0522_A_Magazine_Drain_Piping_Replacement_Rev_A.doc

DOC document 69 KB Posted

Attached to
Repair and Overhaul Dry Docking USNS CARL BRASHEAR
Solicitation number
N3220519R4260
Issued by

About this file

REVISED WI

View the file

Other files

File Type Posted
BRASHERA_AMENDMENT_0007.doc DOC document
J_-_2_Category_A_REV_002.xls XLS spreadsheet
J_-_3_REVISION_002_Category_B_Items.xls XLS spreadsheet
BRASHERA_AMENDMENT_0006.docx DOCX document
J_-_2_REVISION_Category_A_Items.xls XLS spreadsheet
611_MSC_Circ_1331Guidlines_for_Embarkation.pdf PDF
J_-_3_REVISION_Category_B_Items.xls XLS spreadsheet
BRASHEAR_AMENDMENT_0005.doc DOC document
0528_B_Food_Waste_Transfer_Pump_Overhaul.docx DOCX document
0307_B_MOTOR_CONTROL_CENTER_M05_ALTERNATE_POWER_SOURCE_(T-ALT_370).docx DOCX document
BRASHEAR_AMENDMENT_0004.doc DOC document
8391502_A.pdf PDF
8391502_-.pdf PDF
0527_B_Grey_Water_Transfer_Pump_Overhaul.docx DOCX document
0569_B__SW_Check_Valve_Clean_and_Repair_(VR18-0036-55).docx DOCX document
0105_A_DECK_HOUSE_CLEANING_AND_PAINTING_(SPOT_BLAST)_REV_A.docx DOCX document
0227_A_MDG_Attached_Lube_Oil_Pump_Rebuilds.doc DOC document
0530_A_CARGO_AND_AC_30K_HR_COMPRESSOR_REPLACEMENT_REV_A.docx DOCX document
T6225-MS-MMC-010_0_0_(Tech_Manual).pdf PDF
0540_A_No1_Mooring_Capstan_Leak_Repair.doc DOC document
0104_A_Mechanically_Clean_and_Preserve_Tanks_Rev_A.docx DOCX document
0627_B_04_Lounge_Stratica_Deck_Covering_and_Removals_(VR_18-0049).doc DOC document
0507_A_DISTILLER_CLEANING_INSPECTION_AND_MAINTENANCE.doc DOC document
0517_A_Cargo_Defrost_Brine_Heater_Replacement_(VR16-0069)_Rev_A.doc DOC document
0217_A_9_CYLINDER_MAIN_DIESEL_ENGINE_30,000_HOUR_SCHEDULED_MAINTENANCE_R....docx DOCX document
0904_A_STERN_TUBE_SEAL_INSPECTION_(SW_SYS)_REV_-_(CSI).docx DOCX document
AMENDMENT_BRASHEAR_0003.doc DOC document
0216_A_8_CYLINDER_MAIN_DIESEL_ENGINE_30,000_HOUR_SCHEDULED_MAINTENANCE_R....docx DOCX document
BRASHEAR_AMENDMENT_0001.doc DOC document
BRASHEAR_AMENDMENT_0002.doc DOC document
J-4__BRASHEAR_GFP_Module_AttachmentTemplate_-_Rev_3_5_Mar_(3)_1.xlsx XLSX spreadsheet
J_-_4_CARL_BRASHEAR_MAR_2019_ROH_GFM_REPORT_10-05-18.xlsx XLSX spreadsheet
J_-_6_BRASHEAR.pdf PDF
J_-_7_MSC_Ship_Repair_Facility_Survey.docx DOCX document
J_-_2_Category_A_Items.xls XLS spreadsheet
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
J_-_3_Category_B_Items.xls XLS spreadsheet
J_-_12_Past_Performance_Data.doc DOC document
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_14_Technical_Non-Disclosure_Agreement.docx DOCX document
J_-_15_Non-Mariner_Maintenance_Contractor_Vetting_Sheet_(Rev_8_(v4)_20_Sep_2017)_(002).xlsx XLSX spreadsheet
N3220519R4260_BRASHEAR.doc DOC document
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS CARL BRASHEAR

(TAKE 7)

AUXILIARY MACHINERY
N32205-19-R-4260
ITEM NO. 0522
CATEGORY "A"
2018-08-29
Magazine Drain Piping Replacement
MSC/N756/EO

1.0 ABSTRACT:

1.1 This work item describes the replacement of the magazine control panel drain piping.

2.0 REFERENCES:

2.1 MSC Drawing 522-8387385, Cargo Hold Sprinkling System Diagram

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity:

3.1.1 Location:

a. Magazine Cargo Hold 1 2nd Deck to 5th Deck

b. Magazine Cargo Hold 2 2nd Deck to 5th Deck

c. Magazine Cargo Hold 3 2nd Deck to 5th Deck

3.1.2 Quantity: Three (3) Magazine Cargo Hold control panel drain piping systems

3.2 Item Description/Manufacturer's Data: None

3.2.1 Bill of Materials (Contractor Furnished):

Qty
Component Name/Identity
Remarks
400 Linear feet
Pipe, 50mm (2 inch) 316 Stainless Steel
30 Each
Elbow 90 degree
100 each
Couplings
16
Flange, flat faced 50mm (2 ½ inch) 316 Stainles Steel
10 linear Feet
Rubber Channel, pipe chafing material

3.2.2 Contractor shall provide any additional items required such as fittings, welding rod, etc., which are not specifically included in References and the enclosures in order to perform installation of a fully functional system.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Government Furnished Material: Amercoat 240 Paint 30 Gallons.

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs.

5.2 The contractor and all subcontractors regardless of tier are advised to review the other work items under this contract to determine their effect on the work required under this work item.

5.3 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER AUTHORIZATION.

5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED AND PROVEN OTHERWISE. TEST ALL ELECTICAL CABLES TO ENSURE THEY ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.

6.0 Quality Assurance Requirements:

6.1 Welders must be ABS certified.

6.2 All work performed is to be IAW ABS and USCG rules. Piping, valves, fittings and all installations and modifications shall meet ABS Steel Vessel Rules and USCG requirements.

6.3 Inspections and tests shall be conducted in accordance with ABS and USCG rules/regulations and written procedures previously approved by MSC representatives.

7.0 STATEMENT OF WORK REQUIRED:

7.1 Arrangements/Outfitting:

7.1.1 Perform ship check of pipe to be removed to verify all materials are available prior to pipe removal.

7.1.2 Erect Staging to access the piping running in the overhead.

7.1.3 Provide a Marine Chemist to certify the Cargo Holds safe for hot work.

7.2 Removals:

7.2.1 Remove existing drain piping starting at the sprinkling control panels located on the 2nd through the 5th deck to terminating at the bilge well in Cargo Holds 1, 2, and 3. Reference 2.1 sheet 8, Detail 57-A

7.2.2 Retain valves, funnels, and pipe hangar U-Bolts and fasteners for reinstallation.

7.2.3 Check valves will be discarded. Check valves will not be installed in the new system piping.

7.3 Installation:

7.3.1 Install new drain piping starting at the sprinkling control panels located on the 2nd through the 5th deck terminating at the bilge well in Cargo Holds 1, 2, and 3 following the same pipe run as removed in 7.2.1, Reference 2.1 sheet 8, Detail 57-A. Pipe to transit existing bulkhead penetrations.

7.3.2 Pipe bends to be in strict adherence to ABS rules for pipe bending. Reference 2.1, General Note 52 provides ABS guidance for pipe bending.

7.3.3 Pipe penetrations of bulkheads and decks which require fire tight or smoke tight protection, the penetrations shall be made by approved methods which will maintain the same degree of fire tight or smoke tight integrity.

7.4 Painting

7.4.1 Paint all new and disturbed surfaces and new piping to match surrounding surfaces. Ships force will provide paint.

7.5 Markings: None.

7.6 Inspection/Test

7.6.1 Perform dye penetrant test of all new weld joints.

7.6.2 Perform operational test using water hose at each deck to prove accurate drainage. Satisfactory test is no back pressure/flow and zero leakage at pipe joints.

8.0 GENERAL REQUIREMENTS: None Additional.