AVB Operational & Equipment Capabilities 28Mar19.pdf

PDF 13 KB Posted

Attached to
Multiple Award Construction Contract for Physical Security/ Access Control-Amendment 0006 Federal contract opportunity
Solicitation number
N3943020R2201
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document outlines requirements for an active vehicle barrier (AVB) system and related federal contract opportunity. The AVB system must meet USACE and DoD standards for anti-terrorism and force protection barriers, including emergency fast operation, electro-mechanical operation, human activation, standardized interfaces and configurations, maximum 12-second non-emergency cycle time, 120 cycles per hour minimum duty, safety sensors, ASTM M50 rating, and high visibility markings. The system must provide multi-mode operation, common maintenance interfaces, and standardized above and below-ground solutions without plate barriers or bollards.

The federal contract opportunity is a Multiple Award Construction Contract for physical security and access control projects at Naval Station Norfolk. It uses a two-phase design-build selection process to award three to five indefinite-delivery/indefinite-quantity contracts. The total set-aside is for small businesses with one reserve for a women-owned small business. The NAICS code is 237990 for other heavy and civil engineering construction up to $39.5 million. The solicitation number is N3943020R2201 and was issued by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

28 MAR 2019

NAVFAC Anti-Terrorism/Force Protection (AT/FP) Ashore Program

Active Vehicle Barrier (AVB) Operational/Equipment Capabilities:

Must be on the USACE DoD Anti-Ram Vehicle Barrier List Emergency Fast Operate (EFO) function Electro-mechanical operation only (non-hydraulic) Human in the loop activation Standardized Sentry Interface (SI) Standardized above ground barrier solution Standardized in-ground barrier solution to include;

o No plate barriers or bollards o Flush to road surface in down position

Requirements o Maximum non-emergency cycle time of 12 seconds o Rated for continuous duty (120 cycles/hour minimum) o Safety sensors active o Meets safety requirements of UFC 4-022-02 para. 5-2.4 o Have a minimum ASTM M50 rating o High visibility per MUTCD 2B.68 para 15

Multimode operation Maintenance o Common maintenance interface