities”.
e. Part 3, Chapter 2, Section 2.0, Physical Security/Access Control (PS/AC) Systems Objectives, 1., Fifth Paragraph, First Sentence. After “The Contractor is provided the following documents in the Technical Information established as the required NAVFAC AT/FP Ashore Program technical performance requirements and operational capabilities for the NAVFAC AT/FP Ashore Program PS/AC Active Vehicle Barrier (AVB) Systems/equipment as delineated in Part 1 Proposal Forms and Documents and provided by the Government as GFI in Part 6 Attachments of the Basic Contract PWS to include: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST; UFC 4-022- 01 Entry Control Facilities Access Control Points; and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert “; and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities”.
f. Part 3, Chapter 2, Section 2.0, Physical Security/Access Control (PS/AC) Systems Objectives, 1., Fifth Paragraph, Third Sentence. After “The Site Specific Information for this Task Order PWS http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4 includes: Appendix C Site Analysis Report in the Appendixes specific to the Task Order PWS; and the List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, UFC 4- 022-01 Entry Control Facilities Access Control Points, and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert the following: “, and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities”.
g. Part 3, Chapter 2, Section 2.1, Physical Security/Access Control (PS/AC) Systems Applicable Codes, Standards, and References, Third Paragraph, First Bullet. After “Technical information to include: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST;
UFC 4-022-01 Entry Control Facilities Access Control Points; and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert the following: “; and Active Vehicle Barrier (AVB) Operational/ Equipment Capabilities”.
h. Part 3, Chapter 2, Section 2.1, Physical Security/Access Control (PS/AC) Systems Applicable Codes, Standards, and References, Fourth Paragraph, Second Bullet. After “Technical Information specific to this Task Order PWS to include: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST; UFC 4-022-01 Entry Control Facilities Access Control Points; UFC 4-022-02 Selection and Application of Vehicle Barriers;” insert the following: “Active Vehicle Barrier (AVB) Operational/Equipment Capabilities;”.
i. Part 6, Physical Security/Access Control (PS/AC) Systems List of Attachments, 1.c.2.a.
Technical Information: Active Vehicle Barriers –, First Sentence. After “The NAVFAC AT/FP Ashore Program technical performance requirements and operational capabilities for Active Vehicle Barriers (AVBs) are provided in the following documents: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, List Date: May 2019; UFC 4-022-01 Entry Control Facilities Access Control Points dated 27 July 2017; and UFC 4-022-02 Selection and Application of Vehicle Barriers, Change 1, dated 9 August 2010” insert the following: “; and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019”.
j. Part 6, Physical Security/Access Control (PS/AC) Systems List of Attachments, 1.c.2.a.
Technical Information: Active Vehicle Barriers –. Below “Document Names: UFC 4-022-02, Change 1, dated 9 August 2010 – Document Name: ufc_4_022_02_2009_c1.pdf (UFCs are available on the Whole Building Design Guide Web site: http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4). The Contractor shall use the latest version at the time of solicitation of this Task Order, as applicable.” insert the following: “Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019 – Document Name: AVB Operational & Equipment Capabilities 28Mar19.pdf. The Contractor shall use the latest version at the time of solicitation of this Task Order, as applicable.”.
k. Include new Active Vehicle Barrier (AVB) Operational/Equipment Capabilities (Document Name:
AVB Operational & Equipment Capabilities 28Mar19.pdf) as an attachment in Part 6 Attachments.
http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4
4 JAN 2020
NAVFAC Anti-Terrorism/Force Protection (AT/FP) Ashore Program Physical Security/Access Control Systems – 2 (PS/AC-2) Basic Contract
Amendments to the Basic Contract PWS are provided as follows:
1. Include additional Technical Information for Active Vehicle Barriers (AVBs). Make the following changes to the Basic Contract PWS:
a. Part 1, Section 00 72 00, 5.1.3.1., Technical Information: Active Vehicle Barriers (AVBs) –, First Sentence. After “The NAVFAC AT/FP Ashore Program technical performance requirements and operational capabilities for Active Vehicle Barriers (AVBs) are provided in the following documents: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST; UFC 4-022- 01 Entry Control Facilities Access Control Points; and UFC 4-022-02 Selection and Application of Vehicle Barriers” insert the following: “; and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities”.
b. Part 6, Physical Security/Access Control (PS/AC) Systems List of Attachments, 1.c.2.a.
Technical Information: Active Vehicle Barriers (AVBs) –, First Sentence. After “The NAVFAC AT/FP Ashore Program technical performance requirements and operational capabilities for Active Vehicle Barriers (AVBs) are provided in the following documents: List of DoD Certified Anti-Ram Vehicle Barriers titled DoD ANTI-RAM VEHICLE BARRIER LIST, List Date: May 2019; UFC 4-022-01 Entry Control Facilities Access Control Points dated 27 July 2017; and UFC 4-022-02 Selection and Application of Vehicle Barriers, Change 1, dated 9 August 2010” insert the following “; and Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019”.
c. Part 6, Physical Security/Access Control (PS/AC) Systems List of Attachments, 1.c.2.a.
Technical Information: Active Vehicle Barriers (AVBs) –. Below “Document Names: 3. UFC 4-022- 02, Change 1, dated 9 August 2010 – Document Name: ufc_4_022_02_2009_c1.pdf (UFCs are available on the Whole Building Design Guide Web site: http://www.wbdg.org/ccb/browse_cat.php?o= 29&c=4). The Contractor shall use the latest version at the time of solicitation of this Basic Contract and/or individual Task Orders, as applicable.” insert the following: “4. Active Vehicle Barrier (AVB) Operational/Equipment Capabilities dated 28 March 2019 – Document Name: AVB Operational & Equipment Capabilities 28Mar19.pdf. The Contractor shall use the latest version at the time of solicitation of this Basic Contract and/or individual Task Orders, as applicable.”.
d. Include new Active Vehicle Barrier (AVB) Operational/Equipment Capabilities (Document Name:
AVB Operational & Equipment Capabilities 28Mar19.pdf) as an attachment in Part 6 Attachments.
http://www.wbdg.org/ccb/browse_cat.php?o=%2029&c=4 http://www.wbdg.org/ccb/browse_cat.php?o=%2029&c=4
28 MAR 2019
NAVFAC Anti-Terrorism/Force Protection (AT/FP) Ashore Program
Active Vehicle Barrier (AVB) Operational/Equipment Capabilities:
Must be on the USACE DoD Anti-Ram Vehicle Barrier List Emergency Fast Operate (EFO) function Electro-mechanical operation only (non-hydraulic) Human in the loop activation Standardized Sentry Interface (SI) Standardized above ground barrier solution Standardized in-ground barrier solution to include;
o No plate barriers or bollards o Flush to road surface in down position
Requirements o Maximum non-emergency cycle time of 12 seconds o Rated for continuous duty (120 cycles/hour minimum) o Safety sensors active o Meets safety requirements of UFC 4-022-02 para. 5-2.4 o Have a minimum ASTM M50 rating o High visibility per MUTCD 2B.68 para 15
Multimode operation Maintenance o Common maintenance interface