BRASHEAR_AMENDMENT_0005.doc

DOC document 43 KB Posted

Attached to
Repair and Overhaul Dry Docking USNS CARL BRASHEAR
Solicitation number
N3220519R4260
Issued by

About this file

Amendment 0005

View the file

Other files

File Type Posted
BRASHERA_AMENDMENT_0007.doc DOC document
J_-_2_Category_A_REV_002.xls XLS spreadsheet
J_-_3_REVISION_002_Category_B_Items.xls XLS spreadsheet
BRASHERA_AMENDMENT_0006.docx DOCX document
J_-_2_REVISION_Category_A_Items.xls XLS spreadsheet
611_MSC_Circ_1331Guidlines_for_Embarkation.pdf PDF
J_-_3_REVISION_Category_B_Items.xls XLS spreadsheet
0528_B_Food_Waste_Transfer_Pump_Overhaul.docx DOCX document
0307_B_MOTOR_CONTROL_CENTER_M05_ALTERNATE_POWER_SOURCE_(T-ALT_370).docx DOCX document
BRASHEAR_AMENDMENT_0004.doc DOC document
8391502_A.pdf PDF
0522_A_Magazine_Drain_Piping_Replacement_Rev_A.doc DOC document
8391502_-.pdf PDF
0527_B_Grey_Water_Transfer_Pump_Overhaul.docx DOCX document
0569_B__SW_Check_Valve_Clean_and_Repair_(VR18-0036-55).docx DOCX document
0105_A_DECK_HOUSE_CLEANING_AND_PAINTING_(SPOT_BLAST)_REV_A.docx DOCX document
0227_A_MDG_Attached_Lube_Oil_Pump_Rebuilds.doc DOC document
0530_A_CARGO_AND_AC_30K_HR_COMPRESSOR_REPLACEMENT_REV_A.docx DOCX document
T6225-MS-MMC-010_0_0_(Tech_Manual).pdf PDF
0540_A_No1_Mooring_Capstan_Leak_Repair.doc DOC document
0104_A_Mechanically_Clean_and_Preserve_Tanks_Rev_A.docx DOCX document
0627_B_04_Lounge_Stratica_Deck_Covering_and_Removals_(VR_18-0049).doc DOC document
0507_A_DISTILLER_CLEANING_INSPECTION_AND_MAINTENANCE.doc DOC document
0517_A_Cargo_Defrost_Brine_Heater_Replacement_(VR16-0069)_Rev_A.doc DOC document
0217_A_9_CYLINDER_MAIN_DIESEL_ENGINE_30,000_HOUR_SCHEDULED_MAINTENANCE_R....docx DOCX document
0904_A_STERN_TUBE_SEAL_INSPECTION_(SW_SYS)_REV_-_(CSI).docx DOCX document
AMENDMENT_BRASHEAR_0003.doc DOC document
0216_A_8_CYLINDER_MAIN_DIESEL_ENGINE_30,000_HOUR_SCHEDULED_MAINTENANCE_R....docx DOCX document
BRASHEAR_AMENDMENT_0001.doc DOC document
BRASHEAR_AMENDMENT_0002.doc DOC document
J-4__BRASHEAR_GFP_Module_AttachmentTemplate_-_Rev_3_5_Mar_(3)_1.xlsx XLSX spreadsheet
J_-_4_CARL_BRASHEAR_MAR_2019_ROH_GFM_REPORT_10-05-18.xlsx XLSX spreadsheet
J_-_6_BRASHEAR.pdf PDF
J_-_7_MSC_Ship_Repair_Facility_Survey.docx DOCX document
J_-_2_Category_A_Items.xls XLS spreadsheet
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
J_-_3_Category_B_Items.xls XLS spreadsheet
J_-_12_Past_Performance_Data.doc DOC document
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_14_Technical_Non-Disclosure_Agreement.docx DOCX document
J_-_15_Non-Mariner_Maintenance_Contractor_Vetting_Sheet_(Rev_8_(v4)_20_Sep_2017)_(002).xlsx XLSX spreadsheet
N3220519R4260_BRASHEAR.doc DOC document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION / CONTRACT FORM

The required response date/time has changed from 27-Nov-2018 02:00 PM to 13-Dec-2018 02:00 PM.

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been added by full text:

REQUEST FOR CLARIFICATIONS #3

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0602

PARAGRAPH / SECTION NO 2.2

TITLE: ACCOMMODATION LADDER INSPECTION AND LOAD TESTING (5-YR) REV –

QUESTION:

Paragraph 7.3 directs contractor to perform reference 2.2 maintenance and testing, utilizing material provided in para 3.2.2 as required.

Please provide reference 2.2

ANSWER:

Please see attached Reference: Reference was mis-titled. (611_MSC Circ 1331 Guidelines for Embarkation.pdf)

SPECIFICATION ITEM NO.: 0910

PARAGRAPH / SECTION NO 3.1.1, 4.0, 7.0

TITLE: OVERHAUL SEA VALVES REV-

3.1.1 a. for location, says “see sea valves table on sheet 5 of reference 2.1 (for guidance only)”. 7.0 Statement of work has specific lists of valves and operators to be addressed. Paragraph 7.5 requires testing of 24” and 30” valves removed. Contractor has not removed these valves or any other valves not listed in 4.2.1, 4.2.2 and 4.2.3 and is not working any actuators other than those listed in 7.1.1, 7.1.2 & 7.1.3.

Please confirm and or provide clear direction.

ANSWER:

Government requests all valves listed in Reference 2.1 be pulled for inspection cleaning and testing. 7.1.1, 7.1.2, 7.1.3 list interferences for valves (reach Rods and Attachments). GFM is pending, at a minimum, valves are to be pulled, cleaned and report status/possibility for repair/reuse.

SPECIFICATION ITEM NO.: 0602

PARAGRAPH / SECTION NO 3.1.2. 4.0 and J-4

TITLE: T-AKE CLASS HYDRA RADIO UPGRADE (T-ALT 472)

In paragraph 3.1.2 list equipment for the XG-75 Shipset HYDRA System.

Who is supplying the equipment, in paragraph 4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None, but the manufacturers’ representatives Harris Corporation indicated that MSC will be supplying the equipment and the J-4 BRASHEAR_GFP_Module_AttachmentTemplate has the XG-75 equipment listed.

ANSWER:

GFM will not be available in time for availability. Please omit pricing for this work item; cancel work item.

(End of Summary of Changes)